← Back
Parochial school, yeshiva
Congregation Yeshiva Bnei Torah
1571 55 STREET · Borough Park · BIN 3130451
💬 Discuss this project
1920Year Built
7Stories
W2Building Class
R6Zoning
18,286 sfGross Floor Area
1Units
3 Open Violations ▸FDNY Report ↗
Parochial school, yeshiva · Owner of record: CONGREGATION YESHIVA BNEI TORAH INC. · 4,800 sf lot · 3.81 FAR built · Flood zone X
Locations of Work
StructuralMechanicalPlumbingFire Protection
Permit Issued — active, not yet Signed-off
RoofUnder Construction22p · 4 filings · 20 docs
Bulkhead1p · 1 filing · 4 docs
Floor 7Under Construction24p · 4 filings · 20 docs
Floor 6Under Construction22p · 4 filings · 20 docs
Floor 5Under Construction24p · 4 filings · 20 docs
Floor 4Under Construction22p · 4 filings · 20 docs
Floor 3Under Construction23p · 4 filings · 20 docs
Floor 2Under Construction21p · 4 filings · 20 docs
Floor 1Under Construction23p · 4 filings · 20 docs
CellarUnder Construction23p · 3 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
HI TOWER CONTRACTORS103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
04/14/2016$3.1M—— → —$170/sf building
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
AE DESIGN SOLUTION803/21/2026
CITY EXPEDITING803/21/2026
BRICOLAGE DESIGNS403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
HYDRO TECH MECHANICAL CORPPlumbing2307/08/2026
POWERS BRIDGING & SCAFFOLDINGGeneral Contractor607/08/2026
CONGREGATION YESHIVA BNEIGeneral Contractor607/08/2026
SAFETY FIRE SPRINKLER CORPFire Protection207/08/2026
HI-TOWER CONTRACTORS INCGeneral Contractor107/08/2026
BEKKERMAN, MIKHAILElectrical103/21/2026
SAFETY FIRE SPRINKLER CORPlumbing103/22/2026
LEIBY FISCHERElectrical103/21/2026
MP & L METAL INCElectrical103/21/2026
AIRMARK HVAC, LLCGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HRF SERVICES CORP5616704/02/2025
Building Lifecycle
All (84)Filed (12)Permit Issued (16)Signed Off (6)Violation (15)Inspection (13)Special Inspection (22)
08/19/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
07/27/2026
Signed off — Alteration
Install mechanical units and related piping as shown on drawings filed herewith
B00339246-I1
05/20/2026
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
05/15/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
03/31/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
03/23/2026
Inspection — Fail-Final PL - More than 10 Requested Floors
Fail
View inspection ↗
02/18/2026
Permit issued — Sprinklers
B00339227-I1-EW-SP
02/16/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
04/04/2025
Special inspection requirement — HVAC and service water heating equipment
FAHAD FATEH
04/04/2025
Special inspection requirement — Energy Code Compliance Inspections
FAHAD FATEH
04/04/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
04/04/2025
Special inspection requirement — HVAC and service water heating system controls
FAHAD FATEH
04/04/2025
Special inspection requirement — Maintenance information
04/04/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
04/04/2025
Special inspection requirement — Post-installed Anchors
04/02/2025
Filed — Alteration
Install plumbing fixtures and related piping as shown on drawings filed herewith.
B00339259-P2
03/27/2025
Special inspection requirement — Seismic Isolation Systems
FAHAD FATEH
03/27/2025
Special inspection requirement — Post-installed Anchors
FAHAD FATEH
03/27/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
03/27/2025
Special inspection requirement — Sprinkler Systems
FAHAD FATEH
03/20/2025
Filed — Alteration
install new sprinkler heads and related piping as shown on drawings filed herewith.
