Locations of Work
ArchitectureStructuralMechanicalPlumbing
Roof2p · 3 filings · 20 docs
Floor 31p · 1 filing · 9 docs
Floor 2
Floor 1
Cellar5p · 4 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
16 MONROE RESIDENCES1003/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SILVER GROUP103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
YAFE MEOD CORPGeneral Contractor507/08/2026
SAPPHIRE CONSTRUCTION GR*General Contractor303/21/2026
VERRAZANO PLMBG CONT INCPlumbing207/08/2026
PBS CONSTRUCTION CORPGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
H2 CONSULTING PE PC835101/11/2025
MARKANICS CORP4600806/09/2023
DEMERARA ENGINEERING, PLL4248108/09/2022
Building Lifecycle
All (97)Filed (11)Permit Issued (7)Signed Off (6)Violation (20)Inspection (7)Objection (16)Special Inspection (30)
02/24/2026
Signed off — Alteration
The construction of an approx. 500 sf aluminum deck over the existing roof on lt. ga. metal framing supported by steel beams
B01164315-I1
06/10/2025
Violation issued (HPD, closed)
A
05/06/2025
Permit issued — General Construction
B01164315-I1-GC
02/05/2025
Objection resolved — Addressed
02/05/2025
Objection resolved — Addressed
02/05/2025
Objection resolved — Addressed
02/05/2025
Objection resolved — Addressed
02/05/2025
Objection resolved — Addressed
01/14/2025
Objection raised — Other
01/14/2025
Objection raised — Other
01/14/2025
Objection raised — Other
01/14/2025
Objection raised — Other
01/14/2025
Objection raised — Other
01/11/2025
Filed — Alteration
The construction of an approx. 500 sf aluminum deck over the existing roof on lt. ga. metal framing supported by steel beams
B01164315-I1
01/11/2025
Special inspection requirement — Tenant Protection Plan Compliance
Harry Hong
01/08/2025
Special inspection requirement — Final
Anthony Takos
04/11/2024
Violation issued (HPD, closed)
A
11/17/2023
Violation issued (HPD, closed)
I
07/13/2023
Signed off — Alteration
Filing For HW Boiler
B08054256-I1
06/30/2023
Signed off — Alteration
Interior Renovation As Per Submitted Drawings. Combine Two Existing DU. No Change To Egress, Zoning, and C of O Proposed. The Department of Buildings does not require a new or amended certificate of occupancy for combining these apartments.
B00750428-I1
06/28/2023
Signed off — Alteration
INTERIOR RENOVATION. NO EXTERIOR WORK PROPOSED UNDER THIS APPLICATION
B00746154-I1
06/28/2023
Signed off — Alteration
Interior Renovation As Per Submitted Drawings. Combine Two Existing DU. No Change To Egress, Zoning, and C of O Proposed. The Department of Buildings does not require a new or amended certificate of occupancy for combining these apartments.
B00750428-S1
06/27/2023
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
06/21/2023
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
06/09/2023
Filed — Alteration
Filing For HW Boiler
B08054256-P4
06/06/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Malcolm Barkan
06/06/2023
Special inspection requirement — Energy Code Compliance Inspections
Malcolm Barkan
05/25/2023
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
05/19/2023
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
05/19/2023
Special inspection requirement — Energy Code Compliance Inspections
Malcolm Barkan
05/19/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Malcolm Barkan
05/19/2023
Special inspection requirement — Lighting in dwelling units
Malcolm Barkan
05/19/2023
Special inspection requirement — Interior lighting power
Malcolm Barkan
05/19/2023
Special inspection requirement — Lighting controls
Malcolm Barkan
05/16/2023
Filed — Alteration
Interior Renovation As Per Submitted Drawings. Combine Two Existing DU. No Change To Egress, Zoning, and C of O Proposed. The Department of Buildings does not require a new or amended certificate of occupancy for combining these apartments.
