| Owner | Filings | Most Recent |
|---|---|---|
| 16 EAST 80TH HOUSING | 1 | 03/22/2026 |
| 16 EAST 80TH HOUSING WALL | 1 | 03/22/2026 |
| WALLCK MANAGEMENT CO | 6 | 03/22/2026 |
| 16 EAST 80 ST | 1 | 03/22/2026 |
| 16 EAST 80THSTREET HOUSING | 15 | 03/21/2026 |
| 16 E80TH ST HOUSING CORP C O WAL | 3 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| SSA+D | 2 | 03/20/2026 |
| MM ARCHITECTURE DPC | 8 | 12/09/2025 |
| TAN ENGINEERING PC | 1 | 10/10/2024 |
| STONE ENGINEERING & ARCHITECTURE DP | 1 | 10/10/2024 |
| BERNARD OCASIO ARCHITECT, P.C. | 2 | 12/07/2023 |
| MICHAEL MUROFF ARCHITECT LLC | 1 | 03/17/2023 |
| ROYAL ENGINEERING, P.C | 4 | 08/03/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| GREEN LIGHT EXPEDITING LLC | 20 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| PHOENIX SUTTON STR INC | General Contractor | 6 | 07/08/2026 |
| AMERICAN FIRE RESTORATION | General Contractor | 6 | 03/21/2026 |
| JUPITER INTERIORS INC | General Contractor | 6 | 07/08/2026 |
| S.M. GODWIN INC | General Contractor | 4 | 07/08/2026 |
| NYC DESIGN & RENO LLC | General Contractor | 3 | 07/08/2026 |
| M C M PLBG & HTG, INC | Plumbing | 2 | 07/08/2026 |
| LEONARD KRITZ | Electrical | 2 | 03/21/2026 |
| AUTHENTIC PLBG CORP | Plumbing | 1 | 07/08/2026 |
| LIAVIV CONSTRUCTION CORP | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SAHARAT SURATTANONT ARCHI | 1779 | 2 | 03/20/2026 |
| MANCINI DUFFY ARCHITECTUR | 2985 | 4 | 12/09/2025 |
| METRIC CONSULTING AND INS | 1803 | 2 | 10/10/2024 |
| TAN ENGINEERING, P.C. | 1291 | 1 | 10/10/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | NYC DESIGN & RENO LLC | 06/12/2026 |
| DOB NOW | Plumbing | Signed-off | AUTHENTIC PLBG CORP | 05/18/2026 |
| DOB NOW | General Construction | Signed-off | NYC DESIGN & RENO LLC | 05/13/2026 |
| DOB NOW | General Construction | Signed-off | NYC DESIGN & RENO LLC | 05/04/2026 |
| DOB NOW | General Construction | Signed-off | JUPITER INTERIORS INC | 08/28/2025 |
| DOB NOW | Structural | Signed-off | JUPITER INTERIORS INC | 11/07/2024 |
| DOB NOW | General Construction | Signed-off | JUPITER INTERIORS INC | 11/06/2024 |
| DOB NOW | Mechanical Systems | Signed-off | JUPITER INTERIORS INC | 11/06/2024 |
| DOB NOW | Plumbing | Signed-off | M C M PLBG & HTG, INC | 11/01/2024 |
| DOB NOW | Plumbing | Signed-off | M C M PLBG & HTG, INC | 08/02/2024 |
| DOB NOW | General Construction | Signed-off | JUPITER INTERIORS INC | 07/24/2024 |
| DOB NOW | General Construction | Signed-off | AMERICAN FIRE RESTORATION | 07/03/2024 |
| DOB NOW | General Construction | Signed-off | AMERICAN FIRE RESTORATION | 05/29/2024 |
| DOB NOW | General Construction | Permit Issued | LIAVIV CONSTRUCTION CORP | 05/28/2024 |
| DOB NOW | General Construction | Permit Issued | S.M. GODWIN INC | 04/26/2024 |
| DOB NOW | General Construction | Permit Issued | S.M. GODWIN INC | 03/04/2024 |
| DOB NOW | General Construction | Permit Issued | S.M. GODWIN INC | 02/07/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | PHOENIX SUTTON STR INC | 10/31/2018 |
| DOB NOW | Supported Scaffold | Signed-off | PHOENIX SUTTON STR INC | 10/30/2018 |
| DOB NOW | Supported Scaffold | Signed-off | PHOENIX SUTTON STR INC | 04/13/2018 |
| DOB NOW | Sidewalk Shed | Signed-off | PHOENIX SUTTON STR INC | 04/13/2018 |
| BIS | OT | ISSUED | PHOENIX SUTTON STR INC | 11/02/2018 |
| BIS | OT | ISSUED | PHOENIX SUTTON STR INC | 07/20/2018 |
| BIS | OT | ISSUED | DESIGN DEVELOPMENT NYC IN | 07/26/2017 |
| BIS | MH | ISSUED | DESIGN DEVELOPMENT NYC IN | 07/26/2017 |
| BIS | OT | ISSUED | DESIGN DEVELOPMENT NYC IN | 04/21/2017 |
| BIS | PL | ISSUED | ORBIT PLBG & HTG INC | 03/15/2017 |
