← Back
Five to six families
160 BRADFORD STREET
BROOKLYN · BIN 3083568
💬 Discuss this project
1928Year Built
3Stories
C2Building Class
R6BZoning
5,781 sfGross Floor Area
6Units
Rent Stabilized35 Open Violations ▸
Five to six families · 3,150 sf lot · 1.84 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingGeneral
Permit Issued — active, not yet Signed-off
RoofUnder Construction12p · 1 filing · 20 docs
Floor 3Under Construction29p · 1 filing · 20 docs
Floor 2Under Construction30p · 1 filing · 20 docs
Floor 1Under Construction30p · 1 filing · 20 docs
CellarUnder Construction30p · 1 filing · 20 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
01/29/2026$875K—Private party → BRADFORD BLOCK LLC$151/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
LESTER KATZ, NCARB207/31/2026
CHOSEN MEP, CORP.207/28/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
MOGR CONSULTING INCGeneral Contractor308/20/2026
KISHAN PLUMBING INCPlumbing109/16/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HRF SERVICES CORP5616407/31/2026
Building Lifecycle
All (102)Filed (4)Permit Issued (4)Violation (44)Inspection (2)Objection (18)Special Inspection (30)
09/15/2026
Permit issued — Plumbing
B01393419-S2-PL
08/19/2026
Permit issued — General Construction
B01393419-I1-GC
08/14/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
SHAHRIAR QUAYYUM
08/14/2026
Special inspection requirement — Interior lighting power
SHAHRIAR QUAYYUM
08/14/2026
Special inspection requirement — Air barrier - visual inspection
SHAHRIAR QUAYYUM
08/14/2026
Special inspection requirement — Exterior lighting power
SHAHRIAR QUAYYUM
08/14/2026
Special inspection requirement — Metering
SHAHRIAR QUAYYUM
08/14/2026
Special inspection requirement — Lighting controls
SHAHRIAR QUAYYUM
08/14/2026
Special inspection requirement — Fenestration air leakage
SHAHRIAR QUAYYUM
08/14/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
SHAHRIAR QUAYYUM
08/14/2026
Special inspection requirement — Fenestration areas
SHAHRIAR QUAYYUM
08/14/2026
Special inspection requirement — Lighting in dwelling units
SHAHRIAR QUAYYUM
08/14/2026
Special inspection requirement — Energy Code Compliance Inspections
SHAHRIAR QUAYYUM
08/14/2026
Special inspection requirement — Final
SHAHRIAR QUAYYUM
08/14/2026
Special inspection requirement — Fire-Resistance Rated Construction
SHAHRIAR QUAYYUM
08/13/2026
Permit issued — Mechanical Systems
B01393419-S1-MS
08/12/2026
Objection resolved — Resolved
08/12/2026
Objection resolved — Resolved
08/04/2026
Objection raised — Scope
08/04/2026
Objection raised — Cost
08/03/2026
Objection resolved — Addressed
07/31/2026
Filed — Alteration
Mechanical work
B01393419-P1
07/30/2026
Special inspection requirement — Lighting in dwelling units
SHAHRIAR QUAYYUM
07/30/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
SHAHRIAR QUAYYUM
07/30/2026
Special inspection requirement — Energy Code Compliance Inspections
SHAHRIAR QUAYYUM
07/30/2026
Special inspection requirement — Fire-Resistance Rated Construction
SHAHRIAR QUAYYUM
07/30/2026
Special inspection requirement — Final
07/30/2026
Special inspection requirement — Fenestration air leakage
SHAHRIAR QUAYYUM
07/30/2026
Special inspection requirement — Lighting controls
SHAHRIAR QUAYYUM
07/30/2026
Special inspection requirement — Fenestration areas
SHAHRIAR QUAYYUM
07/30/2026
Special inspection requirement — Air barrier - visual inspection
SHAHRIAR QUAYYUM
07/30/2026
Special inspection requirement — Interior lighting power
SHAHRIAR QUAYYUM
07/30/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
SHAHRIAR QUAYYUM
07/30/2026
Special inspection requirement — Exterior lighting power
SHAHRIAR QUAYYUM
07/30/2026
Special inspection requirement — Metering
SHAHRIAR QUAYYUM
07/29/2026
Objection raised — Cost
07/28/2026
Filed — Alteration
Mechanical work
B01393419-S2
07/28/2026
Special inspection requirement — HVAC-R and service water heating equipment
SHAHRIAR QUAYYUM
07/28/2026
Special inspection requirement — Maintenance information
SHAHRIAR QUAYYUM
07/28/2026
Special inspection requirement — Energy Code Compliance Inspections
SHAHRIAR QUAYYUM
07/28/2026
