← Back
Elevator apt, semi-fireproof without stores
Highbridge Rising
1592 JESUP AVENUE · BIN 2008698
💬 Discuss this project
1938Year Built
6Stories
D1Building Class
R7-1Zoning
40,371 sfGross Floor Area
37Units
LL97 CoveredRent Stabilized36 Open Violations 30 unresolved · 6 paperwork only ▸FISP: No Report Filed
Elevator apt, semi-fireproof without stores · 7,500 sf lot · 5.38 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingGeneral
Permit Issued — active, not yet Signed-off
RoofUnder Construction58p · 3 filings · 20 docs
Floor 6Under Construction9p · 2 filings · 20 docs
Floor 5Under Construction16p · 2 filings · 20 docs
Floor 4Under Construction16p · 2 filings · 20 docs
Floor 3Under Construction16p · 2 filings · 20 docs
Floor 2Under Construction16p · 2 filings · 20 docs
Floor 1Under Construction22p · 2 filings · 20 docs
CellarUnder Construction26p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
HIGHBRIDGE COMMUNITY DEV. CORP2008/29/2026
TRIERA CONTRACTING807/08/2026
HIGHBRIDGE COMM.DEVELOPME103/22/2026
HIGHBRIDGE COMMUNITY DEVELOPMENT203/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JON LIBASCI RA403/21/2026
WILLIAM VITACCO ASSOCIATES603/21/2026
MUNICIPAL BUILDING CONSULTANTS103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
1937 CONTRACTING CO. INCGeneral Contractor707/08/2026
TRIERA CONTRACTING INCGeneral Contractor507/08/2026
NOTIAS CONSTRUCTION INCGeneral Contractor307/02/2026
AKM CONSTRUCTION NY CORPGeneral Contractor207/25/2026
AMERICAN STANDARD P&H CORORP.Plumbing207/22/2026
RICHARD NEUElectrical103/22/2026
PANDELI GJINIElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
CONCRETE SOLUTIONS LAB CO5344704/21/2026
LUKE LICALZI P.E.,P.C.3679411/28/2023
GEORGE J. XERAKIAS, PE1658108/25/2022
Building Lifecycle
All (147)Filed (12)Permit Issued (13)Signed Off (1)Facade (FISP) (10)Violation (60)Inspection (11)Objection (10)Special Inspection (30)
07/23/2026
Permit issued — Sidewalk Shed
X01360046-I1-SH
07/21/2026
Permit issued — Plumbing
X01208265-S2-PL
07/21/2026
Permit issued — Boiler Equipment
X01208265-S4-BE
05/21/2026
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
05/19/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
05/14/2026
Permit issued — Mechanical Systems
X01208265-S3-MS
05/14/2026
Permit issued — Structural
X01208265-S1-ST
05/14/2026
Permit issued — General Construction
X01208265-S5-GC
04/21/2026
Filed — Alteration
X01208265-P2
04/21/2026
Special inspection requirement — Air barrier - visual inspection
MINA HANNA
04/21/2026
Special inspection requirement — Interior lighting power
MINA HANNA
04/21/2026
Special inspection requirement — Exterior lighting power
MINA HANNA
04/21/2026
Special inspection requirement — Fire-Resistance Rated Construction
MINA HANNA
04/21/2026
Special inspection requirement — Fenestration air leakage
MINA HANNA
04/21/2026
Special inspection requirement — Lighting controls
MINA HANNA
04/21/2026
Special inspection requirement — Fenestration areas
MINA HANNA
04/21/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
MINA HANNA
04/21/2026
Special inspection requirement — Lighting in dwelling units
MINA HANNA
04/21/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
MINA HANNA
04/21/2026
Special inspection requirement — Tenant Protection Plan Compliance
MINA HANNA
04/21/2026
Special inspection requirement — Final
MINA HANNA
04/21/2026
Special inspection requirement — Energy Code Compliance Inspections
MINA HANNA
04/03/2026
Filed — Alteration
HEAVY DUTY SIDEWALK SHED DURING EXTERIOR FACADE REPAIRS FILED UNDER APPLICATION # X01208265. SIDEWALK SHED SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
X01360046-I1
04/03/2026
Permit issued — Sidewalk Shed
X01360046-I1-SH
03/20/2026
Special inspection requirement — Lighting in dwelling units
03/20/2026
Special inspection requirement — Exterior lighting power
03/20/2026
Special inspection requirement — Interior lighting power
03/20/2026
Special inspection requirement — Lighting controls
12/15/2025
Special inspection requirement — Tenant Protection Plan Compliance
12/11/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
12/02/2025
