← Back
Four families
1580 PROSPECT PLACE
BROOKLYN · BIN 3036340
💬 Discuss this project
1910Year Built
2Stories
C3Building Class
R6Zoning
3,296 sfGross Floor Area
4Units
Rent Stabilized2 Open Violations ▸FDNY Report ↗
Four families · Owner of record: 1580 PROSPECT PL MAZAL LLC · 5,770 sf lot · 0.57 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire Protection
Roof32p · 1 filing · 20 docs
Penthouse31p · 1 filing · 20 docs
Floor 429p · 1 filing · 20 docs
Floor 327p · 1 filing · 20 docs
Floor 231p · 1 filing · 20 docs
Floor 128p · 1 filing · 20 docs
Cellar37p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
1580 PROSPECT PL MAZAL LLC303/22/2026
BHY CONTRACTOR203/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
06/06/2023$886K—— → —$269/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
VASILIOS ARTEMIOU PE501/08/2025
NIKOLAI KATZ ARCHITECT311/20/2024
KCE CONSULTING ENGINEERING PLLC309/26/2024
BRIAN GOLDMAN, ARCHITECT106/30/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
XPDITE GROUP LLC (104)1103/21/2026
XPDITE GROUP LLC 104403/21/2026
XPDITE GROUP 103303/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
BHY CONTRACTOR INCGeneral Contractor707/08/2026
PRIME PIPING & HEATING INFire Protection107/08/2026
TARGET PIPING NY LLCFire Protection107/08/2026
APEX GROUP NY CORPGeneral Contractor104/09/2026
B&B MECH PLBG & HTG LLCPlumbing107/08/2026
MPI PLUMBING CORPPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HRF SERVICES CORP56161001/08/2025
Building Lifecycle
All (174)Filed (12)Permit Issued (12)Signed Off (7)Violation (60)Inspection (9)Objection (44)Special Inspection (30)
07/02/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
05/05/2026
Violation issued (HPD, open)
A
11/20/2025
Violation issued (HPD, open)
I
08/01/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
02/10/2025
Signed off — Alteration CO
APPLICATION FILED HEREWITH TO VERTICALLY ENLARGE EXISTING TWO STORY BUILDING INTO A FOUR STORY + PENTHOUSE TEN FAMILY RESIDENTIAL BUILDING
B00934334-S2
02/03/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
FAHAD FATEH
02/03/2025
Special inspection requirement — Post-installed Anchors
FAHAD FATEH
02/03/2025
Special inspection requirement — Structural Steel - High Strength Bolting
FAHAD FATEH
02/03/2025
Special inspection requirement — Structural Steel - Details
FAHAD FATEH
02/03/2025
Special inspection requirement — Structural Steel - Welding
FAHAD FATEH
02/03/2025
Special inspection requirement — Masonry
FAHAD FATEH
02/03/2025
Special inspection requirement — Structural Cold-Formed Steel
FAHAD FATEH
02/03/2025
Special inspection requirement — Concrete - Cast-In-Place
FAHAD FATEH
02/03/2025
Special inspection requirement — Final
FAHAD FATEH
01/30/2025
Signed off — Alteration CO
APPLICATION FILED HEREWITH TO VERTICALLY ENLARGE EXISTING TWO STORY BUILDING INTO A FOUR STORY + PENTHOUSE TEN FAMILY RESIDENTIAL BUILDING
B00934334-S3
01/28/2025
Special inspection requirement — HVAC-R and service water heating system controls
FAHAD FATEH
01/28/2025
Special inspection requirement — Energy Code Compliance Inspections
FAHAD FATEH
01/28/2025
Special inspection requirement — Post-installed Anchors
FAHAD FATEH
01/28/2025
Special inspection requirement — Final
FAHAD FATEH
01/28/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
FAHAD FATEH
01/28/2025
Special inspection requirement — Mechanical Systems
FAHAD FATEH
01/28/2025
Special inspection requirement — Duct leakage testing, insulation and design
FAHAD FATEH
01/28/2025
Special inspection requirement — Shutoff dampers
FAHAD FATEH
01/28/2025
Special inspection requirement — Maintenance information
FAHAD FATEH
01/28/2025
Special inspection requirement — HVAC-R and service water heating equipment
FAHAD FATEH
01/28/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
FAHAD FATEH
01/28/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
01/23/2025
Objection resolved — Addressed
01/22/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
01/14/2025
Signed off — Alteration CO
APPLICATION FILED HEREWITH TO VERTICALLY ENLARGE EXISTING TWO STORY BUILDING INTO A FOUR STORY + PENTHOUSE TEN FAMILY RESIDENTIAL BUILDING
