| Owner | Filings | Most Recent |
|---|---|---|
| CITYWIDE BUILDERS NY | 1 | 03/22/2026 |
| BY CONSTRUCTION CORP | 13 | 03/22/2026 |
| 157 RUTLEDGE ST | 5 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 05/09/2018 | $990K | — | Private party → Private party | $220/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| CHOSEN MEP, CORP. | 7 | 11/08/2023 |
| FL&M ENGINEERING DESIGN &INSPECTION | 1 | 01/18/2021 |
| JIM KUSI PE | 1 | 10/22/2020 |
| BGM ENGINEERING | 1 | 06/04/2020 |
| BAOBAB ARCHITECTS P.C. | 1 | 02/25/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| ADVANCED BUILDERS SERVICES | 7 | 03/21/2026 |
| ALLSTATE EXPEDITERS | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| B Y CONSTRUCTION CORP | General Contractor | 8 | 07/08/2026 |
| ZONE PLUMBING & HEATING C | Plumbing | 6 | 08/26/2026 |
| CITYWIDE BUILDERS NY INC | General Contractor | 6 | 03/21/2026 |
| VILLAGE P H NY | Plumbing | 3 | 03/22/2026 |
| BLZ ELECTRIC INC 001756 | General Contractor | 2 | 03/22/2026 |
| PRIME PIPING & HEATING IN | Fire Protection | 1 | 07/08/2026 |
| COSTA ARCH + ENG LLP | Electrical | 1 | 03/21/2026 |
| MANHATTAN D ENTERPRISES | General Contractor | 1 | 07/08/2026 |
| VILLAGE P & H NY INC | Fire Protection | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ENGINEERING CONSULTING SE | 2050 | 8 | 11/08/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | ZONE PLUMBING & HEATING C | 12/13/2023 |
| DOB NOW | Plumbing | Signed-off | VILLAGE P & H NY INC | 09/14/2023 |
| DOB NOW | Construction Fence | Signed-off | CITYWIDE BUILDERS NY INC | 08/09/2022 |
| DOB NOW | Construction Fence | Signed-off | CITYWIDE BUILDERS NY INC | 03/23/2022 |
| DOB NOW | Plumbing | Signed-off | A M B MECHANICAL INC | 06/18/2021 |
| DOB NOW | Sprinklers | Permit Issued | ZORIA HOUSING, LLC | 02/10/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | MANHATTAN D ENTERPRISES | 01/19/2021 |
| DOB NOW | Construction Fence | Signed-off | B Y CONSTRUCTION CORP | 10/26/2020 |
| DOB NOW | Mechanical Systems | Permit Issued | B Y CONSTRUCTION CORP | 09/24/2020 |
| DOB NOW | Structural | Permit Issued | B Y CONSTRUCTION CORP | 09/24/2020 |
| DOB NOW | Curb Cut | Permit Issued | B Y CONSTRUCTION CORP | 09/23/2020 |
| BIS | — | ISSUED | CITYWIDE BUILDERS NY INC | 06/22/2022 |
| BIS | — | ISSUED | CITYWIDE BUILDERS NY INC | 03/11/2022 |
| BIS | — | ISSUED | B Y CONSTRUCTION CORP | 09/30/2020 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/08/2023 | Signed-off | PARAMOUNT SERVICES, LLC | 108 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/08/2023 | Permit Issued | ZONE PLUMBING & HEATING C | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/11/2021 | Complete | BLZ ELECTRIC INC. | General Wiring |
| 01/06/2021 | Complete | V. VASS ELECTRIC CORP | — |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/15/2023 | Sprinkler Systems | PAUL MARINO | special |
| 11/15/2023 | Maintenance information | PAUL MARINO | energy_progress |
| 10/26/2023 | Maintenance information | PAUL MARINO | energy_progress |
| 10/26/2023 | Sprinkler Systems | PAUL MARINO | special |
| 06/09/2023 | Maintenance information | PAUL MARINO | energy_progress |
| 06/09/2023 | Sprinkler Systems | PAUL MARINO | special |
| 08/25/2021 | Sprinkler Systems | PAUL MARINO | special |
| 08/25/2021 | Maintenance information | PAUL MARINO | energy_progress |
| 05/20/2021 | Maintenance information | PAUL MARINO | energy_progress |
| 05/20/2021 | Sprinkler Systems | PAUL MARINO | special |
| 01/05/2021 | Final | FADY HABEEL | progress |