Special inspection requirement — Seismic Resistance of Plumbing, Mechanical, Fuel Gas, and Electrical Components
SHAHRIAR QUAYYUM
07/22/2026
Filed — Alteration
Mechanical work
B01393419-S1
07/06/2026
Permit issued — General Construction
B01393419-I1-GC
06/12/2026
Objection resolved — Addressed
06/12/2026
Objection resolved — Addressed
06/09/2026
Objection resolved — Addressed
06/09/2026
Objection resolved — Addressed
06/09/2026
Objection resolved — Addressed
05/27/2026
Objection resolved — Addressed
05/18/2026
Objection raised — Scope
05/18/2026
Objection raised — Inspections
05/18/2026
Objection raised — Scope
05/18/2026
Objection raised — Cost
05/18/2026
Objection raised — Scope
05/18/2026
Objection raised — Other
05/01/2026
Violation issued (HPD, open)
A
04/29/2026
Filed — Alteration
Mechanical work
B01393419-I1
02/11/2026
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
02/11/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
06/06/2025
Violation issued (HPD, open)
A
Latest 60 of 102 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedKISHAN PLUMBING INC09/15/2026
DOB NOWGeneral ConstructionPermit IssuedMOGR CONSULTING INC08/19/2026
DOB NOWMechanical SystemsPermit IssuedMOGR CONSULTING INC08/13/2026
DOB NOWGeneral ConstructionPermit IssuedMOGR CONSULTING INC07/06/2026
1 project · most recent 08/26/2026
General Wiring
FiledStatusContractorScope
08/26/2026Permit IssuedCLAIRMONT ELEC'L CONTR'GGeneral Wiring
▾Field Inspections (DOB CAP) — 2
DateTypeResultReport
02/11/2026Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
02/11/2026Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 44
DateRequirementInspectorRole
08/14/2026Fire-Resistant Penetrations and JointsSHAHRIAR QUAYYUMspecial
08/14/2026Interior lighting powerSHAHRIAR QUAYYUMenergy_progress
08/14/2026Air barrier - visual inspectionSHAHRIAR QUAYYUMenergy_progress
08/14/2026Exterior lighting powerSHAHRIAR QUAYYUMenergy_progress
08/14/2026MeteringSHAHRIAR QUAYYUMenergy_progress
08/14/2026Lighting controlsSHAHRIAR QUAYYUMenergy_progress
08/14/2026Fenestration air leakageSHAHRIAR QUAYYUMenergy_progress
08/14/2026Fenestration and door U-factor and product ratingsSHAHRIAR QUAYYUMenergy_progress
08/14/2026Fenestration areasSHAHRIAR QUAYYUMenergy_progress
08/14/2026Lighting in dwelling unitsSHAHRIAR QUAYYUMenergy_progress
08/14/2026Energy Code Compliance InspectionsSHAHRIAR QUAYYUMprogress
08/14/2026FinalSHAHRIAR QUAYYUMprogress
08/14/2026Fire-Resistance Rated ConstructionSHAHRIAR QUAYYUMprogress
07/30/2026Lighting in dwelling unitsSHAHRIAR QUAYYUMenergy_progress
07/30/2026Fire-Resistant Penetrations and JointsSHAHRIAR QUAYYUMspecial
07/30/2026Energy Code Compliance InspectionsSHAHRIAR QUAYYUMprogress
07/30/2026Fire-Resistance Rated ConstructionSHAHRIAR QUAYYUMprogress
07/30/2026Final—progress
07/30/2026Fenestration air leakageSHAHRIAR QUAYYUMenergy_progress
07/30/2026Lighting controlsSHAHRIAR QUAYYUMenergy_progress
07/30/2026Fenestration areasSHAHRIAR QUAYYUMenergy_progress
07/30/2026Air barrier - visual inspectionSHAHRIAR QUAYYUMenergy_progress
07/30/2026Interior lighting powerSHAHRIAR QUAYYUMenergy_progress
07/30/2026Fenestration and door U-factor and product ratingsSHAHRIAR QUAYYUMenergy_progress
07/30/2026Exterior lighting powerSHAHRIAR QUAYYUMenergy_progress
Latest 25 of 44.
▾Documents — 25 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/17/2026B01393419-P1Request digital key ↗
08/15/2026B01393419-S1Request digital key ↗
08/15/2026B01393419-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸Seals & Professional Certifications17
▸DOB NOWProgress Inspector Seal & Signature9
09/02/2026B01393419-S1Open ↗
09/02/2026B01393419-S1Open ↗
09/01/2026B01393419-I1Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/17/2026B01393419-S1Open ↗
08/17/2026B01393419-P1Open ↗
08/17/2026B01393419-S2Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
09/02/2026B01393419-S1Open ↗
09/01/2026B01393419-I1Open ↗
08/23/2026B01393419-S2Open ↗
Showing 3 of 4 on file for this type
▸Environmental & Asbestos4
▸DOB NOWDEP ACP-5: Asbestos Assessment Report4
08/17/2026B01393419-P1Open ↗
08/15/2026B01393419-S1Open ↗
08/15/2026B01393419-I1Open ↗
Showing 3 of 4 on file for this type