BuildNYC
Elevator apt, semi-fireproof without stores
160 WEST 22ND STREET
MANHATTAN · BIN 1087810
💬 Discuss this project
2000Year Built
13Stories
D1Building Class
C6-3AZoning
41,423 sfGross Floor Area
51Units
LL97 CoveredRent Stabilized2 Active Violations 0 unresolved · 2 paperwork only 1 old, status unconfirmed ▸FISP: SAFE
Elevator apt, semi-fireproof without stores · Owner of record: 160 West 22nd Street · 4,938 sf lot · 8.39 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingEquipmentGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Floor 131p · 1 filing · 5 docs
Floor 12
Floor 11Unit 110211p · 2 filings · 20 docs
Floor 101p · 1 filing · 5 docs
Floor 9
Floor 8
Floor 7
Floor 6
Floor 5
Floor 4
Floor 3
Floor 2
Floor 1
Site & exteriorTemporary sidewalk shed installation31p · 2 filings · 7 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
160 West 22nd St3003/22/2026
122 West 21st Street203/21/2026
160 West 22 Street203/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Judge Architecture511/07/2024
Kevin Gallen PE108/28/2023
Ashraf110/10/2022
Cataldo Properties108/31/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Codegreen303/21/2026
Nexus Consulting NYC603/21/2026
Rigid Structural Design103/21/2026
Municipal Building Consultants103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Exclusive Restorationspecialty_contractor407/08/2026
Steel SystemsScaffold303/21/2026
HI-Tech Plumbing & HeatingPlumbing207/08/2026
MetroPlumbing207/08/2026
Pelham ConstructionGeneral Contractor107/08/2026
HLP ContractingGeneral Contractor107/08/2026
Arree ElectricElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Judge Architecture748511/07/2024
Assure Professional Engineering6962108/28/2023
Building Lifecycle
All (102)Filed (8)Permit Issued (7)Signed Off (3)Facade (FISP) (9)Violation (55)Inspection (3)Special Inspection (17)
01/06/2025
Signed off — Alteration
Mechanical work to be performed in existing unit #1102 on the 11th floor. Initial general construction & subsequent plumbing application have been filed. All in accordance with submitted plans. No changes to use, egress or occupancy under this application
M00878844-S1
11/07/2024
Filed — Alteration
Mechanical work to be performed in existing unit #1102 on the 11th floor. Initial general construction & subsequent plumbing application have been filed. All in accordance with submitted plans. No changes to use, egress or occupancy under this application
M00878844-P3
10/22/2024
Inspection — Pass-Final PL - More than 10 Requested Floors
Pass
View inspection ↗
07/26/2024
Signed off — Alteration
Mechanical work to be performed in existing unit #1102 on the 11th floor. Initial general construction & subsequent plumbing application have been filed. All in accordance with submitted plans. No changes to use, egress or occupancy under this application
M00878844-I1
07/25/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
06/26/2024
Permit issued — General Construction
M00878844-I1-GC
05/17/2024
Permit issued — Plumbing
M00878844-S1-PL
05/13/2024
Filed — Alteration
Mechanical work to be performed in existing unit #1102 on the 11th floor. Initial general construction & subsequent plumbing application have been filed. All in accordance with submitted plans. No changes to use, egress or occupancy under this application
M00878844-P2
05/10/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Rachael Judge
05/10/2024
Special inspection requirement — Energy Code Compliance Inspections
Rachael Judge
05/10/2024
Special inspection requirement — Final
Rachael Judge
05/10/2024
Special inspection requirement — Interior lighting power
Rachael Judge
05/10/2024
Special inspection requirement — Lighting in dwelling units
Rachael Judge
05/10/2024
Special inspection requirement — Lighting controls
Rachael Judge
04/29/2024
Filed — Alteration
Mechanical work to be performed in existing unit #1102 on the 11th floor. Initial general construction & subsequent plumbing application have been filed. All in accordance with submitted plans. No changes to use, egress or occupancy under this application
