DOB11/14/2025VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL HGH PRESSURE INSPECTION
DOB11/14/2025VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL HGH PRESSURE INSPECTION
DOB11/14/2025VIOLATION ISSUED-FAILURE TO FILE 2024 INTERNAL HGH PRESSURE INSPECTION
DOB11/14/2025VIOLATION ISSUED-FAILURE TO FILE 2024 INTERNAL HGH PRESSURE INSPECTION
DOB09/23/2024VIOLATION ISSUED-FAILURE TO FILE 2023 EXTERNAL HGH PRESSURE INSPECTION
DOB09/23/2024VIOLATION ISSUED-FAILURE TO FILE 2023 INTERNAL HGH PRESSURE INSPECTION
DOB09/23/2024VIOLATION ISSUED-FAILURE TO FILE 2023 INTERNAL HGH PRESSURE INSPECTION
DOB09/23/2024VIOLATION ISSUED-FAILURE TO FILE 2023 EXTERNAL HGH PRESSURE INSPECTION
DOB06/30/2023VIOLATION ISSUED-FAILURE TO FILE 2021 INTERNAL HGH PRESSURE INSPECTION
DOB06/30/2023VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL HGH PRESSURE INSPECTION
DOB06/30/2023VIOLATION ISSUED-FAILURE TO FILE 2021 INTERNAL HGH PRESSURE INSPECTION
DOB06/30/2023VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL HGH PRESSURE INSPECTION
DOB06/30/2023VIOLATION ISSUED-FAILURE TO FILE 2020 INTERNAL HGH PRESSURE INSPECTION
DOB04/25/2023VIOLATION ISSUED-FAILURE TO FILE 2022 INTERNAL HIGH PRESSURE INSPECTION
DOB04/25/2023VIOLATION ISSUED-FAILURE TO FILE 2022 EXTERNAL HIGH PRESSURE INSPECTION
DOB03/16/2020VIOLATION ISSUED - FAILURE TO FILE 2017 INTERNAL HIGH PRESSURE BOILER INSPECTION
DOB11/04/2019V-DOB VIOLATION - ACTIVE
DOB11/01/2019V-DOB VIOLATION - ACTIVE
DOB09/06/2019VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2017 CAT 1 INSP/TST TST
DOB09/06/2019VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2017 CAT 1 INSP/TST TST
DOB09/06/2019VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2017 CAT 1 INSP/TST TST
DOB09/06/2019VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2017 CAT 1 INSP/TST TST
DOB04/05/2019VIOLATION ISSUED TO ELEVATOR - FAILURE TO FILE CATEGORY 1 2017 INSPECTION/TEST
DOB10/15/2018V-DOB VIOLATION - ACTIVE
DOB01/26/2018VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2016 CAT 1 INSP/TST
DOB01/26/2018VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2016 CAT 1 INSP/TST
DOB01/26/2018VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2016 CAT 1 INSP/TST
DOB01/26/2018VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2016 CAT 1 INSP/TST
DOB06/23/2017VIOLATION ISSUED FOR FAILURE TO FILE 2015 ANNUAL HIGH PRESSURE BOILER INSPECTION
DOB01/03/2017VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2015 CAT 1 INSP/TST
DOB01/03/2017VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2015 CAT 1 INSP/TST
DOB01/03/2017VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2015 CAT 1 INSP/TST
DOB11/14/2016VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2014 CAT 1 INSP/TST
DOB11/14/2016VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2014 CAT 1 INSP/TST
DOB11/14/2016VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2014 CAT 1 INSP/TST
DOB11/14/2016VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2014 CAT 1 INSP/TST
DOB11/14/2016VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2014 CAT 1 INSP/TST
DOB10/25/2016V-DOB VIOLATION - ACTIVE
DOB10/31/2014VIOLATION ISSUED TO ELEVATOR-FAILURE TO FILE CATEGORY 1 2013 INSPECTION/TEST
DOB10/31/2014VIOLATION ISSUED TO ELEVATOR-FAILURE TO FILE CATEGORY 1 2013 INSPECTION/TEST
