| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/12/2024 | Complete | SUNRUN SOLAR ELECTL CORP | — |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 12/02/2021 | $500K | — | — → — | $521/sf building |
| 09/20/2018 | $375K | — | Private party → Private party | $391/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| PARKER AND WEST ENGINEERING, PLLC | 1 | 07/29/2024 |
| BUILDING ENGINEERING SYSTEMS PLLC | 5 | 09/07/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| SUNRUN | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SUNRUN INSTALLATION SVC | General Contractor | 2 | 03/21/2026 |
| PETERKIN CONSTRUCTION LLC | General Contractor | 1 | 07/08/2026 |
| GLENNS PLUMBING SVCS INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| PARKER AND WEST ENGINEERI | 5272 | 1 | 07/29/2024 |
| ALL STATE PROPERTY INSPEC | 4288 | 5 | 09/07/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | SUNRUN INSTALLATION SVC | 08/13/2024 |
| DOB NOW | Plumbing | Signed-off | GLENNS PLUMBING SVCS INC | 12/08/2022 |
| DOB NOW | General Construction | Signed-off | PETERKIN CONSTRUCTION LLC | 09/13/2022 |
| Date | Type | Result | Report |
|---|---|---|---|
| 11/15/2023 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 11/03/2023 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 12/15/2022 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 12/15/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/15/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 12/13/2022 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/03/2024 | Fire-Resistant Penetrations and Joints | Walid Abdulla | special |
| 07/03/2024 | Structural Stability – Alterations of existing buildings | Walid Abdulla | special |
| 07/03/2024 | Energy Code Compliance Inspections | Walid Abdulla | progress |
| 07/03/2024 | Final | Walid Abdulla | progress |
| 07/03/2024 | Air barrier - visual inspection | Walid Abdulla | energy_progress |
| 09/07/2023 | Fire-Resistant Penetrations and Joints | SEBERT DYER | special |
| 09/07/2023 | Energy Code Compliance Inspections | SEBERT DYER | progress |
| 09/07/2023 | Final | SEBERT DYER | progress |
| 09/07/2023 | Fire-Resistance Rated Construction | SEBERT DYER | progress |
| 09/07/2023 | Fenestration air leakage | SEBERT DYER | energy_progress |
| 09/07/2023 | Fenestration areas | SEBERT DYER | energy_progress |
| 09/07/2023 | Air barrier - visual inspection | SEBERT DYER | energy_progress |
| 09/07/2023 | Fenestration and door U-factor and product ratings | SEBERT DYER | energy_progress |
| 02/01/2023 | Fire-Resistant Penetrations and Joints | SEBERT DYER | special |
| 02/01/2023 | Energy Code Compliance Inspections | SEBERT DYER | progress |
| 02/01/2023 | Final | SEBERT DYER | progress |
| 02/01/2023 | Fire-Resistance Rated Construction | SEBERT DYER | progress |
| 02/01/2023 | Fenestration and door U-factor and product ratings | SEBERT DYER | energy_progress |
| 02/01/2023 | Fenestration air leakage | SEBERT DYER | energy_progress |
| 02/01/2023 | Air barrier - visual inspection | SEBERT DYER | energy_progress |
| 02/01/2023 | Fenestration areas | SEBERT DYER | energy_progress |
| 02/01/2023 | Fire-Resistant Penetrations and Joints | SEBERT DYER | special |