B00339227-P1
03/19/2025
Special inspection requirement — Sprinkler Systems
FAHAD FATEH
03/19/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
03/19/2025
Special inspection requirement — Post-installed Anchors
FAHAD FATEH
03/19/2025
Special inspection requirement — Seismic Isolation Systems
FAHAD FATEH
02/27/2025
Filed — Alteration
Install mechanical units and related piping as shown on drawings filed herewith
B00339246-P1
02/12/2025
Special inspection requirement — Post-installed Anchors
02/12/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
02/12/2025
Special inspection requirement — Maintenance information
01/10/2025
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
01/10/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
01/08/2025
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
01/01/2025
Signed off — Alteration
B00445592-I1
12/18/2024
Signed off — Alteration
B00361583-I1
09/23/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
03/19/2024
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
02/29/2024
Special inspection requirement — Energy Code Compliance Inspections
FAHAD FATEH
02/29/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
02/29/2024
Special inspection requirement — HVAC and service water heating system controls
FAHAD FATEH
02/29/2024
Special inspection requirement — HVAC and service water heating equipment
FAHAD FATEH
01/22/2024
Permit issued — Plumbing
B00339259-I1-PL
05/04/2023
Signed off — Alteration
B00539694-I1
05/04/2023
Signed off — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
B00457724-I1
04/25/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
08/02/2022
Signed off — Alteration
B00339263-I1
06/22/2022
Permit issued — Construction Fence
B00361583-I1-FN
05/13/2022
Permit issued — Mechanical Systems
B00339246-I1-MS
05/10/2022
Permit issued — Supported Scaffold
B00457724-I1-SF
04/13/2022
Permit issued — Sidewalk Shed
B00445592-I1-SH
04/04/2022
Permit issued — Structural
B00339263-I1-ST
03/30/2022
Inspection — Certified Storm Drainage-ST-Piping-Roughing
Certified
View inspection ↗
02/04/2022
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
01/20/2022
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
01/09/2022
Permit issued — Construction Fence
B00361583-I1-FN
08/23/2021
Filed — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
B00457724-P1
08/12/2021
Permit issued — Sprinklers
B00339227-I1-EW-SP
08/11/2021
Violation issued (ECB, closed)
Construction
08/11/2021
Violation issued (ECB, closed)
Construction
07/27/2021
Permit issued — Plumbing
B00339259-I1-PL
Latest 60 of 84 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSprinklersPermit IssuedSAFETY FIRE SPRINKLER CORP02/18/2026
DOB NOWPlumbingPermit IssuedHYDRO TECH MECHANICAL CORP01/22/2024
DOB NOWConstruction FenceSigned-offCONGREGATION YESHIVA BNEI06/22/2022
DOB NOWMechanical SystemsSigned-offAIRMARK HVAC, LLC05/13/2022
DOB NOWSupported ScaffoldSigned-offPOWERS BRIDGING & SCAFFOL05/10/2022
DOB NOWSidewalk ShedSigned-offPOWERS BRIDGING & SCAFFOL04/13/2022
DOB NOWStructuralSigned-offCONGREGATION YESHIVA BNEI04/04/2022
DOB NOWConstruction FenceSigned-offCONGREGATION YESHIVA BNEI01/09/2022
DOB NOWSprinklersPermit IssuedSAFETY FIRE SPRINKLER CORP08/12/2021
DOB NOWPlumbingPermit IssuedHYDRO TECH MECHANICAL CORP07/27/2021
DOB NOWProtection and Mechanical MethodsSigned-offPOWERS BRIDGING & SCAFFOL06/17/2021
DOB NOWSupported ScaffoldSigned-offPOWERS BRIDGING & SCAFFOL05/06/2021
DOB NOWSidewalk ShedSigned-offPOWERS BRIDGING & SCAFFOL04/16/2021
