| Owner | Filings | Most Recent |
|---|---|---|
| AKAM ASSOCIATES, INC. | 89 | 09/09/2026 |
| LINCOLN CENTER FOR THE PERFORMING A | 79 | 07/08/2026 |
| LINCOLN CENTER | 16 | 03/22/2026 |
| XINOS CONSTRUCTION | 8 | 07/08/2026 |
| 6FACE1 PROPERTIES | 7 | 03/21/2026 |
| UWSLC | 4 | 03/21/2026 |
| GBA 100 | 2 | 03/22/2026 |
| BROWN HARRIS STEVENS | 1 | 03/22/2026 |
| BAR CONSTRUCTION | 1 | 03/21/2026 |
| FIRE DEPARTMENT CITY OF NEW YORK | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| HANY RIZKALLA ARCHITECT PLLC | 8 | 08/26/2026 |
| LUIS PICHARDO, PE | 15 | 04/30/2026 |
| JACK GREEN ASSOCIATES | 3 | 10/23/2025 |
| VERONA CARPENTER ARCHITECTS | 4 | 08/15/2025 |
| SHAWN MEINDL ARCHITECT | 1 | 08/05/2025 |
| SYNC ARCHITECTURE P.C | 5 | 07/07/2025 |
| COLLADO ENGINEERING | 8 | 06/09/2025 |
| QUEENS ENGINEERING | 1 | 05/14/2025 |
| MIDTOWN PRESERVATION | 1 | 05/02/2025 |
| A2 ARCHITECT, PC | 11 | 04/21/2025 |
| C&B CONSULTING ENGINEERS LLC | 2 | 03/14/2025 |
| JENNY PEYSIN ARCHITECTURE PLLC | 1 | 03/12/2025 |
| SANDEEP GUNNALA ENGINEERING PLLC | 1 | 01/28/2025 |
| WSP | 1 | 01/15/2025 |
| POLISE CONSULTING ENGINEERS DPC | 3 | 12/18/2024 |
| NICOLAS BARATTO | 1 | 12/18/2024 |
| CRIBSTONE ENGINEERING PLLC | 1 | 11/21/2024 |
| BRENDAN KELLY | 2 | 11/07/2024 |
| Z+ ARCHITECTS | 2 | 10/23/2024 |
| FMO ENGINEERING PC | 1 | 10/23/2024 |
| MONTROY ARCHITECTURE PLLC | 1 | 08/22/2024 |
| P.A. COLLINS PE | 1 | 08/22/2024 |
| CO4ARCHITECTURE.PC | 6 | 10/17/2023 |
| DERIVE ENGINEERS | 2 | 09/20/2023 |
| ME ENGINEERS | 1 | 09/12/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| J A EXPEDITING | 22 | 03/21/2026 |
| DEZIGNPLUS | 11 | 03/21/2026 |
| A1 EXPEDITING SERVICE | 4 | 03/21/2026 |
| AGOUTI CONSTRUCTION CONSULTING | 4 | 03/21/2026 |
| DVA Advisors | 4 | 03/21/2026 |
| WILLIAM VITACCO ASSOCIATES | 19 | 03/21/2026 |
| NEXUS CONSULTING NYC, INC | 10 | 03/21/2026 |
| SOL BUILDING CONSULTING SERVICES | 2 | 03/21/2026 |
| NYCCODE | 18 | 03/21/2026 |
| MIDTOWN PRESERVATION ARCHITECTURE | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| BERDYNAJ CONSTRUCTION COR | General Contractor | 11 | 07/25/2026 |
| JRM CONSTRUCTION MGMT LLC | General Contractor | 10 | 07/08/2026 |
| THE METRO GROUP, INC | General Contractor | 9 | 04/09/2026 |
| YORKE CONSTRUCTION CORP | General Contractor | 9 | 07/08/2026 |
| ABS CONSTRUCTION, INC | General Contractor | 8 | 07/08/2026 |
| BELIDA ASSOCIATES INC | General Contractor | 8 | 07/08/2026 |
| GDC CONTRACTING LLC | General Contractor | 6 | 07/08/2026 |
| XINOS CONSTRUCTION CORP | General Contractor | 5 | 07/08/2026 |
| YORK SCAFFOLD EQUIPMENT CORP. | General Contractor | 5 | 07/08/2026 |
| SPK/LEWIS CONSTRUCTION LL | General Contractor | 4 | 07/08/2026 |
| A. HTG AND PLBG WORKS INC | Plumbing | 4 | 07/08/2026 |
| BOGEN INC | General Contractor | 4 | 07/08/2026 |
| JKR GROUP, LLC | General Contractor | 4 | 09/09/2026 |
| VINCENT FRANCO CONSULT DE | General Contractor | 3 | 03/21/2026 |
| TAP PLUMBING CORP | Plumbing | 3 | 07/08/2026 |
| LITESPEED ELECTRIC, INC | Electrical | 3 | 03/22/2026 |
| DYNAMIC BLUE WATER MECH | Plumbing | 3 | 07/08/2026 |
| GOLDEN CONSTRUCTION NY CO | General Contractor | 3 | 03/21/2026 |
| CORE DESIGN & BUILD INC | General Contractor | 3 | 03/21/2026 |
| BP MECHANICAL CORP | General Contractor | 3 | 07/08/2026 |
| B N J CONSTRUCTION CORP | General Contractor | 3 | 03/21/2026 |
| A&H EXPRESS PLBG&HTG CORP | Plumbing | 3 | 07/08/2026 |
| DONATO PLUMBING, INC | Plumbing | 3 | 07/08/2026 |
| WEBUILD INC | General Contractor | 2 | 03/21/2026 |
| ELPO ELECTRICAL CONTG INC | Electrical | 2 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| BUILDTECH ENGINEERING | 6369 | 4 | 04/30/2026 |
| CITISCAPE CONSULTING LTD | 762 | 4 | 11/11/2025 |
| JACK GREEN ASSOCIATES | 422 | 4 | 10/23/2025 |
| AK ENGINEERING PC | 678 | 12 | 08/15/2025 |
| QUEENS ENGINEERING PLLC | 8898 | 1 | 05/14/2025 |
