← Back
Two family converted from one family
158-02 134 AVENUE
💬 Discuss this project
1950Year Built
2Stories
B3Building Class
R3XZoning
1,490 sfGross Floor Area
2Units
Two family converted from one family · 3,339 sf lot · 0.45 FAR built · Flood zone X
Locations of Work
Electrical
Roof1 filing · 7 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MOMENTUM SOLAR111/26/2025
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MXV SIA LLC9281111/26/2025
Building Lifecycle
All (10)Filed (1)Permit Issued (1)Signed Off (1)Objection (2)Special Inspection (5)
04/28/2026
Signed off — Alteration
installation of solar panels, rooftop, railed, grid-tied, 19 modules, 7.79 KW
Q01325144-I1
01/12/2026
Permit issued — Solar
Q01325144-I1-SL
12/18/2025
Objection resolved — Addressed
12/16/2025
Objection raised — Admin
11/26/2025
Filed — Alteration
installation of solar panels, rooftop, railed, grid-tied, 19 modules, 7.79 KW
Q01325144-I1
11/26/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
11/26/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mina Makar
11/26/2025
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
11/26/2025
Special inspection requirement — Final
Mina Makar
11/26/2025
Special inspection requirement — Air barrier - visual inspection
Mina Makar
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offMOMENTUM SOLAR01/12/2026
BISEQISSUEDUNIVERSAL CONSTR & BUILDERS INC04/02/2008
BIS—ISSUEDUNIVERSAL CONSTR & BUILDERS INC04/02/2008
BIS—ISSUEDN/A11/28/2007
1 project · most recent 11/26/2025
FiledStatusContractorScope
11/26/2025CompleteISLAND ELECTRIC CORP—
1 project · most recent 11/26/2025
FiledStatusContractorScope
11/26/2025Signed-offMOMENTUM SOLAR38 panels, 15.58 kw, 334 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
11/26/2025Fire-Resistant Penetrations and JointsMina Makarspecial
11/26/2025Structural Stability – Alterations of existing buildingsMina Makarspecial
11/26/2025Energy Code Compliance InspectionsMina Makarprogress
11/26/2025FinalMina Makarprogress
11/26/2025Air barrier - visual inspectionMina Makarenergy_progress
▾Documents — 17 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/18/2026Q01325144-I1Request digital key ↗
▸Applications & Permits3
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION2
01/24/2008410026699Open ↗
12/04/2007410026699Open ↗
▸BISWORK PERMIT APPLICATION1
11/28/2007410026699Open ↗
▸Seals & Professional Certifications7
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION2
01/24/2008410026699Open ↗
11/28/2007410026699Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
08/31/2026Q01325144-I1Open ↗
08/31/2026Q01325144-I1Open ↗
▸BISPC FULL REPORT1
11/08/2007410026699Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026Q01325144-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/31/2026Q01325144-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026Q01325144-I1Open ↗
▸Approvals, Objections & Sign-offs3
▸BISADMINISTRATIVE OBJECTIONS1
11/08/2007410026699Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
01/24/2008410026699Open ↗
▸DOB NOWUtility Company Final Acceptance Letter1
08/18/2026Q01325144-I1Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
01/24/2008410026699Open ↗