Special inspection requirement — Energy Code Compliance Inspections
MINA HANNA
12/02/2025
Special inspection requirement — Fenestration areas
MINA HANNA
12/02/2025
Special inspection requirement — Fenestration air leakage
MINA HANNA
12/02/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
MINA HANNA
12/02/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
MINA HANNA
12/02/2025
Special inspection requirement — Air barrier - visual inspection
MINA HANNA
12/02/2025
Special inspection requirement — Fire-Resistance Rated Construction
MINA HANNA
12/02/2025
Special inspection requirement — Final
MINA HANNA
11/05/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
10/17/2025
Violation issued (ECB, open)
Elevators
09/18/2025
Filed — Alteration
X01208265-S4
08/25/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
07/28/2025
Filed — Alteration
X01208265-S1
07/25/2025
Filed — Alteration
X01208265-S5
07/11/2025
Filed — Alteration
X01208265-S3
07/11/2025
Filed — Alteration
X01208265-S2
06/25/2025
Filed — Alteration
X01208265-I1
06/11/2025
Special inspection requirement — Tenant Protection Plan Compliance
MINA HANNA
06/10/2025
Special inspection requirement — Structural Steel - Details
MINA HANNA
06/10/2025
Special inspection requirement — Structural Steel - Welding
MINA HANNA
06/10/2025
Special inspection requirement — Masonry
MINA HANNA
04/08/2025
Violation issued (ECB, open)
Local Law
02/25/2025
Violation issued (ECB, open)
Construction
02/22/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
01/18/2024
Signed off — Alteration
facade repair
X00583511-I1
01/16/2024
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
12/18/2023
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
12/08/2023
Permit issued — General Construction
X00583511-I1-GC-CX
11/28/2023
Filed — Alteration
facade repair
X00583511-P1
08/17/2023
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
Latest 60 of 147 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSidewalk ShedPermit IssuedAKM CONSTRUCTION NY CORP07/23/2026
DOB NOWPlumbingPermit IssuedAMERICAN STANDARD P&H CORORP.07/21/2026
DOB NOWBoiler EquipmentPermit IssuedAMERICAN STANDARD P&H CORORP.07/21/2026
DOB NOWMechanical SystemsPermit IssuedNOTIAS CONSTRUCTION INC05/14/2026
DOB NOWStructuralPermit IssuedNOTIAS CONSTRUCTION INC05/14/2026
DOB NOWGeneral ConstructionPermit IssuedNOTIAS CONSTRUCTION INC05/14/2026
DOB NOWSidewalk ShedPermit IssuedAKM CONSTRUCTION NY04/03/2026
DOB NOWGeneral ConstructionSigned-off1937 CONTRACTING CO. INC12/08/2023
DOB NOWSidewalk ShedPermit IssuedTRIERA CONTRACTING INC07/06/2023
DOB NOWSupported ScaffoldPermit Issued1937 CONTRACTING CO. INC06/06/2023
DOB NOWSupported ScaffoldPermit Issued1937 CONTRACTING CO. INC08/26/2022
DOB NOWSidewalk ShedPermit IssuedTRIERA CONTRACTING INC07/09/2022
DOB NOWSidewalk ShedPermit IssuedTRIERA CONTRACTING INC07/14/2021
BISEQISSUEDCS BRIDGE CORP03/28/2011
BISOTISSUEDDAVE RESTORATION INC01/13/2011
BISOTISSUEDK.E.S CONSTRUCTION CO INC10/07/2010
BISEQISSUEDCS BRIDGE CORP09/28/2010
BISEQISSUEDM.S.S. CONSTRUCTION CORP.11/14/2006
5 projects · most recent 05/27/2026
General Wiring
FiledStatusContractorScope
05/27/2026Permit IssuedCENTENNIAL ELEVATOR INDUSGeneral Wiring
02/26/2026Permit IssuedHIGH QUALITY ELEC.OF NYC—
12/17/2025Permit IssuedTECHNO-VOLT ELEC, INCGeneral Wiring
10/31/2022Permit IssuedRICHARD NEU—
03/18/2022CompleteMHO'S ELECTRIC CORPGeneral Wiring
3 projects · most recent 04/03/2026
Sidewalk Shed Scaffold
FiledStatusContractorScope
04/03/2026Permit IssuedAKM CONSTRUCTION NY CORPSidewalk Shed
08/25/2022Permit Issued1937 CONTRACTING CO. INCScaffold
07/14/2021Permit IssuedTRIERA CONTRACTING INCSidewalk Shed
▾Field Inspections (DOB CAP) — 11
DateTypeResultReport
05/21/2026Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
05/19/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
12/11/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
11/05/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
08/25/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/16/2024Pass-Final General Construction Non-Directive 14PassView ↗
12/18/2023Fail-Final General Construction Non-Directive 14FailView ↗