DOB NOWSidewalk ShedSigned-offPOWERS BRIDGING & SCAFFOL01/21/2021
DOB NOWConstruction FenceSigned-offCONGREGATION YESHIVA BNEI01/06/2021
DOB NOWConstruction FenceSigned-offHI-TOWER CONTRACTORS INC08/04/2020
BIS—ISSUEDCONGREGATION YESHIVA BNEI09/11/2024
BIS—ISSUEDCONGREGATION YESHIVA BNEI06/22/2022
BISOTISSUEDHI-TOWER CONTRACTORS INC01/07/2022
BIS—ISSUEDCONGREGATION YESHIVA BNEI01/06/2022
BIS—ISSUEDCONGREGATION YESHIVA BNEI01/27/2021
BISOTISSUEDHI-TOWER CONTRACTORS INC06/24/2020
1 project · most recent 02/27/2025
Heating and Air Conditioning Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
02/27/2025Signed-offAIRMARK HVAC, LLCHeating and Air Conditioning Systems, Ventilation Systems
Heat / Cool
Mitsubishi Electric TURYP1683AN40AN 168,000 BTU · Vrf Outdoor ×16
TURYP1203AN40AN 120,000 BTU · Vrf Outdoor ×5
TUMYP0481AN40AN 48,000 BTU · Vrf Outdoor ×4
Ventilation
Greenheck ERVe-55-30L 4,790 CFM · Erv ×5
1 project · most recent 03/20/2025
FiledStatusContractorScope
03/20/2025Permit IssuedSAFETY FIRE SPRINKLER COR—
1 project · most recent 04/02/2025
Gas Storm Water/Sanitary
FiledStatusContractorScope
04/02/2025Permit IssuedHYDRO TECH MECHANICAL CORGas, Storm, Water/Sanitary
4 projects · most recent 10/24/2022
General Wiring
FiledStatusContractorScope
10/24/2022Permit IssuedSHTRAL ELECT'L CONT'G CORGeneral Wiring
09/17/2021CompleteSTAR ELEC'L CONTRACTORS C—
06/07/2021Permit IssuedSHTRAL ELECT'L CONT'G COR—
01/12/2021CompleteOPTIMAL ELECTRIC, INC—
▾Field Inspections (DOB CAP) — 13
DateTypeResultReport
08/19/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/20/2026Fail-Final PL - Up to 3 Requested FloorsFailView ↗
05/15/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
03/31/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
03/23/2026Fail-Final PL - More than 10 Requested FloorsFailView ↗
02/16/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
01/10/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
01/10/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/08/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
03/19/2024Fail-Final General Construction Non-Directive 14FailView ↗
03/30/2022Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
02/04/2022Pass-Final PL - Up to 9 Requested FloorsPassView ↗
01/20/2022Pass-Final PL - Up to 9 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 22
DateRequirementInspectorRole
04/04/2025HVAC and service water heating equipment FAHAD FATEHenergy_progress
04/04/2025Energy Code Compliance InspectionsFAHAD FATEHprogress
04/04/2025HVAC-R and service water piping design and insulation—energy_progress
04/04/2025HVAC and service water heating system controls FAHAD FATEHenergy_progress
04/04/2025Maintenance information—energy_progress
04/04/2025Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
04/04/2025Post-installed Anchors—special
03/27/2025Seismic Isolation SystemsFAHAD FATEHspecial
03/27/2025Post-installed AnchorsFAHAD FATEHspecial
03/27/2025Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
03/27/2025Sprinkler SystemsFAHAD FATEHspecial
03/19/2025Sprinkler SystemsFAHAD FATEHspecial
03/19/2025Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
03/19/2025Post-installed AnchorsFAHAD FATEHspecial
03/19/2025Seismic Isolation SystemsFAHAD FATEHspecial
02/12/2025Post-installed Anchors—special
02/12/2025HVAC-R and service water piping design and insulation—energy_progress
02/12/2025Maintenance information—energy_progress
02/29/2024Energy Code Compliance InspectionsFAHAD FATEHprogress
02/29/2024Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