M00878844-P1
04/26/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Rachael Judge
01/07/2024
Violation issued (HPD, closed)
C
01/07/2024
Violation issued (HPD, closed)
C
01/07/2024
Violation issued (HPD, closed)
A
01/07/2024
Violation issued (HPD, closed)
C
01/07/2024
Violation issued (HPD, closed)
C
01/07/2024
Violation issued (HPD, closed)
C
01/07/2024
Violation issued (HPD, closed)
C
01/07/2024
Violation issued (HPD, closed)
B
01/07/2024
Violation issued (HPD, closed)
B
01/07/2024
Violation issued (HPD, closed)
A
10/26/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
09/18/2023
Permit issued — Plumbing
M00878844-S1-PL
08/28/2023
Filed — Alteration
Mechanical work to be performed in existing unit #1102 on the 11th floor. Initial general construction & subsequent plumbing application have been filed. All in accordance with submitted plans. No changes to use, egress or occupancy under this application
M00878844-S2
08/17/2023
Special inspection requirement — Maintenance information
STEVEN CHROSTOWSKI
08/17/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
GUNJAN KHANDWALA
08/17/2023
Special inspection requirement — Post-installed Anchors
GUNJAN KHANDWALA
08/17/2023
Special inspection requirement — HVAC-R and service water heating system controls
STEVEN CHROSTOWSKI
08/17/2023
Special inspection requirement — HVAC-R and service water piping design and insulation
STEVEN CHROSTOWSKI
08/17/2023
Special inspection requirement — Energy Code Compliance Inspections
STEVEN CHROSTOWSKI
08/17/2023
Special inspection requirement — HVAC-R and service water heating equipment
STEVEN CHROSTOWSKI
08/17/2023
Special inspection requirement — Duct leakage testing, insulation and design
STEVEN CHROSTOWSKI
07/17/2023
Special inspection requirement — Final
STEVEN CHROSTOWSKI
07/17/2023
Special inspection requirement — Mechanical Systems
GUNJAN KHANDWALA
07/07/2023
Permit issued — General Construction
M00878844-I1-GC
06/09/2023
Cycle 9 facade report submitted
06/09/2023
Cycle 9 facade report signed — SAFE
05/30/2023
Signed off — Alteration
M00797978-I1
05/26/2023
Filed — Alteration
Mechanical work to be performed in existing unit #1102 on the 11th floor. Initial general construction & subsequent plumbing application have been filed. All in accordance with submitted plans. No changes to use, egress or occupancy under this application
M00878844-S1
05/26/2023
Filed — Alteration
Mechanical work to be performed in existing unit #1102 on the 11th floor. Initial general construction & subsequent plumbing application have been filed. All in accordance with submitted plans. No changes to use, egress or occupancy under this application
M00878844-I1
05/15/2023
Cycle 9 facade inspection completed
04/18/2023
Permit issued — General Construction
M00797978-I1-GC
02/22/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/28/2022
Permit issued — General Construction
M00797978-I1-GC
10/19/2022
Permit issued — Sidewalk Shed
M08018140-I1-SH
10/10/2022
Filed — Alteration
Installation of temporary sidewalk shed as per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M08018140-I1
08/31/2022
Filed — Alteration
M00797978-I1
03/08/2022
Violation issued (HPD, closed)
A
07/10/2017
Cycle 8 facade report submitted
07/10/2017
Cycle 8 facade report signed — SWARMP
06/15/2017
Cycle 8 facade inspection completed
01/27/2016
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
10/19/2015
Violation issued (HPD, closed)
I
03/31/2014
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
08/22/2013
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
Latest 60 of 102 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offPelham Construction06/26/2024
DOB NOWPlumbingSigned-offMetro05/17/2024
DOB NOWPlumbingSigned-offHI-Tech Plumbing & Heating09/18/2023
DOB NOWGeneral ConstructionSigned-offHLP Contracting07/07/2023
DOB NOWGeneral ConstructionSigned-offExclusive Restoration04/18/2023