B00934334-S4
01/14/2025
Objection resolved — Addressed
01/14/2025
Objection resolved — Addressed
01/13/2025
Objection resolved — Addressed
01/10/2025
Objection raised — Scope
01/10/2025
Objection raised — Scope
01/10/2025
Objection raised — Scope
01/09/2025
Signed off — Alteration CO
APPLICATION FILED HEREWITH TO VERTICALLY ENLARGE EXISTING TWO STORY BUILDING INTO A FOUR STORY + PENTHOUSE TEN FAMILY RESIDENTIAL BUILDING
B00934334-S1
01/09/2025
Signed off — Alteration CO
APPLICATION FILED HEREWITH TO VERTICALLY ENLARGE EXISTING TWO STORY BUILDING INTO A FOUR STORY + PENTHOUSE TEN FAMILY RESIDENTIAL BUILDING
B00934334-S5
01/08/2025
Filed — Alteration CO
APPLICATION FILED HEREWITH TO VERTICALLY ENLARGE EXISTING TWO STORY BUILDING INTO A FOUR STORY + PENTHOUSE TEN FAMILY RESIDENTIAL BUILDING
B00934334-P5
01/06/2025
Inspection — Pass-Final SP - Up to 9 Requested Floors
Pass
View inspection ↗
01/06/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
01/06/2025
Special inspection requirement — HVAC-R and service water heating system controls
FAHAD FATEH
01/06/2025
Special inspection requirement — Final
FAHAD FATEH
01/06/2025
Special inspection requirement — HVAC-R and service water heating equipment
FAHAD FATEH
01/06/2025
Special inspection requirement — Post-installed Anchors
FAHAD FATEH
01/06/2025
Special inspection requirement — Shutoff dampers
FAHAD FATEH
01/06/2025
Special inspection requirement — Energy Code Compliance Inspections
FAHAD FATEH
01/06/2025
Special inspection requirement — Maintenance information
FAHAD FATEH
01/06/2025
Special inspection requirement — Duct leakage testing, insulation and design
FAHAD FATEH
01/02/2025
Objection resolved — Addressed
01/02/2025
Objection resolved — Addressed
12/31/2024
Inspection — Certified Storm Drainage-ST-Fixtures-Finish
Certified
View inspection ↗
12/31/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
12/24/2024
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
12/18/2024
Signed off — Alteration
APPLICATION FILED HEREWITH FOR INSTALLATION OF TEMPORARY CONSTRUCTION FENCE
B00965571-I1
12/13/2024
Objection resolved — Addressed
11/29/2024
Violation issued (HPD, closed)
I
11/20/2024
Filed — Alteration CO
APPLICATION FILED HEREWITH TO VERTICALLY ENLARGE EXISTING TWO STORY BUILDING INTO A FOUR STORY + PENTHOUSE TEN FAMILY RESIDENTIAL BUILDING
B00934334-P3
11/20/2024
Objection raised — Admin
11/12/2024
Objection resolved — Addressed
Latest 60 of 174 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedBHY CONTRACTOR INC11/01/2024
DOB NOWPlumbingSigned-offTARGET PIPING NY LLC07/30/2024
DOB NOWMechanical SystemsSigned-offBHY CONTRACTOR INC07/25/2024
DOB NOWSprinklersSigned-offTARGET PIPING NY LLC07/22/2024
DOB NOWSidewalk ShedSigned-offAPEX GROUP NY CORP07/02/2024
DOB NOWStructuralSigned-offBHY CONTRACTOR INC06/18/2024
DOB NOWPlumbingSigned-offYG SERVICES INC05/22/2024
DOB NOWSprinklersSigned-offA M B MECHANICAL INC05/22/2024
DOB NOWGeneral ConstructionPermit IssuedBHY CONTRACTOR INC05/20/2024
DOB NOWEarth WorkSigned-offBHY CONTRACTOR INC05/14/2024
DOB NOWStructuralSigned-offBHY CONTRACTOR INC05/13/2024
DOB NOWConstruction FenceSigned-offBHY CONTRACTOR INC04/09/2024
1 project · most recent 01/08/2025
Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
01/08/2025Permit IssuedBHY CONTRACTOR INCHeating and Air Conditioning Systems
Heat / Cool
Fujitsu AOU24RLXFZ 24,000 BTU · Split System ×10
AOU36RLXFZH 36,400 BTU · Split System ×4
AOU18RLXFZH 22,000 BTU · Split System ×2
AOU36RLXFZ1 35,200 BTU · Split System ×2
AOUH12LPAS1 14,000 BTU · Split System ×2
1 project · most recent 01/08/2025
Sprinkler System
FiledStatusContractorScope
01/08/2025Signed-offTARGET PIPING NY LLCSprinkler System
1 project · most recent 01/08/2025
Storm Water/Sanitary
FiledStatusContractorScope
01/08/2025Signed-offTARGET PIPING NY LLCStorm, Water/Sanitary
4 projects · most recent 01/27/2025
General Wiring
FiledStatusContractorScope
01/27/2025CompletePOWER DIRECT ELECTRIC INCGeneral Wiring
07/10/2024CompleteGRX EURO ELECTRIC CORP—
07/08/2024CompleteHIGH QUALITY ELECTRIC OF—
05/29/2024CompletePOWER DIRECT ELECTRIC INC—
