LL97 Covered0 Active Violations 1 old, status unconfirmed ▸FDNY Report ↗
Office only, 2-6 stories · Owner of record: Dormitory Authority of the State of New York · 134,900 sf lot · 1.93 FAR built · Flood zone X
Locations of Work
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Penthouse1 filing
Floor 41 filing
Floor 3
Floor 2
Floor 1
Cellar1 filing
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Dormitory Authority of the State of New York103/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Ejz Engineering303/12/2026
AKF Engineers109/14/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
J.W.P.303/21/2026
Milrose Consultants203/21/2026
JPK Associates303/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Turner ConstructionGeneral Contractor703/21/2026
Maxxum Constructionspecialty_contractor203/21/2026
Hines GS PropertiesGeneral Contractor103/21/2026
Ferko Plumbing & HeatingPlumbing106/28/2026
Ara Plumbing & HeattingPlumbing106/08/1999
JGN ConstructionGeneral Contractor507/24/2018
Lab PLG & HeatingPlumbing105/09/2003
Liberty MechanicalPlumbing105/01/1998
Liberty Mechanical ContractorsPlumbing107/17/1998
Turner ConstructionGeneral Contractor104/09/1999
Turner ConstrcutionGeneral Contractor407/08/1999
World Wide SPKRFire Protection105/05/1999
World Wide SprinklerFire Protection108/21/1998
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Ejz Engineering7852303/12/2026
AKF Engineers2751109/14/2021
Building Lifecycle
10/27/2026
Boiler inspection report filed
Initial · no defects · Accepted
08/31/2026
Signed off — Alteration
Direct replacement of two (2) existing hot water heating boilers with new at existing locations.
Q01239451-I1
08/03/2026
Boiler inspection report filed
Initial · no defects · Accepted
06/18/2026
Boiler inspection report filed
Initial · no defects · Accepted
03/12/2026
Filed — Alteration
Direct replacement of two (2) existing hot water heating boilers with new at existing locations.
Q01239451-P2
91 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOW—Ferko Plumbing & Heating—
DOB NOW—Maxxum Construction—
BIS—JGN Construction—
BIS—JGN Construction—
BIS—JGN Construction—
BIS—JGN Construction—
BIS—JGN Construction—
BIS—Lab Plumbing & Heating—
BIS—Hines GS Properties—
BIS—Turner Construction Company—
BIS—Turner Construction Company—
BIS—Turner Construction Company—
BIS—Turner Construction Company—
BIS—Turner Construction Company—
BIS—Turner Construction Company—
BIS—Ara Plumbing—
BIS—World Wide SPKR—
BIS—Peter A JR—
BIS—Turner Construction Company—
BIS—Turner Construction Company—
BIS—Turner Construction Company—
BIS—World Wide Sprinkler—
BIS—Liberty Mechanical—
BIS—Turner Construction—
BIS—Liberty Mechanical—
BIS—Turner Construction Company—
BIS—Turner Construction Company—
BIS—Turner Construction Company—
Nothing on file for this building.
Nothing on file for this building.
54 filed documents on file for this building. Sign in free to see the full history. Sign in · Create account