DOB NOWGeneral ConstructionSigned-offExclusive Restoration11/28/2022
DOB NOWSidewalk ShedPermit IssuedSteel Systems10/19/2022
BISSDISSUEDTMJ Plumbing Heat03/21/2002
BISPLISSUEDTMJ _Plumbing Heat03/21/2002
BISEQISSUEDUnited Hoisting03/21/2002
BIS—ISSUEDWeatherbee Construction02/08/2002
BISEQISSUEDWeatherbee Construction02/04/2002
BISEQISSUEDWeatherbee Construction02/01/2002
BISPLISSUEDT J Mechanical01/28/2002
BISEQISSUEDUnited Hoisting08/13/2001
BISEQISSUEDRegional Scaffold & Hoisting08/01/2001
BISEQISSUEDRome Construction02/14/2001
BISEQISSUEDWeatherbee Construction01/31/2001
BISPLISSUEDT J Mechanical01/31/2001
BIS—RE-ISSUEDWeatherbee Construction01/31/2001
BIS—ISSUEDWeatherbee Construction01/19/2001
BISEQISSUEDWeatherbee Construction01/19/2001
BISEQISSUEDRome Construction04/24/2000
BISEQISSUEDRome Construction04/24/2000
1 project · most recent 11/07/2024
Heating and Air Conditioning Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
11/07/2024Signed-offPelham ConstructionHeating and Air Conditioning Systems, Ventilation Systems
Heat / Cool
Mitsubishi Electric Mitsubishi PUZ-A30NHA7 30,000 BTU · Heat Pump Outdoor ×1
Mitsubishi PVA-A30AA7 30,000 BTU · Fan Coil Indoor ×1
N/A n/a 1,600 CFM · Ductwork ×1
Ventilation
N/A n/a 50 CFM · Exhaust Fan ×1
1 project · most recent 11/07/2024
Gas Water/Sanitary
FiledStatusContractorScope
11/07/2024Signed-offMetroGas, Water/Sanitary
3 projects · most recent 03/24/2025
General Wiring
FiledStatusContractorScope
03/24/2025CompleteArree ElectricGeneral Wiring
03/24/2025CompleteArree ElectricGeneral Wiring
10/07/2022Permit IssuedTop Shelf Electric—
▾Field Inspections (DOB CAP) — 3
DateTypeResultReport
10/22/2024Pass-Final PL - More than 10 Requested FloorsPassView ↗
07/25/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
10/26/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 17
DateRequirementInspectorRole
05/10/2024Fire-Resistant Penetrations and JointsRachael Judgespecial
05/10/2024Energy Code Compliance InspectionsRachael Judgeprogress
05/10/2024FinalRachael Judgeprogress
05/10/2024Interior lighting powerRachael Judgeenergy_progress
05/10/2024Lighting in dwelling unitsRachael Judgeenergy_progress
05/10/2024Lighting controlsRachael Judgeenergy_progress
04/26/2024Fire-Resistant Penetrations and JointsRachael Judgespecial
08/17/2023Maintenance informationSTEVEN CHROSTOWSKIenergy_progress
08/17/2023Fire-Resistant Penetrations and JointsGUNJAN KHANDWALAspecial
08/17/2023Post-installed AnchorsGUNJAN KHANDWALAspecial
08/17/2023HVAC-R and service water heating system controlsSTEVEN CHROSTOWSKIenergy_progress
08/17/2023HVAC-R and service water piping design and insulationSTEVEN CHROSTOWSKIenergy_progress
08/17/2023Energy Code Compliance InspectionsSTEVEN CHROSTOWSKIprogress
08/17/2023HVAC-R and service water heating equipmentSTEVEN CHROSTOWSKIenergy_progress
08/17/2023Duct leakage testing, insulation and designSTEVEN CHROSTOWSKIenergy_progress
07/17/2023FinalSTEVEN CHROSTOWSKIprogress
07/17/2023Mechanical SystemsGUNJAN KHANDWALAspecial
▾Documents — 36 on file (BIS + DOB NOW)
▸Plans & Drawings8
▸DOB NOWPlans/Sketch8
09/01/2026M00797978-I1Request digital key ↗
09/01/2026M08018140-I1Request digital key ↗
08/29/2026M00878844-P2Request digital key ↗
Showing 3 of 8 on file for this type
▸Seals & Professional Certifications21
▸DOB NOWProgress Inspector Seal & Signature11
08/27/2026M00878844-S2Open ↗
08/27/2026M00878844-S2Open ↗
08/27/2026M00878844-S2Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature8
09/01/2026M08018140-I1Open ↗
08/29/2026M00878844-P1Open ↗
08/29/2026M00878844-S1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature2
09/01/2026M00878844-P1Open ↗
08/25/2026M00878844-P2Open ↗
▸Environmental & Asbestos7
▸DOB NOWOER: Notice to Proceed3
08/13/2026M00797978-I1Open ↗
08/13/2026M00878844-S1Open ↗
08/13/2026M00878844-S2Open ↗
▸DOB NOWOER: Notice of Satisfaction3
08/13/2026M00878844-S1Open ↗
08/13/2026M00878844-S2Open ↗
08/13/2026M00797978-I1Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026M00797978-I1Open ↗