DOB10/31/2014VIOLATION ISSUED TO ELEVATOR-FAILURE TO FILE CATEGORY 1 2013 INSPECTION/TEST
DOB10/31/2014VIOLATION ISSUED TO ELEVATOR-FAILURE TO FILE CATEGORY 1 2013 INSPECTION/TEST
DOB10/31/2014VIOLATION ISSUED TO ELEVATOR-FAILURE TO FILE CATEGORY 1 2013 INSPECTION/TEST
DOB05/15/2014VIOLATION ISSUED FOR FAILURE TO FILE 2012 ANNUAL HIGH PRESSURE BOILER INSPECTION
DOB03/31/2014VIOLATION ISSUED TO ELEVATOR-FAILURE TO FILE CATEGORY 1 2012 INSPECTION/TEST
DOB10/08/2010V-DOB VIOLATION - ACTIVE
DOB03/31/2008V-DOB VIOLATION - ACTIVE
DOB04/02/2007V-DOB VIOLATION - ACTIVE
DOB01/17/2007V-DOB VIOLATION - ACTIVE
DOB10/01/2005V-DOB VIOLATION - ACTIVE
DOB06/09/2004VW-VIOLATION WORK WITHOUT PERMIT - ACTIVE
DOB01/13/1997V-DOB VIOLATION - ACTIVE
DOB05/31/1994V-DOB VIOLATION - ACTIVE
DOB03/06/1990V-DOB VIOLATION - ACTIVE
DOB03/06/1990V-DOB VIOLATION - ACTIVE
DOB03/06/1990V-DOB VIOLATION - ACTIVE
DOB02/23/1989V-DOB VIOLATION - ACTIVE
DOB02/23/1989V-DOB VIOLATION - ACTIVE
DOB02/23/1989V-DOB VIOLATION - ACTIVE
DOB02/23/1989V-DOB VIOLATION - ACTIVE
DOB02/23/1989V-DOB VIOLATION - ACTIVE
DOB02/23/1989V-DOB VIOLATION - ACTIVE
DOB02/23/1989V-DOB VIOLATION - ACTIVE
ECB10/03/2025REISSUE #35689030L. EXIT DOOR NOT CLOSING. NOTED EXTERIOR DOOR AT GROUND FL STAIR C, LEADING TO STREET, WAS DIFFICULT TO OPEN W/O EXCESSIVE FORCE AND NOT SELF-CLOSING. REMEDY: REPAIR/REPLACE DOOR.Nothing owed — awaiting certificate of correction
ECB09/13/2024REISSUE#35665502Y DATE OF ISSUE:06.21.2022 EXIT DOOR NOT SELF CLOSING PROPERLY AT THE TIME OF INSPECTION,OBSERVED THAT AT STAIR C EXIT TO STREET LEVEL TWO EXIT DOOR NOT SELF CLOSING PROPERLY.AT STAIR A AT 1ST FNothing owed — awaiting certificate of correction
ECB06/21/2022REISSUE#35582311H ISSUED ON 7/21/2021.EXIT DOOR NOT SELF-CLOSING PROPERLY AT GROUND FLOOR MAIN ENTRANCE INSIDE.TWO EXIT DOORS NOT SELF-CLOSING AT GROUND FLOOR NEAR STAIR C.TWO OUTSIDE EXIT DOORS NOT SELF-CLOSINNothing owed — awaiting certificate of correction
ECB07/21/2021EXIT DOOR NOT SELF CLOSING PROPERLY AT GROUND FLOOR MAIN ENTRANCE ( INSIDE) TWO EXIT DOOR NOT SELF CLOSING PROPERLY AT GROUND FLOOR NEAR (STAIR-C) TWO OUTSIDE EIXT DOORS NOT SELF CLOSING PROPERLY AT THE TIME OFNothing owed — awaiting certificate of correction
ECB11/16/2016FAILURE TO MAINTAIN BLDG WALL(S) OR APPURTENANCES (EXTERIOR). NOTED: @ EXP#4 ON THE 140 STREET SIDE, OBSERVED STEP CRACKS & VERTICAL CRACKS THROUGHOUT STONE RETAINING WALL NEXT STAIR C EXIT DOOR. REM: MAINTAINNothing owed — awaiting certificate of correction
ECB11/16/2016FAILURE TO MAINTAIN BLDG IN CODE COMPLIANT MANNER (INTERIOR), NOTED: @ FLR B STAIR C OBSERVED WATER PENETRATION ALL AROUND INTERIOR OF THE EXIT DOOR RESULTING IN SPALLING PLASTER. REM: REPAIR &/OR REPLACE.Nothing owed — awaiting certificate of correction
ECB07/06/2015FAILURE TO MAINTAIN BLDG WALL(S) OR APPURTENANCES. VIOLATION #35086033Y ISSUED 3/12/14. FAILURE TO MAINTAIN BLDG WALL(S) & APPURTENANCES; WATER PENETRATING BLDG ENVELOPE AT VARIOUS LOCATION THROUGHOUT NORTH & SNothing owed — awaiting certificate of correction
ECB07/06/2015FAILURE TO MAINTAIN BLDG IN CODE COMPLIANT MANNER. VIOLATION #35086034X ISSUED ON 3/12/14. FAILURE TO MAINTAIN BLDG IN CODE COMPLIANT MANNER. PLASTER CEILINGS & WALLS ARE FLAKING & SPALLING IN ROOMS 201 & 202 &Nothing owed — awaiting certificate of correction
