| Owner | Filings | Most Recent |
|---|---|---|
| ETROG | 10 | 08/29/2026 |
| XYZ 1555 PACIFIC LLC | 8 | 03/22/2026 |
| XYZ 155 PACIFIC LLC | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 01/22/2025 | $1.1M | — | — → — | $512/sf building |
| 03/07/2018 | $1.3M | — | — → — | $598/sf building |
| 01/31/2017 | $500K | — | ALF OF THE HOLDERS OF THE ASSET BACKED SECURITIES → Private party | $238/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| ASR ENGINEERING PC | 3 | 07/13/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| 718 DESIGN PRO INC | General Contractor | 3 | 04/09/2026 |
| KISHAN PLUMBING INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ASR ENGINEERING PC | 8404 | 3 | 07/13/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | N AND S PLUMBING INC | 01/08/2026 |
| DOB NOW | Structural | Permit Issued | 718 DESIGN PRO INC | 12/22/2025 |
| DOB NOW | Foundation | Signed-off | 718 DESIGN PRO INC | 12/22/2025 |
| DOB NOW | Foundation | Permit Issued | 718 DESIGN PRO INC | 12/22/2025 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/13/2026 | Signed-off | KISHAN PLUMBING INC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/08/2026 | Permit Issued | JOSEPH WEINSTEIN ELECTRIC | 2 meters, 2 new_meters |
| 11/20/2025 | Permit Issued | JOSEPH WEINSTEIN ELECTRIC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/13/2026 | Signed-off | KISHAN PLUMBING INC | Steel, Wood |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/13/2026 | Fire-Resistant Penetrations and Joints | AKM RAHMAN | special |
| 07/13/2026 | Structural Stability – Alterations of existing buildings | AKM RAHMAN | special |
| 07/13/2026 | Structural Steel - Details | AKM RAHMAN | special |
| 07/13/2026 | Energy Code Compliance Inspections | AKM RAHMAN | progress |
| 07/13/2026 | Final | AKM RAHMAN | progress |
| 07/13/2026 | Fire-Resistance Rated Construction | AKM RAHMAN | progress |
| 07/13/2026 | Footing and Foundation | AKM RAHMAN | progress |
| 07/13/2026 | HVAC-R and service water piping design and insulation | AKM RAHMAN | energy_progress |
| 07/13/2026 | HVAC-R and service water heating equipment | AKM RAHMAN | energy_progress |
| 07/13/2026 | Fenestration and door U-factor and product ratings | AKM RAHMAN | energy_progress |
| 07/13/2026 | Insulation placement and R values | AKM RAHMAN | energy_progress |
| 07/13/2026 | Air barrier - visual inspection | AKM RAHMAN | energy_progress |
| 07/13/2026 | HVAC-R and service water heating system controls | AKM RAHMAN | energy_progress |
| 07/13/2026 | Interior lighting power | AKM RAHMAN | energy_progress |
| 07/13/2026 | Fenestration areas | AKM RAHMAN | energy_progress |
| 07/13/2026 | Fenestration air leakage | AKM RAHMAN | energy_progress |
| 07/13/2026 | Maintenance information | AKM RAHMAN | energy_progress |
| 07/13/2026 | Permanent certificate | AKM RAHMAN | energy_progress |
| 11/09/2025 | Fire-Resistant Penetrations and Joints | AKM RAHMAN | special |
| 11/09/2025 | Energy Code Compliance Inspections | AKM RAHMAN | progress |
| 11/09/2025 | HVAC-R and service water heating equipment | AKM RAHMAN | energy_progress |
| 11/09/2025 | HVAC-R and service water heating system controls | AKM RAHMAN | energy_progress |
| 11/09/2025 | HVAC-R and service water piping design and insulation | AKM RAHMAN | energy_progress |
| 11/09/2025 | Maintenance information | AKM RAHMAN | energy_progress |