← Back
Miscellaneous two family
159 BOND STREET
BROOKLYN · BIN 3005897
💬 Discuss this project
1854Year Built
3Stories
B9Building Class
R6BZoning
2,904 sfGross Floor Area
2Units
Miscellaneous two family · Owner of record: 159 BH LLC · 2,500 sf lot · 1.16 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbing
Permit Issued — active, not yet Signed-off
RoofUnder Construction7p · 1 filing · 20 docs
Floor 3Under Construction7p · 1 filing · 20 docs
Floor 2Under Construction7p · 1 filing · 20 docs
Floor 1Under Construction7p · 1 filing · 20 docs
CellarUnder Construction7p · 1 filing · 20 docs
BasementUnder Construction7p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
MINERVA1008/29/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
05/28/2025$2.7M—Private party → 159 CHARM LLC$930/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
JBA508/18/2026
WORLD DESIGN ARCHITECTURE,PLLC106/11/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
NYC BUILDING SOLUTIONS303/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
EJ HOMES 45 LLCGeneral Contractor203/21/2026
NYC BUILDING SOLUTIONS COGeneral Contractor104/09/2026
RRP PLUMBING CORPPlumbing106/28/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
WORLD DESIGN ARCHITECTURE9323408/18/2026
Building Lifecycle
All (65)Filed (6)Permit Issued (3)Signed Off (1)Inspection (3)Objection (22)Special Inspection (30)
09/15/2026
Objection resolved — Addressed
08/18/2026
Filed — Alteration CO
HEREWITH FILING APPLICATION FOR NEW CO-INTERIOR WORK; NEW GYP BOARD, REPLACE ALL FINISHES AS PER PLANS. PROPOSED 1 FAMILY DWELLING.
B01239845-P4
07/28/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
07/28/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
William Alicea
07/28/2026
Special inspection requirement — Insulation placement and R values
William Alicea
07/28/2026
Special inspection requirement — Metering
William Alicea
07/28/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
William Alicea
07/28/2026
Special inspection requirement — Fenestration air leakage
William Alicea
07/28/2026
Special inspection requirement — Interior lighting power
William Alicea
07/28/2026
Special inspection requirement — Maintenance information
William Alicea
07/28/2026
Special inspection requirement — Lighting controls
William Alicea
07/28/2026
Special inspection requirement — Fenestration areas
William Alicea
07/28/2026
Special inspection requirement — Lighting in dwelling units
William Alicea
07/28/2026
Special inspection requirement — Fire-Resistance Rated Construction
William Alicea
07/28/2026
Special inspection requirement — Energy Code Compliance Inspections
William Alicea
07/28/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
William Alicea
07/23/2026
Objection raised — Other
07/18/2026
Filed — Alteration CO
HEREWITH FILING APPLICATION FOR NEW CO-INTERIOR WORK; NEW GYP BOARD, REPLACE ALL FINISHES AS PER PLANS. PROPOSED 1 FAMILY DWELLING.
B01239845-P3
07/13/2026
Special inspection requirement — Lighting controls
William Alicea
07/13/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
William Alicea
07/13/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
William Alicea
07/13/2026
Special inspection requirement — Energy Code Compliance Inspections
William Alicea
07/13/2026
Special inspection requirement — Fire-Resistance Rated Construction
William Alicea
07/13/2026
Special inspection requirement — Insulation placement and R values
William Alicea
07/13/2026
Special inspection requirement — Fenestration areas
William Alicea
07/13/2026
Special inspection requirement — Metering
William Alicea
07/13/2026
Special inspection requirement — Lighting in dwelling units
William Alicea
07/13/2026
Special inspection requirement — Interior lighting power
William Alicea
07/13/2026
Special inspection requirement — Fenestration air leakage
William Alicea
07/13/2026
Special inspection requirement — Maintenance information
William Alicea
07/13/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
William Alicea
07/02/2026
Filed — Alteration CO
HEREWITH FILING APPLICATION FOR NEW CO-INTERIOR WORK; NEW GYP BOARD, REPLACE ALL FINISHES AS PER PLANS. PROPOSED 1 FAMILY DWELLING.