ECB03/12/2014FAILURE TO MAINTAIN BLDG IN CODE-COMPLIANT MANNER. NEAR STAIR "C" ADJACENT TO RM B12 AT LOCATION OF 6 RISERS NO HANDRAIL. ALSO ADJACENT TO RM C-01 AT LOCATION OF 7 RISERS, NO HANDRAIL. REMEDY; INSTALL HANDRAILSNothing owed — awaiting certificate of correction
ECB03/12/2014RE-ISSUE # 35015852J. FAILURE TO MAINTAIN BLDG IN CODE-COMPLIANT MANNER. PLASTER CEILINGS & WALLS ARE FLAKING & SPALLING IN ROOMS 201 & 202 & ALSO IN RMS B22 & B23 (LOCATED INSIDE RM B20). REMEDY: REPAIR WALLSNothing owed — awaiting certificate of correction
ECB03/12/2014RE-ISSUE ECB #35015853L.FAILURE TO MAINTAIN BLDG WALLS & APPURTENANCES:WATER PENETRATING BLDG ENVELOPE @ VARIOUS LOC THROUGHOUT NORTH & SOUTH WALLS.CRUMBLING PLASTER & SPALLING NOTEABLE IN RMS 202,201 & IN RMSNothing owed — awaiting certificate of correction
ECB03/12/2014RE-ISSUE ECB #35015851H.@ CELLAR LVL STAIR"C" NEXT TO RM C-01(PREVIOUSLY NOTED @ 1ST STORY)RIGHT HANDRAIL IS LOOSE & DOES NOT OFFER SUPPORT.REMEDY:SECURELY ATTACH HANDRAIL TO WALL.Nothing owed — awaiting certificate of correction
ECB04/17/2013WATER/WEATHER PENETRATING BUILDING ENVELOPE AT VARIOUS LOCATIONS THROUGHOUT NORTH ELEVATION. RMDY: MAINTAIN WEATHER PROOF INTEGRITY OF BLDG ENVELOPE.Nothing owed — awaiting certificate of correction
ECB04/17/2013REISSUE VIO #34847063M LOOSE HANDRAIL NOTED: AT 1ST STORY STAIR C RMDY: REPAIR DEFECT NOTED.Nothing owed — awaiting certificate of correction
ECB04/17/2013WATER DAMAGED PLASTER WALLS AND CEILINGS AT EXIT C VESTIBULE,AT ROOMS B23 AND B22 AT ROOMS 202,201 APPRX 400 SQUARE FEET OF PLASTER WATER DAMAGED.RMDY: REPAIR DEFECTS NOTED.Nothing owed — awaiting certificate of correction
ECB02/17/2012REISSUE # 34909638P. FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER. 1ST FLOOR STWY "D" (AKA EXIT # 2) HANDRAIL IS LOOSE. ALSO NOTE: PLASTER IS SPALLING & MISSING AT SAID EXIT DOOR AROUND THE FRAME. REMNothing owed — awaiting certificate of correction
ECB06/17/2010FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER. NOTE: 1ST FLOOR STWY "C" HANDRAIL IS LOOSE. ALSO NOTE PLASTER IS SPALLING AND MISSING AROUND DOOR FRAME OF EXIT NEAR STWY "C". REMEDY: REPAIR ALL DEFECTS.Nothing owed — awaiting certificate of correction
ECB05/07/2010REISSUE : 34792726Z, 34718792L 1ST FL STWY "C" HANDRAIL IS LOOSE NOT SECTED . ALSO NOT PLASTER IS SPALLING AND MISSING AROUND DOOR FRAME AT SAID EXIT DOOR. REMEDY : REPAIR ALL DEFECTSNothing owed — awaiting certificate of correction
ECB06/12/2009REISSUE: 34718792L. 1ST FLR STWY C HANDRAIL IS LOOSE NOT SECURED. ALSO NO PLASTER SPALLING & MISSING AROUND DOOR FRAME AT SAME EXIT. REMEDY: REPAIR/REPLACE HANDRAIL & PLASTER AROUND DOOR FRAME.Nothing owed — awaiting certificate of correction
ECB11/06/2008FAILURE TO MAINTAIN BLDG IN CODE COMPLIANT MANNER NOTE AT FIRST FLOOR STAIR C EXIT TO 140 ST HANDRAILS IS LOOSE & NOT SECURED PROPERLY & SPALLING & MISSING PLASTER AROUND DOOR FRAME REM: REPAIR/REPLACENothing owed — awaiting certificate of correction
ECB06/04/200383## REMOVED DEVICE 153780 WITHOUT PERMIT FILE FOR AND OBTAIN PERMITNothing owed — awaiting certificate of correction
ECB02/14/199203S,05M,05I,17L,35#,57O,62I,73X, (03) PLYWOOD WALL 05-PROVIDE GATE ON WEST SIDE OF OUR 35 REMOVE ALL NON-PERTIMENT/EQUIPMENT 73 RESTORE TO SERVICE & PERFORM 2 AND 5 YEAR TESTS.Nothing owed — awaiting certificate of correction