B00750428-P1
05/15/2023
Special inspection requirement — Interior lighting power
Malcolm Barkan
05/15/2023
Special inspection requirement — Lighting controls
Malcolm Barkan
05/15/2023
Special inspection requirement — Lighting in dwelling units
Malcolm Barkan
05/15/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Malcolm Barkan
05/15/2023
Special inspection requirement — Energy Code Compliance Inspections
Malcolm Barkan
05/04/2023
Signed off — Alteration
FILING HVAC SYSTEM FOR HEATING AND COOLING OF ALL DU IN THE BUILDING
B00848532-I1
05/02/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
05/02/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
04/28/2023
Permit issued — Boiler Equipment
B08054256-S1-BE
04/27/2023
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
03/29/2023
Permit issued — Mechanical Systems
B00848532-I1-MS
03/24/2023
Filed — Alteration
FILING HVAC SYSTEM FOR HEATING AND COOLING OF ALL DU IN THE BUILDING
B00848532-I1
03/24/2023
Violation issued (HPD, closed)
A
03/22/2023
Special inspection requirement — Energy Code Compliance Inspections
Malcolm Barkan
03/22/2023
Special inspection requirement — Final
CHARLES MALLEA
03/22/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Malcolm Barkan
03/22/2023
Special inspection requirement — Maintenance information
Malcolm Barkan
03/22/2023
Special inspection requirement — HVAC-R and service water heating system controls
Malcolm Barkan
03/22/2023
Special inspection requirement — Mechanical Systems
Malcolm Barkan
03/22/2023
Special inspection requirement — HVAC-R and service water heating equipment
Malcolm Barkan
03/17/2023
Filed — Alteration
Filing For HW Boiler
B08054256-P3
03/01/2023
Filed — Alteration
Filing For HW Boiler
B08054256-S1
03/01/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Malcolm Barkan
03/01/2023
Special inspection requirement — Heating Systems
Malcolm Barkan
02/13/2023
Filed — Alteration
Filing For HW Boiler
B08054256-P1
Latest 60 of 97 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offPBS CONSTRUCTION CORP05/06/2025
DOB NOWBoiler EquipmentPermit IssuedVERRAZANO PLMBG CONT INC04/28/2023
DOB NOWMechanical SystemsSigned-offSAPPHIRE CONSTRUCTION GR*03/29/2023
DOB NOWPlumbingSigned-offVERRAZANO PLMBG CONT INC01/17/2023
DOB NOWStructuralSigned-offYAFE MEOD CORP08/13/2022
DOB NOWGeneral ConstructionSigned-offYAFE MEOD CORP08/04/2022
DOB NOWGeneral ConstructionSigned-offYAFE MEOD CORP06/14/2022
BISPLISSUEDORBIT PLBG & HTG INC03/23/2018
BISOTISSUEDBIZON RUBBISH REMOVAL INC03/15/2018
BISPLISSUEDAMERICAN STANDARD P&H CORORP.11/16/2017
BISOTISSUEDHONEST & QUALITY CORP10/30/2017
BISPLISSUEDAMERICAN STANDARD P&H CORORP.09/20/2017
BISOTISSUEDHONEST & QUALITY CORP09/14/2017
1 project · most recent 06/09/2023
Gas Water/Sanitary
FiledStatusContractorScope
06/09/2023Permit IssuedVERRAZANO PLMBG CONT INCGas, Water/Sanitary
2 projects · most recent 07/03/2023
General Wiring
FiledStatusContractorScope
07/03/2023CompleteK.A.B. ELECTRIC CORPGeneral Wiring
02/15/2018CompleteE & M ELECTRICAL NY CORPGeneral Wiring
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
06/27/2023Pass-Final General Construction Non-Directive 14PassView ↗
06/21/2023Pass-Final General Construction Non-Directive 14PassView ↗
05/25/2023Fail-Final General Construction Non-Directive 14FailView ↗
05/19/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/02/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
05/02/2023Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
04/27/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 32
DateRequirementInspectorRole
01/11/2025Tenant Protection Plan ComplianceHarry Hongspecial
01/08/2025FinalAnthony Takosprogress
06/06/2023Fire-Resistant Penetrations and JointsMalcolm Barkanspecial
06/06/2023Energy Code Compliance InspectionsMalcolm Barkanprogress
05/19/2023Energy Code Compliance InspectionsMalcolm Barkanprogress
05/19/2023Fire-Resistant Penetrations and JointsMalcolm Barkanspecial
05/19/2023Lighting in dwelling unitsMalcolm Barkanenergy_progress
05/19/2023Interior lighting powerMalcolm Barkanenergy_progress
05/19/2023Lighting controlsMalcolm Barkanenergy_progress
05/15/2023Interior lighting powerMalcolm Barkanenergy_progress
05/15/2023Lighting controlsMalcolm Barkanenergy_progress
05/15/2023Lighting in dwelling unitsMalcolm Barkanenergy_progress
05/15/2023Fire-Resistant Penetrations and JointsMalcolm Barkanspecial
05/15/2023Energy Code Compliance InspectionsMalcolm Barkanprogress
03/22/2023Energy Code Compliance InspectionsMalcolm Barkanprogress
03/22/2023FinalCHARLES MALLEAprogress
03/22/2023Fire-Resistant Penetrations and JointsMalcolm Barkanspecial
03/22/2023Maintenance informationMalcolm Barkanenergy_progress
03/22/2023HVAC-R and service water heating system controlsMalcolm Barkanenergy_progress
03/22/2023Mechanical SystemsMalcolm Barkanspecial
03/22/2023HVAC-R and service water heating equipmentMalcolm Barkanenergy_progress
03/01/2023Fire-Resistant Penetrations and JointsMalcolm Barkanspecial
03/01/2023Heating SystemsMalcolm Barkanspecial
02/10/2023Fire-Resistant Penetrations and JointsMalcolm Barkanspecial
02/10/2023Energy Code Compliance InspectionsMalcolm Barkanprogress
Latest 25 of 32.
