| Owner | Filings | Most Recent |
|---|---|---|
| SPLEN CONSTRUCTION | 6 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 05/28/2024 | $2.3M | — | — → — | $517/sf building |
| 05/27/2021 | $1.1M | — | — → — | $243/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| MEI ARCHITECT PLLC | 7 | 05/19/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| IBUILD CONSULTING | 14 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| L&L CONSTRUCTION DEVELOP | General Contractor | 6 | 03/21/2026 |
| SPLEN CONSTRUCTION INC | General Contractor | 4 | 07/08/2026 |
| HP SERVICES INC | Plumbing | 1 | 07/08/2026 |
| XH&RC PLBG AND HTG INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| MEHDI GHAZI, P.E. P.C. | 7129 | 5 | 05/19/2023 |
| TRIANGLE INSPECTION & TES | 7495 | 3 | 05/16/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | L&L CONSTRUCTION DEVELOP | 08/18/2023 |
| DOB NOW | Plumbing | Signed-off | HP SERVICES INC | 06/07/2023 |
| DOB NOW | Structural | Permit Issued | L&L CONSTRUCTION DEVELOP | 03/07/2023 |
| DOB NOW | Plumbing | Signed-off | XH&RC PLBG AND HTG INC | 04/20/2022 |
| DOB NOW | General Construction | Permit Issued | SPLEN CONSTRUCTION INC | 04/12/2022 |
| DOB NOW | Construction Fence | Signed-off | SPLEN CONSTRUCTION INC | 03/22/2022 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 05/19/2023 | Permit Issued | L&L CONSTRUCTION DEVELOP | Heating Systems | Heating Williamson GWA-140 140,000 BTU · Boiler ×4 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/22/2022 | Complete | KJK ELECTRIC INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/19/2023 | Permit Issued | L&L CONSTRUCTION DEVELOP | Steel, Wood |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/19/2023 | Permit Issued | L&L CONSTRUCTION DEVELOP | Earthwork |
| Date | Type | Result | Report |
|---|---|---|---|
| 01/22/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 08/22/2023 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 08/21/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 06/13/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/08/2022 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 07/08/2022 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 07/08/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/08/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/24/2023 | Air barrier continuity plan testing | MEHDI GHAZI | energy_progress |
| 05/24/2023 | Metering | MEHDI GHAZI | energy_progress |
| 05/24/2023 | Electric vehicle service equipment requirements | MEHDI GHAZI | energy_progress |
| 05/24/2023 | Final | MEHDI GHAZI | progress |
| 05/24/2023 | Footing and Foundation | MEHDI GHAZI | progress |
| 05/24/2023 | Energy Code Compliance Inspections | MEHDI GHAZI | progress |
| 05/24/2023 | Fenestration air leakage | MEHDI GHAZI | energy_progress |
| 05/24/2023 | HVAC-R and service water piping design and insulation | MEHDI GHAZI | energy_progress |
| 05/24/2023 | Maintenance information | MEHDI GHAZI | energy_progress |
| 05/24/2023 | Fenestration areas | MEHDI GHAZI | energy_progress |
| 05/24/2023 | Fire-Resistance Rated Construction | MEHDI GHAZI | progress |
| 05/24/2023 | Duct leakage testing, insulation and design | MEHDI GHAZI | energy_progress |
| 05/24/2023 | Insulation placement and R values | MEHDI GHAZI | energy_progress |
| 05/24/2023 | HVAC-R and service water heating system controls | MEHDI GHAZI | energy_progress |
| 05/24/2023 | Permanent certificate | MEHDI GHAZI | energy_progress |
| 05/24/2023 | Air barrier - visual inspection | MEHDI GHAZI | energy_progress |
| 05/24/2023 | HVAC-R and service water heating equipment | MEHDI GHAZI | energy_progress |
| 05/24/2023 | Interior lighting power | MEHDI GHAZI | energy_progress |
| 05/24/2023 | Fenestration and door U-factor and product ratings | MEHDI GHAZI | energy_progress |
| 05/24/2023 | Air barrier — testing | MEHDI GHAZI | energy_progress |
| 05/24/2023 | Ventilation and air distribution system | MEHDI GHAZI | energy_progress |
| 05/24/2023 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | MEHDI GHAZI | special |
| 05/24/2023 | Fire-Resistant Penetrations and Joints | MEHDI GHAZI | special |
| 05/24/2023 | Concrete - Cast-In-Place | MEHDI GHAZI | special |
| 05/24/2023 | Structural Steel - Details | MEHDI GHAZI | special |