Roof1p · 2 filings · 16 docs
ArchitectureMechanical
Issued Permit Scope
General Construction · Mechanical Systems
Application filed for Exterior Facade/structural probes as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
12 documents · 1 drawing sheet
FILING HEREWITH DRAWINGS TO REPLACING TWO (2) COOLING TOWERS ON EXISTING DUNNAGE, IN-KIND, AT THE FIFTH FLOOR LEVEL ROOF TERRACE ADJACENT TO THE SOUTH (COURTYARD) FACADE.
On file for this project
4 documents
Bulkhead4p · 1 filing · 12 docs
Architecture
Application filed for Exterior Facade/structural probes as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
12 documents · 4 drawing sheets
Floor 351p · 1 filing · 4 docs
Structural
APPLICATION FILED FOR STRUCTURAL MODIFICATION/ADDITIONS (Installation of supplemental framing for support of moving partition.) ON THE 34TH FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
Floor 347p · 4 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers · Structural
APPLICATION FILED FOR PLUMBING & SPRINKLER MODIFICATIONS/ADDITIONS ON THE 34TH FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
10 documents · 2 drawing sheets
APPLICATION FILED FOR MECHANICAL MODIFICATIONS/ADDITIONS ON THE 34TH FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
5 documents · 2 drawing sheets
APPLICATION FILED FOR INTERIOR RENOVATION OF NON-LOAD BEARING PARTITIONS, CEILINGS, AND FINISHES ON THE 34TH FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
4 documents · 3 drawing sheets
Latest 3 of 4 filings on this floor.
Floor 33
Floor 32
Floor 31
Floor 3011p · 3 filings · 20 docs
ArchitectureDMElectricalFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing
APPLICATION FILED FOR MECHANICAL MODIFICATIONS/ADDITIONS ON THE 30TH FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
7 documents · 2 drawing sheets
APPLICATION FILED FOR PLUMBING & SPRINKLER MODIFICATIONS/ADDITIONS ON THE 30TH FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
6 documents · 4 drawing sheets
APPLICATION FILED FOR INTERIOR RENOVATION OF NON-LOAD BEARING PARTITIONS, CEILINGS, AND FINISHES ON THE 30TH FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
7 documents · 5 drawing sheets
Floor 29
Floor 28
Floor 27
Floor 26
Floor 259p · 3 filings · 17 docs
ArchitectureDMElectricalFire ProtectionGeneralOther
Issued Permit Scope
General Construction · Sprinklers
APPLICATION FILED FOR SPRINKLER MODIFICATIONS/ADDITIONS ON THE 25TH FLOOR (CRUMILLER) AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
APPLICATION FILED FOR INTERIOR RENOVATION OF NON-LOAD BEARING PARTITIONS, CEILINGS, AND FINISHES ON THE 25TH FLOOR (CRUMILLER) AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
8 documents · 6 drawing sheets
Removal and disposal of interior partitions, doors, suspended ceilings and finishes on the 25th floor as per plans. No change to use, egress or occupancy.
On file for this project
5 documents · 3 drawing sheets
Floor 24
Floor 23
Floor 22
Floor 212 filings · 5 docs
Fire ProtectionMechanical
Issued Permit Scope
Mechanical Systems · Sprinklers
Modifications to the existing sprinkler system on the 20th and 21st floor as per plans. No change to use, egress or occupancy.
On file for this project
3 documents
IN-KIND REPLACEMENT OF A HVAC UNIT ON THE 21st FLOOR.
On file for this project
2 documents
Floor 202p · 3 filings · 12 docs
ArchitectureFire ProtectionMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
Modifications to the existing sprinkler system on the 20th and 21st floor as per plans. No change to use, egress or occupancy.
On file for this project
3 documents · 2 drawing sheets
Minor demolition with patch and repair of drywall, paint and installation of lighting on the 20th floor as per plans. No change to use, egress or occupancy.
On file for this project
5 documents
HVAC removals on the 20th floor as per plans. No change to use, egress or occupancy.
On file for this project
4 documents
Floor 19
Floor 18
Floor 17
Floor 167p · 4 filings · 16 docs
ArchitectureElectricalFire ProtectionGeneralMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Modifications to the existing plumbing system on the 16th floor (DOT) as per plans. No change to use, egress or occupancy.
On file for this project
4 documents · 1 drawing sheet
Modifications to the existing sprinkler system on the 15th and 16th floors (DOT) as per plans. No change to use, egress or occupancy.
On file for this project
3 documents · 2 drawing sheets
Minor demolition with installation of new partitions, doors, suspended ceilings and finishes on the 16th floor (DOT) as per plans. No change to use, egress or occupancy.
On file for this project
12 documents · 2 drawing sheets
Latest 3 of 4 filings on this floor.
Floor 1514p · 9 filings · 19 docs
ArchitectureDMElectricalFire ProtectionGeneralMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
filing herewith sprinkler modifications to an existing commercial space located on the 15th floor as per plans
On file for this project
4 documents · 1 drawing sheet
Filing herewith general construction to include minor demo and interior renovation of an existing commercial space as per plans
On file for this project
4 documents · 5 drawing sheets
Filing herewith mechanical modifications to an existing commercial space located on the 15th fl as per plans
On file for this project
11 documents · 1 drawing sheet
Latest 3 of 9 filings on this floor.