1 project · most recent 01/08/2025
Masonry Wood
FiledStatusContractorScope
01/08/2025Permit IssuedBHY CONTRACTOR INCMasonry, Wood
▾Field Inspections (DOB CAP) — 9
DateTypeResultReport
07/02/2026Pass-Final CND-Occupancy InspectionPassView ↗
08/01/2025Pass-Final CND-Occupancy InspectionPassView ↗
01/22/2025Pass-Final CND-Occupancy InspectionPassView ↗
01/06/2025Pass-Final SP - Up to 9 Requested FloorsPassView ↗
12/31/2024Certified Storm Drainage-ST-Fixtures-FinishCertifiedView ↗
12/31/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
12/24/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
09/25/2024Pass-Final PL - Up to 9 Requested FloorsPassView ↗
07/10/2024Pass-Final PL - UndergroundPassView ↗
▾Special Inspection Requirements (DOB NOW) — 66
DateRequirementInspectorRole
02/03/2025FinalFAHAD FATEHprogress
02/03/2025Structural Steel - High Strength BoltingFAHAD FATEHspecial
02/03/2025Concrete - Cast-In-PlaceFAHAD FATEHspecial
02/03/2025Structural Stability – Alterations of existing buildingsFAHAD FATEHspecial
02/03/2025Post-installed AnchorsFAHAD FATEHspecial
02/03/2025Structural Steel - WeldingFAHAD FATEHspecial
02/03/2025MasonryFAHAD FATEHspecial
02/03/2025Structural Steel - DetailsFAHAD FATEHspecial
02/03/2025Structural Cold-Formed SteelFAHAD FATEHspecial
01/28/2025HVAC-R and service water piping design and insulationFAHAD FATEHenergy_progress
01/28/2025Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
01/28/2025Mechanical SystemsFAHAD FATEHspecial
01/28/2025Post-installed AnchorsFAHAD FATEHspecial
01/28/2025Structural Stability – Alterations of existing buildingsFAHAD FATEHspecial
01/28/2025FinalFAHAD FATEHprogress
01/28/2025Energy Code Compliance InspectionsFAHAD FATEHprogress
01/28/2025HVAC-R and service water heating system controlsFAHAD FATEHenergy_progress
01/28/2025Shutoff dampersFAHAD FATEHenergy_progress
01/28/2025Duct leakage testing, insulation and designFAHAD FATEHenergy_progress
01/28/2025Maintenance informationFAHAD FATEHenergy_progress
01/28/2025HVAC-R and service water heating equipmentFAHAD FATEHenergy_progress
01/06/2025Mechanical SystemsFAHAD FATEHspecial
01/06/2025Shutoff dampersFAHAD FATEHenergy_progress
01/06/2025HVAC-R and service water heating equipmentFAHAD FATEHenergy_progress
01/06/2025Maintenance informationFAHAD FATEHenergy_progress
Latest 25 of 66.
▾Documents — 65 on file (BIS + DOB NOW)
▸Plans & Drawings12
▸DOB NOWPlans/Sketch12
08/26/2026B00965571-I1Request digital key ↗
08/24/2026B01074280-I1Request digital key ↗
08/23/2026B00934334-I1Request digital key ↗
Showing 3 of 12 on file for this type
▸Zoning, Tax Lot & Property Records3
▸DOB NOWZD1: DOB Zoning Diagram2
08/13/2026B00934334-P3Open ↗
08/13/2026B00934334-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026B00934334-I1Open ↗
▸Seals & Professional Certifications34
▸DOB NOWSpecial Inspector Seal & Signature12
08/28/2026B00934334-P3Open ↗
08/27/2026B00934334-S2Open ↗
08/27/2026B00934334-S2Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature12
08/26/2026B00965571-I1Open ↗
08/13/2026B00934334-P2Open ↗
08/13/2026B00934334-P1Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWProgress Inspector Seal & Signature10
08/28/2026B00934334-P3Open ↗
08/28/2026B00934334-P3Open ↗
08/27/2026B00934334-S2Open ↗
Showing 3 of 10 on file for this type
▸Safety & Tenant Protection5
▸DOB NOWStreet Tree Checklist2
08/13/2026B00934334-I1Open ↗
08/13/2026B00934334-P3Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026B00934334-I1Open ↗
▸DOB NOWStreet Trees Site Plan1
08/13/2026B00934334-I1Open ↗
▸DOB NOWStreet Tree Sign Off1
08/13/2026B00934334-I1Open ↗
▸Other Documents11
▸DOB NOWPlot Diagram3
08/13/2026B00934334-P3Open ↗
08/13/2026B00934334-S1Open ↗
08/13/2026B00934334-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/13/2026B00934334-P3Open ↗
08/13/2026B00934334-I1Open ↗
▸DOB NOWProperty Ownership Certification2
08/13/2026B00934334-P3Open ↗
08/13/2026B00934334-I1Open ↗
▸DOB NOWSite Survey: Initial2
08/13/2026B00934334-I1Open ↗
08/13/2026B00934334-P3Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026B00934334-S1Open ↗
▸DOB NOWFinal Survey1
08/13/2026B00934334-I1Open ↗