02/29/2024HVAC and service water heating system controls FAHAD FATEHenergy_progress
02/29/2024HVAC and service water heating equipment FAHAD FATEHenergy_progress
▾Documents — 166 on file (BIS + DOB NOW)
▸Plans & Drawings12
▸DOB NOWPlans/Sketch - Supported Scaffold2
09/01/2026B00457724-I1Request digital key ↗
08/15/2026B00457724-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Mechanical Systems2
09/01/2026B00339246-I1Request digital key ↗
09/01/2026B00339246-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Sprinkler2
08/22/2026B00339227-I1Request digital key ↗
08/22/2026B00339227-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing2
08/22/2026B00339259-P2Request digital key ↗
08/22/2026B00339259-I1Request digital key ↗
▸DOB NOWPlans/Sketch1
09/01/2026B00539694-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Construction Fence1
09/02/2026B00361583-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sidewalk Shed1
09/01/2026B00445592-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Structural1
09/02/2026B00339263-I1Request digital key ↗
▸Applications & Permits17
▸BISPLAN / WORK APPROVAL APPLICATION11
04/24/2025302180789Open ↗
04/08/2025300241995Open ↗
01/07/2025302180789Open ↗
Showing 3 of 11 on file for this type
▸BISWORK PERMIT APPLICATION5
09/13/2024322041973Open ↗
09/13/2024322041973Open ↗
01/27/2021322041973Open ↗
Showing 3 of 5 on file for this type
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
06/21/2022322041973Open ↗
▸Zoning, Tax Lot & Property Records5
▸BISZONING EXHIBIT III:DESC. & OWNRSHP.STMNT1
03/26/2020322041973Open ↗
▸BISVERIFY TAX LOT1
07/28/2022322041973Open ↗
▸BISCO OBJ: VERIFY ADDRESS-TOPO STAMP1
07/28/2022322041973Open ↗
▸BISZONING DIAGRAM1
04/17/2020322041973Open ↗
▸BISZONING EXHIBIT I: CERTIFICATION1
03/26/2020322041973Open ↗
▸Seals & Professional Certifications26
▸DOB NOWDPL-1: Design Professional Seal & Signature12
09/02/2026B00361583-I1Open ↗
09/01/2026B00445592-I1Open ↗
09/01/2026B00457724-I1Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature6
08/28/2026B00339259-I1Open ↗
08/28/2026B00339227-I1Open ↗
08/28/2026B00339227-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWProgress Inspector Seal & Signature4
08/28/2026B00339259-I1Open ↗
08/28/2026B00339259-I1Open ↗
08/25/2026B00339259-P2Open ↗
Showing 3 of 4 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
06/17/2020340736332Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
06/17/2020340736332Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION1
02/21/2020322041973Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
06/17/2020340736332Open ↗
▸Safety & Tenant Protection4
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM1
03/26/2020322041973Open ↗
▸BISSTREET TREES: RECEIPT OF STREET TREES SITE PLAN1
01/27/2021322041973Open ↗
▸BISSTREET TREE CHECKLIST1
03/26/2020322041973Open ↗
▸BISSTREET TREE SIGNOFF1
10/03/2022322041973Open ↗
▸Environmental & Asbestos9
▸DOB NOWDEP ACP-5: Asbestos Assessment Report7
08/13/2026B00339246-I1Open ↗
08/13/2026B00339227-P1Open ↗
08/13/2026B00339259-I1Open ↗
Showing 3 of 7 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)2
06/17/2020340736332Open ↗
03/26/2020322041973Open ↗
▸Energy Compliance19
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY5
02/07/2022340736332Open ↗
01/27/2021322041973Open ↗
01/20/2021322041973Open ↗
Showing 3 of 5 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS (EN2)2
12/18/2024322041973Open ↗
02/07/2022340736332Open ↗
▸BISAIR SEALING AND INSULATION - VISUAL1