Floor 1418p · 3 filings · 20 docs
ArchitectureCivilDMElectricalFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
APPLICATION FILED FOR PLUMBING/SPRINKLER MODIFICATIONS/ADDITIONS ON THE 14TH FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
12 documents · 4 drawing sheets
APPLICATION FILED FOR MECHANICAL MODIFICATIONS/ADDITIONS ON THE 14TH FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
12 documents · 3 drawing sheets
APPLICATION FILED FOR INTERIOR RENOVATION OF NON-LOAD BEARING PARTITIONS, CEILINGS, AND FINISHES ON THE 14TH FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
16 documents · 11 drawing sheets
Floor 13
Floor 12
Floor 11
Floor 10
Floor 93p · 2 filings · 16 docs
Fire ProtectionMechanicalPlumbing
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers
Application filed for plumbing work at 9th floor as shown on plans filed herewith.
On file for this project
12 documents · 1 drawing sheet
Application filed for sprinkler work at 9th floor as shown on plans filed herewith.
On file for this project
8 documents · 2 drawing sheets
Floor 8
Floor 713p · 5 filings · 16 docs
ArchitectureDMFire ProtectionGeneralMechanicalPlumbingOther
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Modifications to the existing sprinkler system on the 7th floor as per plans. No change to use, egress or occupancy.
On file for this project
4 documents · 2 drawing sheets
Modifications to the existing plumbing system on the 7th floor as per plans. No change to use, egress or occupancy.
On file for this project
4 documents · 2 drawing sheets
Modifications to the existing HVAC system on the 7th floor as per plans. No change to use, egress or occupancy.
On file for this project
8 documents · 1 drawing sheet
Latest 3 of 5 filings on this floor.
Floor 6
Floor 513p · 7 filings · 16 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
filing herewith mechanical modifications to an existing commercial space located on the 5th fl, suite 505
On file for this project
6 documents · 1 drawing sheet
filing herewith interior renovation to an existing commercial space located on 5th fl, suite 505
On file for this project
9 documents · 3 drawing sheets
filing herewith sprinkler modifications to an existing commercial space located on the 5th fl, suite 505
On file for this project
3 documents · 1 drawing sheet
Latest 3 of 7 filings on this floor.
Floor 41p · 1 filing · 4 docs
Mechanical
Issued Permit Scope
Mechanical Systems
AC replacement and louver relocation on the 4th floor as per plans. No change to use, egress or occupancy.
On file for this project
4 documents · 1 drawing sheet
Floor 3
Floor 2
Floor 11p · 1 filing · 4 docs
Mechanical
Issued Permit Scope
Mechanical Systems
application filed herewith to replace 4 ceiling hung hvac units at ground floor.
On file for this project
4 documents · 1 drawing sheet
Cellar3p · 2 filings · 20 docs
Fire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Structural
APPLICATION FILED FOR STRUCTURAL MODIFICATIONS/ADDITIONS (REINFORCEMENT) IN THE CELLAR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
16 documents · 3 drawing sheets
Modifications to the existing plumbing system in the basement and cellar levels as per plans. No change to use, egress or occupancy.
On file for this project
4 documents
Basement1p · 1 filing · 4 docs
Plumbing
Modifications to the existing plumbing system in the basement and cellar levels as per plans. No change to use, egress or occupancy.
On file for this project
4 documents · 1 drawing sheet
Sub-Basement1 filing · 4 docs
Plumbing
Issued Permit Scope
Plumbing
Modifications to the existing plumbing system in the basement and cellar levels as per plans. No change to use, egress or occupancy.
On file for this project
4 documents
Site & exterior5 filings · 20 docs
ArchitectureCivilEquipmentGeneralPlumbingStructural
Issued Permit Scope
General Construction · Sidewalk Shed · Sign · Structural · Supported Scaffold
INSTALLATION OF SIDEWALK SHED FOR PEDESTRIAN SAFETY DURING CONSTRUCTION. SIDEWALK SHED SHALL COMPLY WITH NYCC 2022 CHAPTER 33 . NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
On file for this project
2 documents · 6 drawing sheets
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents · 5 drawing sheets
Application filed for Exterior Facade/structural probes as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
12 documents · 12 drawing sheets
Latest 3 of 5 filings on this floor.
Filed — no permit issued2 filings · 20 docs
ArchitectureCivilDMGeneralMechanicalStructural
Sidewalk wearing course, curb and limited roadway paving replacement at Court Street & Montague Street frontages over vault water proofing and below grade sidewalk vault structural work and spalling concrete repair repairs under separate tandem app.
On file for this project
12 documents · 12 drawing sheets
Below grade sidewalk vault structural work and spalling concrete repairs work in association with tandem application for Sidewalk wearing course, curb and limited roadway paving at Court Street & Montague Street frontages over vault water proofing
On file for this project
9 documents · 12 drawing sheets