| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/01/2026 | Permit Issued | 5 BORO'S PLUMBING INC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/21/2026 | Permit Issued | AMBER ELECTL CONTNG INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/01/2026 | Permit Issued | 5 BORO'S PLUMBING INC | Steel |
| Owner | Filings | Most Recent |
|---|---|---|
| BH SUCCESS GROUP | 3 | 04/09/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 12/30/2025 | $603K | — | — → — | $300/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| ASR ENGINEERING PC | 4 | 06/01/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ACE GROUP NY CORP | General Contractor | 4 | 06/28/2026 |
| ZONE PLUMBING & HEATING C | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ASR ENGINEERING PC | 8404 | 3 | 06/01/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | ZONE PLUMBING & HEATING C | 05/01/2026 |
| DOB NOW | Structural | Permit Issued | ACE GROUP NY CORP | 04/22/2026 |
| DOB NOW | Foundation | Permit Issued | ACE GROUP NY CORP | 04/22/2026 |
| DOB NOW | General Construction | Permit Issued | ACE GROUP NY CORP | 04/22/2026 |
| DOB NOW | Construction Fence | Permit Issued | ACE GROUP NY CORP | 02/11/2026 |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/02/2026 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 07/02/2026 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 07/02/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/02/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 06/29/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 05/18/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/18/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 05/11/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 03/13/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/26/2026 | Structural Stability – Alterations of existing buildings | AKM RAHMAN | special |
| 06/26/2026 | Structural Steel - Details | AKM RAHMAN | special |
| 06/26/2026 | Concrete - Cast-In-Place | AKM RAHMAN | special |
| 06/26/2026 | Fire-Resistant Penetrations and Joints | AKM RAHMAN | special |
| 06/26/2026 | Fire-Resistance Rated Construction | AKM RAHMAN | progress |
| 06/26/2026 | Energy Code Compliance Inspections | AKM RAHMAN | progress |
| 06/26/2026 | Final | AKM RAHMAN | progress |
| 06/26/2026 | Footing and Foundation | AKM RAHMAN | progress |
| 06/26/2026 | Fenestration areas | AKM RAHMAN | energy_progress |
| 06/26/2026 | Fenestration air leakage | AKM RAHMAN | energy_progress |
| 06/26/2026 | Maintenance information | AKM RAHMAN | energy_progress |
| 06/26/2026 | Permanent certificate | AKM RAHMAN | energy_progress |
| 06/26/2026 | Air barrier - visual inspection | AKM RAHMAN | energy_progress |
| 06/26/2026 | Interior lighting power | AKM RAHMAN | energy_progress |
| 06/26/2026 | Insulation placement and R values | AKM RAHMAN | energy_progress |
| 06/26/2026 | Fenestration and door U-factor and product ratings | AKM RAHMAN | energy_progress |
| 05/31/2026 | Fenestration air leakage | AKM RAHMAN | energy_progress |
| 05/31/2026 | Fenestration and door U-factor and product ratings | AKM RAHMAN | energy_progress |
| 05/31/2026 | Interior lighting power | AKM RAHMAN | energy_progress |
| 05/31/2026 | Maintenance information | AKM RAHMAN | energy_progress |
| 05/31/2026 | Air barrier - visual inspection | AKM RAHMAN | energy_progress |
| 05/31/2026 | Fenestration areas | AKM RAHMAN | energy_progress |
| 05/31/2026 | Permanent certificate | AKM RAHMAN | energy_progress |
| 05/31/2026 | Concrete - Cast-In-Place | AKM RAHMAN | special |
| 05/31/2026 | Fire-Resistant Penetrations and Joints | AKM RAHMAN | special |