| Owner | Filings | Most Recent |
|---|---|---|
| HI TOWER CONTRACTORS | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 04/14/2016 | $3.1M | — | — → — | $170/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| SHARON ENGINEERING, P.C | 6 | 04/02/2025 |
| PAUL PERDEK, PROF. ENG. PLLC | 4 | 08/23/2021 |
| YORK TOWER CONSULTING ENGINEERING | 1 | 08/14/2020 |
| BRICOLAGE DESIGNS | 1 | 06/23/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| AE DESIGN SOLUTION | 8 | 03/21/2026 |
| CITY EXPEDITING | 8 | 03/21/2026 |
| BRICOLAGE DESIGNS | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| HYDRO TECH MECHANICAL CORP | Plumbing | 23 | 07/08/2026 |
| POWERS BRIDGING & SCAFFOLDING | General Contractor | 6 | 07/08/2026 |
| CONGREGATION YESHIVA BNEI | General Contractor | 6 | 07/08/2026 |
| SAFETY FIRE SPRINKLER CORP | Fire Protection | 2 | 07/08/2026 |
| HI-TOWER CONTRACTORS INC | General Contractor | 1 | 07/08/2026 |
| BEKKERMAN, MIKHAIL | Electrical | 1 | 03/21/2026 |
| SAFETY FIRE SPRINKLER COR | Plumbing | 1 | 03/22/2026 |
| LEIBY FISCHER | Electrical | 1 | 03/21/2026 |
| MP & L METAL INC | Electrical | 1 | 03/21/2026 |
| AIRMARK HVAC, LLC | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HRF SERVICES CORP | 5616 | 7 | 04/02/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sprinklers | Permit Issued | SAFETY FIRE SPRINKLER CORP | 02/18/2026 |
| DOB NOW | Plumbing | Permit Issued | HYDRO TECH MECHANICAL CORP | 01/22/2024 |
| DOB NOW | Construction Fence | Signed-off | CONGREGATION YESHIVA BNEI | 06/22/2022 |
| DOB NOW | Mechanical Systems | Signed-off | AIRMARK HVAC, LLC | 05/13/2022 |
| DOB NOW | Supported Scaffold | Signed-off | POWERS BRIDGING & SCAFFOL | 05/10/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | POWERS BRIDGING & SCAFFOL | 04/13/2022 |
| DOB NOW | Structural | Signed-off | CONGREGATION YESHIVA BNEI | 04/04/2022 |
| DOB NOW | Construction Fence | Signed-off | CONGREGATION YESHIVA BNEI | 01/09/2022 |
| DOB NOW | Sprinklers | Permit Issued | SAFETY FIRE SPRINKLER CORP | 08/12/2021 |
| DOB NOW | Plumbing | Permit Issued | HYDRO TECH MECHANICAL CORP | 07/27/2021 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | POWERS BRIDGING & SCAFFOL | 06/17/2021 |
| DOB NOW | Supported Scaffold | Signed-off | POWERS BRIDGING & SCAFFOL | 05/06/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | POWERS BRIDGING & SCAFFOL | 04/16/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | POWERS BRIDGING & SCAFFOL | 01/21/2021 |
| DOB NOW | Construction Fence | Signed-off | CONGREGATION YESHIVA BNEI | 01/06/2021 |
| DOB NOW | Construction Fence | Signed-off | HI-TOWER CONTRACTORS INC | 08/04/2020 |
| BIS | — | ISSUED | CONGREGATION YESHIVA BNEI | 09/11/2024 |
| BIS | — | ISSUED | CONGREGATION YESHIVA BNEI | 06/22/2022 |
| BIS | OT | ISSUED | HI-TOWER CONTRACTORS INC | 01/07/2022 |
| BIS | — | ISSUED | CONGREGATION YESHIVA BNEI | 01/06/2022 |
| BIS | — | ISSUED | CONGREGATION YESHIVA BNEI | 01/27/2021 |
| BIS | OT | ISSUED | HI-TOWER CONTRACTORS INC | 06/24/2020 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 02/27/2025 | Signed-off | AIRMARK HVAC, LLC | Heating and Air Conditioning Systems, Ventilation Systems | Heat / Cool Mitsubishi Electric TURYP1683AN40AN 168,000 BTU · Vrf Outdoor ×16 TURYP1203AN40AN 120,000 BTU · Vrf Outdoor ×5 TUMYP0481AN40AN 48,000 BTU · Vrf Outdoor ×4 Ventilation Greenheck ERVe-55-30L 4,790 CFM · Erv ×5 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/20/2025 | Permit Issued | SAFETY FIRE SPRINKLER COR | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/02/2025 | Permit Issued | HYDRO TECH MECHANICAL COR | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/24/2022 | Permit Issued | SHTRAL ELECT'L CONT'G COR | General Wiring |
| 09/17/2021 | Complete | STAR ELEC'L CONTRACTORS C | — |
| 06/07/2021 | Permit Issued | SHTRAL ELECT'L CONT'G COR | — |
| 01/12/2021 | Complete | OPTIMAL ELECTRIC, INC | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/19/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/20/2026 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 05/15/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 03/31/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/23/2026 | Fail-Final PL - More than 10 Requested Floors | Fail | View ↗ |
| 02/16/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 01/10/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 01/10/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/08/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/19/2024 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 03/30/2022 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 02/04/2022 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 01/20/2022 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/04/2025 | HVAC and service water heating equipment | FAHAD FATEH | energy_progress |
| 04/04/2025 | Energy Code Compliance Inspections | FAHAD FATEH | progress |
| 04/04/2025 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 04/04/2025 | HVAC and service water heating system controls | FAHAD FATEH | energy_progress |
| 04/04/2025 | Maintenance information | — | energy_progress |
| 04/04/2025 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 04/04/2025 | Post-installed Anchors | — | special |
| 03/27/2025 | Seismic Isolation Systems | FAHAD FATEH | special |
| 03/27/2025 | Post-installed Anchors | FAHAD FATEH | special |
| 03/27/2025 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 03/27/2025 | Sprinkler Systems | FAHAD FATEH | special |
| 03/19/2025 | Sprinkler Systems | FAHAD FATEH | special |
| 03/19/2025 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 03/19/2025 | Post-installed Anchors | FAHAD FATEH | special |
| 03/19/2025 | Seismic Isolation Systems | FAHAD FATEH | special |
| 02/12/2025 | Post-installed Anchors | — | special |
| 02/12/2025 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 02/12/2025 | Maintenance information | — | energy_progress |
| 02/29/2024 | Energy Code Compliance Inspections | FAHAD FATEH | progress |
| 02/29/2024 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 02/29/2024 | HVAC and service water heating system controls | FAHAD FATEH | energy_progress |
| 02/29/2024 | HVAC and service water heating equipment | FAHAD FATEH | energy_progress |