| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 03/29/2023 | $2.0M | — | — → — | $686/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| D'ANTONIO CONSULTING ENGINEERS | 3 | 08/07/2025 |
| RIGID STRUCTURAL DESIGN, LLC | 1 | 03/31/2025 |
| D'HUY ENGINEERING, INC. | 3 | 12/10/2024 |
| NEUHAUS DESIGN ARCHITECTURE, P.C. | 2 | 07/08/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| BMB BUILDING CONSULTING | 16 | 03/21/2026 |
| Rigid Structural Design, LLC | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| INFINITY CONSTRUCTION INC. | General Contractor | 11 | 07/08/2026 |
| INTERSYSTEMS INSTAL S&S | General Contractor | 3 | 03/21/2026 |
| Z.W. PLBG & HTG CORP | Plumbing | 2 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| D'ANTONIO CONSULTING ENGI | 931 | 3 | 08/07/2025 |
| MACIA INSPECTION & TESTIN | 402 | 3 | 12/10/2024 |
| JSPECS,INC | 9429 | 2 | 10/26/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Supported Scaffold | Signed-off | INTERSYSTEMS INSTAL S&S | 04/01/2025 |
| DOB NOW | Plumbing | Signed-off | Z.W. PLBG & HTG CORP | 03/24/2025 |
| DOB NOW | Structural | Signed-off | INFINITY CONSTRUCTION INC. | 01/15/2025 |
| DOB NOW | Mechanical Systems | Signed-off | INFINITY CONSTRUCTION INC. | 12/19/2024 |
| DOB NOW | General Construction | Signed-off | INFINITY CONSTRUCTION INC. | 12/10/2024 |
| DOB NOW | General Construction | Signed-off | INFINITY CONSTRUCTION INC. | 01/03/2024 |
| DOB NOW | Mechanical Systems | Signed-off | INFINITY CONSTRUCTION INC. | 01/02/2024 |
| DOB NOW | Plumbing | Signed-off | Z.W. PLBG & HTG CORP | 12/22/2023 |
| DOB NOW | General Construction | Signed-off | INFINITY CONSTRUCTION INC. | 12/13/2023 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/19/2025 | Complete | AE ELECTRIC INC | General Wiring |
| 11/04/2025 | Complete | AE ELECTRIC INC | General Wiring |
| 03/14/2024 | Cancelled | AE ELECTRIC INC | General Wiring |
| 12/14/2023 | Complete | AE ELECTRIC INC | — |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/07/2025 | Fire-Resistant Penetrations and Joints | GAETANO D'ANTONIO | special |
| 08/07/2025 | Final | GAETANO D'ANTONIO | progress |
| 08/07/2025 | Energy Code Compliance Inspections | GAETANO D'ANTONIO | progress |
| 08/07/2025 | Mechanical Systems | GAETANO D'ANTONIO | special |
| 08/07/2025 | Heating Systems | GAETANO D'ANTONIO | special |
| 12/23/2024 | Footing and Foundation | Jeffrey Stones | progress |
| 12/23/2024 | Structural Stability – Alterations of existing buildings | Jeffrey Stones | special |
| 12/23/2024 | Concrete - Cast-In-Place | Jeffrey Stones | special |
| 12/23/2024 | Subgrade Inspections | Jeffrey Stones | special |
| 12/23/2024 | Post-installed Anchors | Jeffrey Stones | special |
| 12/23/2024 | Structural Steel - Details | Jeffrey Stones | special |
| 12/23/2024 | Structural Steel - Welding | Jeffrey Stones | special |
| 12/23/2024 | Structural Steel - High Strength Bolting | Jeffrey Stones | special |
| 12/23/2024 | Fire-Resistant Penetrations and Joints | Jeffrey Stones | special |
| 12/23/2024 | Final | Jeffrey Stones | progress |
| 11/26/2024 | Concrete - Cast-In-Place | Jeffrey Stones | special |
| 11/26/2024 | Final | Jeffrey Stones | progress |
| 11/26/2024 | Footing and Foundation | Jeffrey Stones | progress |
| 11/26/2024 | Fire-Resistant Penetrations and Joints | — | special |
| 11/26/2024 | Post-installed Anchors | Jeffrey Stones | special |
| 11/26/2024 | Structural Stability – Alterations of existing buildings | Jeffrey Stones | special |
| 11/26/2024 | Structural Steel - Details | Jeffrey Stones | special |
| 11/26/2024 | Structural Steel - High Strength Bolting | Jeffrey Stones | special |
| 11/26/2024 | Structural Steel - Welding | Jeffrey Stones | special |
| 11/26/2024 | Subgrade Inspections | Jeffrey Stones | special |