▾Documents — 174 on file (BIS + DOB NOW)
▸Plans & Drawings11
▸DOB NOWPlans/Sketch11
08/29/2026B00746154-I1Request digital key ↗
08/29/2026B00750428-S1Request digital key ↗
08/29/2026B00750428-P1Request digital key ↗
Showing 3 of 11 on file for this type
▸Applications & Permits32
▸BISWORK PERMIT APPLICATION11
03/26/2018321733754Open ↗
03/16/2018321733754Open ↗
03/16/2018321733754Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWLPC Approval/Permit10
08/29/2026B00746154-I1Open ↗
08/29/2026B00750428-P1Open ↗
08/29/2026B00750428-S1Open ↗
Showing 3 of 10 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION8
09/16/2022322099117Open ↗
03/13/2018321733754Open ↗
03/08/2018321733754Open ↗
Showing 3 of 8 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION3
02/12/2018321665756Open ↗
01/10/2018321665756Open ↗
10/25/2017321632961Open ↗
▸Seals & Professional Certifications38
▸DOB NOWDPL-1: Design Professional Seal & Signature11
08/29/2026B00746154-I1Open ↗
08/29/2026B00750428-P1Open ↗
08/29/2026B00750428-S1Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWProgress Inspector Seal & Signature11
09/02/2026B00750428-S1Open ↗
08/26/2026B08054256-P1Open ↗
08/26/2026B00750428-P1Open ↗
Showing 3 of 11 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION8
06/28/2018321733754Open ↗
06/28/2018321733754Open ↗
06/19/2018321733754Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature8
09/23/2026B08054256-S1Open ↗
09/02/2026B00750428-S1Open ↗
08/26/2026B08054256-P1Open ↗
Showing 3 of 8 on file for this type
▸Trade Schedules & Equipment6
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE4
03/08/2018321733754Open ↗
10/12/2017321665756Open ↗
09/14/2017321650343Open ↗
Showing 3 of 4 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT1
03/23/2018321665756Open ↗
▸BISEQUIPMENT USE PERMITS1
03/23/2018321665756Open ↗
▸Safety & Tenant Protection4
▸BISTenant Protection Plan and Notes4
03/08/2018321733754Open ↗
10/12/2017321665756Open ↗
09/14/2017321650343Open ↗
Showing 3 of 4 on file for this type
▸Environmental & Asbestos15
▸DOB NOWDEP ACP-5: Asbestos Assessment Report11
08/29/2026B00746154-I1Open ↗
08/29/2026B00750428-S1Open ↗
08/29/2026B00750428-P1Open ↗
Showing 3 of 11 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)4
03/08/2018321733754Open ↗
10/12/2017321665756Open ↗
09/14/2017321650343Open ↗
Showing 3 of 4 on file for this type
▸Energy Compliance10
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS6
06/19/2018321733754Open ↗
03/07/2018321665756Open ↗
11/28/2017321632961Open ↗
Showing 3 of 6 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS3
06/19/2018321733754Open ↗
03/07/2018321665756Open ↗
11/28/2017321632961Open ↗
▸DOB NOWEN2: As Built Energy Analysis1
08/14/2026B00750428-I1Open ↗
▸Inspections & Test Reports1
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX1
03/08/2018321733754Open ↗
▸Approvals, Objections & Sign-offs17
▸BISLETTERS - SUPPORTING DOCUMENTATION8
09/16/2022322099117Open ↗
09/16/2022322099117Open ↗
09/16/2022322099117Open ↗
Showing 3 of 8 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST5
06/28/2018321733754Open ↗
06/19/2018321733754Open ↗
03/23/2018321665756Open ↗
Showing 3 of 5 on file for this type
▸BISLANDMARKS APPROVAL3
03/13/2018321733754Open ↗
10/31/2017321665756Open ↗
08/29/2017321632961Open ↗
▸BISSCHEDULE A - OCCUPANCY / USE1
09/16/2022322099117Open ↗
▸Cost, Insurance & Ownership11
▸BISCOST AFFIDAVIT7
06/19/2018321733754Open ↗
03/08/2018321733754Open ↗
03/07/2018321665756Open ↗
Showing 3 of 7 on file for this type
▸BISHIC LICENSE OR AFFIDAVIT4
03/16/2018321733754Open ↗
10/31/2017321665756Open ↗
09/20/2017321632961Open ↗
Showing 3 of 4 on file for this type
▸Filing & Intake Forms16
▸BISBOROUGH INTAKE FORM7
06/28/2018321733754Open ↗
06/19/2018321733754Open ↗
03/23/2018321665756Open ↗
Showing 3 of 7 on file for this type
▸BISEFILING COVER SHEET5
09/16/2022322099117Open ↗
03/08/2018321733754Open ↗
10/12/2017321665756Open ↗
Showing 3 of 5 on file for this type
▸BISADDITIONAL INFORMATION4
09/16/2022322099117Open ↗
02/21/2018321665756Open ↗
01/18/2018321665756Open ↗
Showing 3 of 4 on file for this type
▸Other Documents13
▸DOB NOWDHCR Document12
08/29/2026B00746154-I1Open ↗
08/29/2026B00750428-S1Open ↗
08/29/2026B00750428-P1Open ↗
Showing 3 of 12 on file for this type
▸BISPLOT DIAGRAM1
09/16/2022322099117Open ↗