B01239845-P2
07/02/2026
Special inspection requirement — Maintenance information
William Alicea
07/02/2026
Special inspection requirement — HVAC-R and service water heating system controls
William Alicea
07/02/2026
Special inspection requirement — HVAC-R and service water heating equipment
William Alicea
07/02/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
William Alicea
02/04/2026
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
02/01/2026
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
01/27/2026
Permit issued — Plumbing
B01239845-S2-PL
01/20/2026
Signed off — Alteration
HEREWITH FILING INTERIOR NON STRUCTURAL INTERIOR DEMO AS PER CONSTRUCTION PLANS.
B01236914-I1
01/02/2026
Permit issued — General Construction
B01239845-I1-GC
12/23/2025
Filed — Alteration CO
HEREWITH FILING APPLICATION FOR NEW CO-INTERIOR WORK; NEW GYP BOARD, REPLACE ALL FINISHES AS PER PLANS. PROPOSED 1 FAMILY DWELLING.
B01239845-S2
12/04/2025
Objection resolved — Addressed
12/03/2025
Objection resolved — Addressed
12/03/2025
Objection resolved — Addressed
11/20/2025
Objection resolved — Addressed
11/20/2025
Objection resolved — Addressed
08/11/2025
Objection resolved — Addressed
07/31/2025
Permit issued — Structural
B01236914-I1-GC-CX
07/30/2025
Objection resolved — Addressed
07/10/2025
Objection raised — Cost
07/07/2025
Objection raised — Cost
07/07/2025
Objection raised — Other
07/03/2025
Objection raised — Other
07/03/2025
Objection raised — Other
07/03/2025
Objection raised — Other
07/03/2025
Objection raised — Other
06/30/2025
Filed — Alteration CO
HEREWITH FILING APPLICATION FOR NEW CO-INTERIOR WORK; NEW GYP BOARD, REPLACE ALL FINISHES AS PER PLANS. PROPOSED 1 FAMILY DWELLING.
B01239845-I1
06/27/2025
Objection resolved — Addressed
06/27/2025
Objection resolved — Addressed
Latest 60 of 65 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedRRP PLUMBING CORP01/27/2026
DOB NOWGeneral ConstructionPermit IssuedEJ HOMES 4501/02/2026
DOB NOWStructuralSigned-offNYC BUILDING SOLUTIONS CO07/31/2025
1 project · most recent 08/18/2026
Gas Storm Water/Sanitary
FiledStatusContractorScope
08/18/2026Permit IssuedRRP PLUMBING CORPGas, Storm, Water/Sanitary
1 project · most recent 11/04/2025
General Wiring
FiledStatusContractorScope
11/04/2025CompleteSAFEWAY CONSTRUCTION, INCGeneral Wiring
▾Field Inspections (DOB CAP) — 3
DateTypeResultReport
07/28/2026Pass-Final CND-Occupancy InspectionPassView ↗
02/04/2026Pass-Final PL - Up to 9 Requested FloorsPassView ↗
02/01/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 46
DateRequirementInspectorRole
07/28/2026Fire-Resistant Penetrations and JointsWilliam Aliceaspecial
07/28/2026Insulation placement and R valuesWilliam Aliceaenergy_progress
07/28/2026MeteringWilliam Aliceaenergy_progress
07/28/2026Fenestration and door U-factor and product ratingsWilliam Aliceaenergy_progress
07/28/2026Fenestration air leakageWilliam Aliceaenergy_progress
07/28/2026Interior lighting powerWilliam Aliceaenergy_progress
07/28/2026Maintenance informationWilliam Aliceaenergy_progress
07/28/2026Lighting controlsWilliam Aliceaenergy_progress
07/28/2026Fenestration areasWilliam Aliceaenergy_progress
07/28/2026Lighting in dwelling unitsWilliam Aliceaenergy_progress
07/28/2026Fire-Resistance Rated ConstructionWilliam Aliceaprogress
07/28/2026Energy Code Compliance InspectionsWilliam Aliceaprogress
07/28/2026Structural Stability – Alterations of existing buildingsWilliam Aliceaspecial
07/13/2026Lighting controlsWilliam Aliceaenergy_progress
07/13/2026Structural Stability – Alterations of existing buildingsWilliam Aliceaspecial
07/13/2026Fire-Resistant Penetrations and JointsWilliam Aliceaspecial
07/13/2026Energy Code Compliance InspectionsWilliam Aliceaprogress
07/13/2026Fire-Resistance Rated ConstructionWilliam Aliceaprogress
07/13/2026Insulation placement and R valuesWilliam Aliceaenergy_progress
07/13/2026Fenestration areasWilliam Aliceaenergy_progress
07/13/2026MeteringWilliam Aliceaenergy_progress
07/13/2026Lighting in dwelling unitsWilliam Aliceaenergy_progress
07/13/2026Interior lighting powerWilliam Aliceaenergy_progress
07/13/2026Fenestration air leakageWilliam Aliceaenergy_progress
07/13/2026Maintenance informationWilliam Aliceaenergy_progress
Latest 25 of 46.