| BIS | OT | ISSUED | DESIGN DEVELOPMENT NYC IN | 03/06/2017 |
| BIS | OT | ISSUED | CAMPBELL DESIGN & | 01/26/2016 |
| BIS | PL | ISSUED | HYDROKINETIC PLBG & HTG I | 12/29/2015 |
| BIS | OT | ISSUED | CAMPBELL DESIGN & | 12/17/2015 |
| BIS | PL | ISSUED | FRED SMITH P&H CO INC | 09/20/2013 |
| BIS | PL | ISSUED | COD PLUMBING CORP | 02/03/2011 |
| BIS | OT | ISSUED | BEECHWOOD CONSTRUCTION IN | 01/14/2011 |
| BIS | OT | ISSUED | DNA PLUMBING CONTRACTORS | 03/26/2008 |
| BIS | MH | ISSUED | BELLE ISLE CONSTRUCTION CORP | 10/25/2006 |
| BIS | PL | ISSUED | FRED SMITH P&H CO INC | 10/14/2005 |
| BIS | OT | ISSUED | BELLE ISLE CONSTRUC. CORP | 07/19/2005 |
| BIS | — | ISSUED | CUSTOM ASSOCIATES INC | 05/23/2005 |
| BIS | OT | ISSUED | CAMPBELL CONTRACTING INC | 05/25/2004 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/20/2026 | Signed-off | AUTHENTIC PLBG CORP | Water/Sanitary |
| 12/07/2023 | — | — | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/03/2024 | Complete | HIGH-LIGHT ELEC'L CORP | General Wiring |
| 08/03/2024 | Permit Issued | HIGH-LIGHT ELEC'L CORP | — |
| 05/14/2020 | Complete | GRAMERCY ELECTRIC INC | General Wiring |
| 02/26/2019 | Permit Issued | GRAMERCY ELECTRIC INC | General Wiring |
| 04/13/2018 | Permit Issued | MEO ELECTRIC CORP | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/28/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/26/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 08/26/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 11/26/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/29/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/22/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/22/2022 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 07/22/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/22/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/05/2026 | Fire-Resistant Penetrations and Joints | SAHARAT SURATTANONT | special |
| 03/03/2026 | Final | SAHARAT SURATTANONT | progress |
| 03/03/2026 | Fire-Resistant Penetrations and Joints | SAHARAT SURATTANONT | special |
| 12/29/2025 | Final | William Mandara | progress |
| 12/29/2025 | Fire-Resistance Rated Construction | William Mandara | progress |
| 12/23/2025 | Fire-Resistant Penetrations and Joints | William Mandara | special |
| 12/08/2025 | Fire-Resistance Rated Construction | William Mandara | progress |
| 12/08/2025 | Fire-Resistant Penetrations and Joints | William Mandara | special |
| 12/08/2025 | Final | William Mandara | progress |
| 10/28/2025 | Fire-Resistant Penetrations and Joints | William Mandara | special |
| 10/28/2025 | Final | William Mandara | progress |
| 10/28/2025 | Fire-Resistance Rated Construction | William Mandara | progress |
| 10/16/2025 | Final | William Mandara | progress |
| 10/16/2025 | Fire-Resistant Penetrations and Joints | William Mandara | special |
| 10/16/2025 | Fire-Resistance Rated Construction | William Mandara | progress |
| 08/26/2024 | Mechanical Systems | Roger Tan | special |
| 08/26/2024 | Final | Roger Tan | progress |
| 10/03/2023 | Energy Code Compliance Inspections | Anthony Farina | progress |
| 10/03/2023 | Lighting in dwelling units | Anthony Farina | energy_progress |
| 10/03/2023 | Final | Anthony Farina | progress |
| 10/03/2023 | Fire-Resistance Rated Construction | Anthony Farina | progress |
| 03/15/2023 | Fire-Resistant Penetrations and Joints | SAMI HAJJAR P.E | special |
| 03/15/2023 | Fire-Resistance Rated Construction | SAMI HAJJAR P.E | progress |
| 03/15/2023 | Tenant Protection Plan Compliance | SAMI HAJJAR P.E | special |
| 03/14/2023 | Final | SAMI HAJJAR P.E | progress |