08/01/2024322041973Open ↗
▸BISINTERIOR LIGHTING POWER1
08/01/2024322041973Open ↗
▸BISFENESTRATION U-FACTOR & PRODUCT RATING1
08/01/2024322041973Open ↗
▸BISFENESTRATION AREAS1
08/01/2024322041973Open ↗
▸BISINSULATION PLACEMENT & R VALUES1
08/01/2024322041973Open ↗
▸BISENERGY CODE COMPLIANCE INSPECTIONS1
08/01/2024322041973Open ↗
▸BISLIGHTING CONTROLS1
08/01/2024322041973Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
02/21/2020322041973Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
06/17/2020340736332Open ↗
▸BISFENESTRATION AIR LEAKAGE1
08/01/2024322041973Open ↗
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026B00339246-I1Open ↗
▸DOB NOWPreliminary Commissioning Report Certification1
09/01/2026B00339246-I1Open ↗
▸Inspections & Test Reports29
▸BISTECHNICAL REPORT: RESPONSIBILITY11
02/07/2022340736332Open ↗
02/07/2022340736332Open ↗
02/07/2022340736332Open ↗
Showing 3 of 11 on file for this type
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER3
09/16/2022322041973Open ↗
01/20/2021322041973Open ↗
06/17/2020340736332Open ↗
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX3
01/27/2021322041973Open ↗
01/20/2021322041973Open ↗
06/17/2020340736332Open ↗
▸BISSUBSURFACE / SOILS INVESTIGATION (BORINGS/TEST PITS)1
06/17/2020340736332Open ↗
▸BISTR3: CONCRETE DESIGN MIX TECHNICAL REPORT1
06/18/2020340736332Open ↗
▸BISSTRUCTURAL STABILITY - ALTERATIONS OF EXISTING BUILDINGS1
08/01/2024322041973Open ↗
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)1
08/01/2024322041973Open ↗
▸BISFIRE-RESISTIVE RATED CONSTRUCTION1
08/01/2024322041973Open ↗
▸BISFOOTING AND FOUNDATION INSPECTION1
08/01/2024322041973Open ↗
▸BISMASONRY1
08/01/2024322041973Open ↗
▸BISDIR-14 ID OF RESPONSIBILITY (TR1)1
06/18/2020340736332Open ↗
▸BISSUBGRADE INSP / SOILS-SITE PREP1
08/01/2024322041973Open ↗
▸BISSOIL REPORT1
06/17/2020340736332Open ↗
▸BISTECHNICAL REPORT: SOIL INSPECTION1
04/17/2020322041973Open ↗
▸BISTR2: CONCRETE FIELD TESTING TECHNICAL REPORT1
06/18/2020340736332Open ↗
▸Approvals, Objections & Sign-offs23
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter12
09/02/2026B00361583-I1Open ↗
09/01/2026B00445592-I1Open ↗
09/01/2026B00457724-I1Open ↗
Showing 3 of 12 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE8
09/09/2020322041973Open ↗
08/11/2020322041973Open ↗
04/13/2020322041973Open ↗
Showing 3 of 8 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
02/08/2022340736332Open ↗
▸BISFINAL1
06/18/2020340736332Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION1
09/13/2024322041973Open ↗
▸Cost, Insurance & Ownership5
▸BISCOST AFFIDAVIT3
02/07/2022340736332Open ↗
06/17/2020340736332Open ↗
02/21/2020322041973Open ↗
▸BISCOST AFFIDAVIT (FINAL): PW31
08/02/2022322041973Open ↗
▸BISPROJECT-SPECIFIC GL INSURANCE1
01/27/2021322041973Open ↗
▸Filing & Intake Forms12
▸BISBOROUGH INTAKE FORM6
04/13/2020322041973Open ↗
04/09/2020322041973Open ↗
04/06/2020322041973Open ↗
Showing 3 of 6 on file for this type
▸BISADDITIONAL INFORMATION4
09/13/2024322041973Open ↗
09/11/2020322041973Open ↗
09/08/2020322041973Open ↗
Showing 3 of 4 on file for this type
▸BISEFILING COVER SHEET1
02/21/2020322041973Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
06/17/2020340736332Open ↗
▸Other Documents5
▸BISMAINTENANCE INFORMATION1
08/01/2024322041973Open ↗
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION1
04/17/2020322041973Open ↗
▸BISPROTECTION OF EXPOSED FOUNDATION INSULATION1
08/01/2024322041973Open ↗
▸BISPLOT DIAGRAM1
02/21/2020322041973Open ↗
▸BISCHIMNEYS AND VENTS1
08/01/2024322041973Open ↗