| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 05/07/2026 | Signed-off | CS RENOVATION INC | Air Conditioning Systems, Ventilation Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/07/2026 | Signed-off | TRI STATE PLBG & HTG INC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/08/2026 | Complete | ACCORD POWER ELECTRIC LLC | — |
| 12/05/2025 | Complete | GOODALL ELECTRIC CORP | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/07/2026 | Signed-off | CS RENOVATION INC | Wood |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/03/2026 | Signed-off | ACCORD POWER INC | 10 panels, 4.4 kw, 1,717.83 roof_area_sqft |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 11/06/2024 | $1.3M | — | PROMILA LLC → WX&YY LLC | $589/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| SYNERGIC DESIGN ARCHITECTS | 1 | 06/03/2026 |
| POLAR ENGINEERING, P.C. | 8 | 05/07/2026 |
| NIC 88 CORP | 1 | 02/04/2025 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CS RENOVATION INC | General Contractor | 7 | 04/09/2026 |
| TRI STATE PLBG & HTG INC | Plumbing | 2 | 07/08/2026 |
| ACCORD POWER INC | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SYNERGIC DESIGN LLC | 8561 | 1 | 06/03/2026 |
| WELLDONE INSPECTION INC. | 8628 | 8 | 05/07/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | ACCORD POWER INC | 06/08/2026 |
| DOB NOW | General Construction | Signed-off | CS RENOVATION INC | 02/11/2026 |
| DOB NOW | Mechanical Systems | Signed-off | CS RENOVATION INC | 11/30/2025 |
| DOB NOW | Plumbing | Signed-off | DW PLUMBING INC | 11/06/2025 |
| DOB NOW | Structural | Permit Issued | CS RENOVATION INC | 06/04/2025 |
| DOB NOW | Plumbing | Signed-off | DW PLUMBING INC | 02/25/2025 |
| DOB NOW | Structural | Permit Issued | CS RENOVATION INC | 02/10/2025 |
| DOB NOW | Construction Fence | Signed-off | CS RENOVATION INC | 02/10/2025 |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/31/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 11/18/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/05/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/09/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 10/02/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/02/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/23/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 05/23/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/12/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/03/2026 | Air barrier - visual inspection | Malathi Ananthakrishnan | energy_progress |
| 06/03/2026 | Final | Malathi Ananthakrishnan | progress |
| 06/03/2026 | Energy Code Compliance Inspections | Malathi Ananthakrishnan | progress |
| 06/03/2026 | Structural Stability – Alterations of existing buildings | Malathi Ananthakrishnan | special |
| 06/03/2026 | Fire-Resistant Penetrations and Joints | Malathi Ananthakrishnan | special |
| 05/26/2026 | Energy Code Compliance Inspections | QIUFAN JIANG | progress |
| 05/26/2026 | Fenestration areas | QIUFAN JIANG | energy_progress |
| 05/26/2026 | Insulation placement and R values | QIUFAN JIANG | energy_progress |
| 05/26/2026 | Interior lighting power | QIUFAN JIANG | energy_progress |
| 05/26/2026 | Maintenance information | QIUFAN JIANG | energy_progress |
| 05/26/2026 | Structural Stability – Alterations of existing buildings | QIUFAN JIANG | special |
| 05/26/2026 | Fenestration air leakage | QIUFAN JIANG | energy_progress |
| 05/26/2026 | Air barrier - visual inspection | QIUFAN JIANG | energy_progress |
| 05/26/2026 | Fenestration and door U-factor and product ratings | QIUFAN JIANG | energy_progress |
| 05/26/2026 | Metering | QIUFAN JIANG | energy_progress |
| 05/26/2026 | Electric vehicle service equipment requirements | QIUFAN JIANG | energy_progress |
| 05/26/2026 | Permanent certificate | QIUFAN JIANG | energy_progress |
| 05/26/2026 | Wood – Prefabricated I-Joists | QIUFAN JIANG | special |
| 05/26/2026 | Fire-Resistant Penetrations and Joints | QIUFAN JIANG | special |
| 05/26/2026 | Fire-Resistance Rated Construction | QIUFAN JIANG | progress |
| 05/26/2026 | Final | QIUFAN JIANG | progress |
| 04/30/2026 | Maintenance information | QIUFAN JIANG | energy_progress |
| 04/30/2026 | Fire-Resistant Penetrations and Joints | QIUFAN JIANG | special |
| 04/30/2026 | Structural Stability – Alterations of existing buildings | QIUFAN JIANG | special |
| 04/30/2026 | Wood – Prefabricated I-Joists | QIUFAN JIANG | special |