← Back
One story - permanent living quarter
16 WEST 16 ROAD
QUEENS · BIN 4297171
💬 Discuss this project
1925Year Built
1Stories
A2Building Class
R3AZoning
893 sfGross Floor Area
1Units
One story - permanent living quarter · 2,500 sf lot · 0.36 FAR built · Flood zone AE
Locations of Work
ArchitectureElectricalGeneral
Roof5p · 2 filings · 10 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
10/22/2021$319K—Private party → Private party$358/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TOM PETERSEN ARCHITECT, LLC210/16/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SUNCO CAPITAL403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SUNCO CAPITAL LLCGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
THOMAS PETERSEN ARCHITECT7854110/16/2025
Building Lifecycle
All (22)Filed (2)Permit Issued (1)Inspection (2)Objection (7)Special Inspection (10)
01/14/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
12/04/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
11/06/2025
Permit issued — Solar
Q01303218-I1-SL
11/03/2025
Objection resolved — Resolved
10/28/2025
Objection resolved — Resolved
10/17/2025
Objection raised — Inspections
10/17/2025
Objection raised — Other
10/17/2025
Objection raised — Electrical
10/17/2025
Objection raised — Other
10/17/2025
Objection raised — Other
10/16/2025
Filed — Alteration
Q01303218-I1
10/15/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
TOM PETERSEN
10/15/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
TOM PETERSEN
10/15/2025
Special inspection requirement — Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)
TOM PETERSEN
10/15/2025
Special inspection requirement — Energy Code Compliance Inspections
TOM PETERSEN
10/15/2025
Special inspection requirement — Final
TOM PETERSEN
10/15/2025
Special inspection requirement — Air barrier - visual inspection
TOM PETERSEN
10/14/2025
Filed — Alteration
INSTALLATION OF SOLAR PANELS ON ROOF. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
Q01300913-I1
10/10/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
10/10/2025
Special inspection requirement — Energy Code Compliance Inspections
10/10/2025
Special inspection requirement — Final
10/10/2025
Special inspection requirement — Air barrier - visual inspection
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarPermit IssuedSUNCO CAPITAL LLC11/06/2025
1 project · most recent 10/14/2025
FiledStatusContractorScope
10/14/2025Permit IssuedBERGER QUALITY ELEC'L CON—
1 project · most recent 10/14/2025
FiledStatusContractorScope
10/14/2025——32 panels, 13.76 kw, 938 roof_area_sqft
▾Field Inspections (DOB CAP) — 2
DateTypeResultReport
01/14/2026Pass-Final CND-Occupancy InspectionPassView ↗
12/04/2025Pass-Final CND-Occupancy InspectionPassView ↗
▾Special Inspection Requirements (DOB NOW) — 10
DateRequirementInspectorRole
10/15/2025Fire-Resistant Penetrations and JointsTOM PETERSENspecial
10/15/2025Structural Stability – Alterations of existing buildingsTOM PETERSENspecial
10/15/2025Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)TOM PETERSENspecial
10/15/2025Energy Code Compliance InspectionsTOM PETERSENprogress
10/15/2025FinalTOM PETERSENprogress
10/15/2025Air barrier - visual inspectionTOM PETERSENenergy_progress
10/10/2025Fire-Resistant Penetrations and Joints—special
10/10/2025Energy Code Compliance Inspections—progress
10/10/2025Final—progress
10/10/2025Air barrier - visual inspection—energy_progress
▾Documents — 10 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/18/2026Q01303218-I1Request digital key ↗
08/15/2026Q01300913-I1Request digital key ↗
▸Seals & Professional Certifications6
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/18/2026Q01300913-I1Open ↗
08/13/2026Q01303218-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
08/27/2026Q01303218-I1Open ↗
08/27/2026Q01303218-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/27/2026Q01303218-I1Open ↗
08/27/2026Q01303218-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026Q01303218-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01300913-I1Open ↗