▾Documents — 62 on file (BIS + DOB NOW)
▸Plans & Drawings6
▸DOB NOWPlans/Sketch6
08/21/2026B01236914-I1Request digital key ↗
08/19/2026B01239845-P2Request digital key ↗
08/19/2026B01239845-S2Request digital key ↗
Showing 3 of 6 on file for this type
▸Applications & Permits6
▸DOB NOWLPC Approval/Permit6
08/19/2026B01239845-P2Open ↗
08/19/2026B01239845-P4Open ↗
08/15/2026B01239845-P3Open ↗
Showing 3 of 6 on file for this type
▸Zoning, Tax Lot & Property Records4
▸DOB NOWZD1: DOB Zoning Diagram3
08/19/2026B01239845-P2Open ↗
08/19/2026B01239845-P4Open ↗
08/13/2026B01239845-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026B01239845-I1Open ↗
▸Seals & Professional Certifications19
▸DOB NOWProgress Inspector Seal & Signature8
09/13/2026B01239845-P2Open ↗
09/13/2026B01239845-P2Open ↗
08/28/2026B01239845-P3Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature6
08/21/2026B01236914-I1Open ↗
08/19/2026B01239845-S2Open ↗
08/19/2026B01239845-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature5
09/13/2026B01239845-P2Open ↗
08/27/2026B01239845-P4Open ↗
08/24/2026B01239845-I1Open ↗
Showing 3 of 5 on file for this type
▸Safety & Tenant Protection4
▸DOB NOWStreet Tree Checklist3
08/19/2026B01239845-P2Open ↗
08/19/2026B01239845-I1Open ↗
08/19/2026B01239845-P4Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026B01239845-I1Open ↗
▸Environmental & Asbestos6
▸DOB NOWDEP ACP-5: Asbestos Assessment Report6
08/21/2026B01236914-I1Open ↗
08/19/2026B01239845-S2Open ↗
08/19/2026B01239845-I1Open ↗
Showing 3 of 6 on file for this type
▸Other Documents17
▸DOB NOWWaiver Document5
08/19/2026B01239845-P2Open ↗
08/19/2026B01239845-S2Open ↗
08/19/2026B01239845-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSite Survey: Initial3
08/19/2026B01239845-P4Open ↗
08/19/2026B01239845-P2Open ↗
08/13/2026B01239845-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone3
08/19/2026B01239845-P2Open ↗
08/19/2026B01239845-P4Open ↗
08/13/2026B01239845-I1Open ↗
▸DOB NOWPlot Diagram3
08/19/2026B01239845-P4Open ↗
08/19/2026B01239845-P2Open ↗
08/13/2026B01239845-I1Open ↗
▸DOB NOWProperty Ownership Certification3
08/19/2026B01239845-P2Open ↗
08/19/2026B01239845-I1Open ↗
08/19/2026B01239845-P4Open ↗