08/17/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
07/20/2023Certified Gas-Gas-Piping-RoughingCertifiedView ↗
07/20/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
07/18/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 59
DateRequirementInspectorRole
04/21/2026Air barrier - visual inspectionMINA HANNAenergy_progress
04/21/2026Interior lighting powerMINA HANNAenergy_progress
04/21/2026Exterior lighting powerMINA HANNAenergy_progress
04/21/2026Fire-Resistance Rated ConstructionMINA HANNAprogress
04/21/2026Fenestration air leakageMINA HANNAenergy_progress
04/21/2026Lighting controlsMINA HANNAenergy_progress
04/21/2026Fenestration areasMINA HANNAenergy_progress
04/21/2026Fenestration and door U-factor and product ratingsMINA HANNAenergy_progress
04/21/2026Lighting in dwelling unitsMINA HANNAenergy_progress
04/21/2026Fire-Resistant Penetrations and JointsMINA HANNAspecial
04/21/2026Tenant Protection Plan ComplianceMINA HANNAspecial
04/21/2026FinalMINA HANNAprogress
04/21/2026Energy Code Compliance InspectionsMINA HANNAprogress
03/20/2026Lighting in dwelling units—energy_progress
03/20/2026Exterior lighting power—energy_progress
03/20/2026Interior lighting power—energy_progress
03/20/2026Lighting controls—energy_progress
12/15/2025Tenant Protection Plan Compliance—special
12/02/2025Energy Code Compliance InspectionsMINA HANNAprogress
12/02/2025Fenestration areasMINA HANNAenergy_progress
12/02/2025Fenestration air leakageMINA HANNAenergy_progress
12/02/2025Fire-Resistant Penetrations and JointsMINA HANNAspecial
12/02/2025Fenestration and door U-factor and product ratingsMINA HANNAenergy_progress
12/02/2025Air barrier - visual inspectionMINA HANNAenergy_progress
12/02/2025Fire-Resistance Rated ConstructionMINA HANNAprogress
Latest 25 of 59.
▾Documents — 63 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/25/2026X00557306-I1Request digital key ↗
08/24/2026X00583511-P1Request digital key ↗
08/17/2026X01360046-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸Applications & Permits6
▸BISWORK PERMIT APPLICATION4
03/29/2011220084771Open ↗
01/18/2011220027021Open ↗
10/07/2010220027021Open ↗
Showing 3 of 4 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION2
09/28/2010220084771Open ↗
09/10/2009220027021Open ↗
▸Seals & Professional Certifications35
▸DOB NOWSpecial Inspector Seal & Signature12
09/17/2026X01208265-P3Open ↗
09/02/2026X01208265-I1Open ↗
09/02/2026X01208265-I1Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWProgress Inspector Seal & Signature11
09/17/2026X01208265-P3Open ↗
09/02/2026X01208265-I1Open ↗
09/02/2026X01208265-I1Open ↗
Showing 3 of 11 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION4
02/02/2012220084771Open ↗
05/18/2011220027021Open ↗
09/28/2010220084771Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/25/2026X00557306-I1Open ↗
08/24/2026X00583511-P1Open ↗
08/24/2026X00583511-I1Open ↗
Showing 3 of 4 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST2
09/28/2010220084771Open ↗
09/10/2009220027021Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM2
09/28/2010220084771Open ↗
09/10/2009220027021Open ↗
▸Environmental & Asbestos4
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER2
09/28/2010220084771Open ↗
09/10/2009220027021Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/24/2026X00583511-P1Open ↗
08/14/2026X00583511-I1Open ↗
▸Approvals, Objections & Sign-offs8
▸BISLETTERS - SUPPORTING DOCUMENTATION2
02/02/2012220084771Open ↗
03/29/2011220084771Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST2
02/02/2012220084771Open ↗
05/18/2011220027021Open ↗
▸BISADMINISTRATIVE OBJECTIONS2
09/28/2010220084771Open ↗
09/10/2009220027021Open ↗
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter2
08/13/2026X00583511-P1Open ↗
08/13/2026X00583511-I1Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
05/18/2011220027021Open ↗
09/10/2009220027021Open ↗
▸Filing & Intake Forms2
▸BISEFILING COVER SHEET2
09/28/2010220084771Open ↗
09/10/2009220027021Open ↗
▸Other Documents2
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/13/2026X01208265-I1Open ↗
08/13/2026X01208265-P2Open ↗