| MIDTOWN PRESERVATION ARCH | 2634 | 1 | 05/02/2025 |
| A2 ARCHITECT, PC | 2504 | 11 | 04/21/2025 |
| STUDIO NYANDAK ARCHITECTU | 8378 | 3 | 03/14/2025 |
| SKYLINE ENGINEERING, PLLC | 267 | 5 | 12/18/2024 |
| ARCHITECTURE AND | 5545 | 1 | 11/07/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | JKR GROUP, LLC | 09/08/2026 |
| DOB NOW | General Construction | Permit Issued | BERDYNAJ CONSTRUCTION COR | 07/24/2026 |
| DOB NOW | General Construction | Permit Issued | BERDYNAJ CONSTRUCTION COR | 07/24/2026 |
| DOB NOW | Plumbing | Permit Issued | A&H EXPRESS PLBG&HTG CORP | 06/25/2026 |
| DOB NOW | Plumbing | Permit Issued | A&H EXPRESS PLBG&HTG CORP | 06/23/2026 |
| DOB NOW | General Construction | Permit Issued | BELIDA ASSOCIATES INC | 02/18/2026 |
| DOB NOW | General Construction | Permit Issued | JKR GROUP, LLC | 02/18/2026 |
| DOB NOW | General Construction | Permit Issued | ABS CONSTRUCTION, INC | 01/26/2026 |
| DOB NOW | Plumbing | Signed-off | TAP PLUMBING CORP | 01/08/2026 |
| DOB NOW | General Construction | Permit Issued | BELIDA ASSOCIATES INC | 12/29/2025 |
| DOB NOW | Plumbing | Permit Issued | DONATO PLUMBING, INC | 12/17/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | XINOS CONSTRUCTION CORP | 12/04/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | JKR GROUP, LLC | 12/03/2025 |
| DOB NOW | General Construction | Permit Issued | JKR GROUP, LLC | 12/03/2025 |
| DOB NOW | General Construction | Signed-off | YANECK HOME IMPROVEMENT C | 10/16/2025 |
| DOB NOW | Structural | Permit Issued | THE METRO GROUP, INC | 10/10/2025 |
| DOB NOW | Structural | Permit Issued | THE METRO GROUP, INC | 09/03/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | GDC CONTRACTING | 07/08/2025 |
| DOB NOW | General Construction | Permit Issued | GDC CONTRACTING | 07/08/2025 |
| DOB NOW | General Construction | Signed-off | XINOS CONSTRUCTION CORP | 06/13/2025 |
| DOB NOW | Supported Scaffold | Signed-off | XINOS CONSTRUCTION CORP | 05/14/2025 |
| DOB NOW | General Construction | Permit Issued | MANHATTAN CABINETS, INC | 05/07/2025 |
| DOB NOW | Plumbing | Permit Issued | PROCORE MECHANICAL CORP | 05/06/2025 |
| DOB NOW | Plumbing | Signed-off | SUPER PLUMBERS CORP | 04/21/2025 |
| DOB NOW | General Construction | Permit Issued | JRM CONSTRUCTION MGMT LLC | 04/04/2025 |
| DOB NOW | Sprinklers | Signed-off | LAWRENCE J. LEVINE | 04/04/2025 |
| DOB NOW | Plumbing | Signed-off | TAP PLUMBING CORP | 03/28/2025 |
| DOB NOW | General Construction | Permit Issued | XINOS CONSTRUCTION CORP | 03/20/2025 |
| DOB NOW | Plumbing | Signed-off | PAR PLUMBING CO., INC | 03/14/2025 |
| DOB NOW | Plumbing | Signed-off | SIMPLE CHOICE PLBG AND HT | 03/14/2025 |
| DOB NOW | Plumbing | Signed-off | SIMPLE CHOICE PLBG AND HT | 02/25/2025 |
| DOB NOW | Mechanical Systems | Signed-off | JRM CONSTRUCTION MGMT LLC | 02/13/2025 |
| DOB NOW | Structural | Signed-off | JRM CONSTRUCTION MGMT LLC | 02/12/2025 |
| DOB NOW | Structural | Permit Issued | THE METRO GROUP, INC | 02/03/2025 |
| DOB NOW | General Construction | Signed-off | YOLLO INTERIORS LLC | 02/03/2025 |
| DOB NOW | General Construction | Signed-off | JRM CONSTRUCTION MGMT LLC | 01/27/2025 |
| DOB NOW | Mechanical Systems | Signed-off | SPK/LEWIS CONSTRUCTION LL | 12/23/2024 |
| DOB NOW | Sprinklers | Signed-off | AGGRESSIVE FIRE PROT LLC | 12/23/2024 |
| DOB NOW | Plumbing | Signed-off | M&T PLBG AND HTG CO., INC | 12/23/2024 |
| DOB NOW | General Construction | Signed-off | SPK/LEWIS CONSTRUCTION LL | 12/23/2024 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 03/14/2025 | Permit Issued | JKR GROUP, LLC | Heating and Air Conditioning Systems | Heat / Cool Islandaire EZ15B4LRA_E44AA 14,800 BTU · Heat Pump Outdoor ×2 EZ15B4LRA_EA44AA 14,800 BTU · Heat Pump Outdoor ×1 |
| 10/23/2024 | Permit Issued | THE METRO GROUP, INC | Cooling Towers, Heating and Air Conditioning Systems | Heat / Cool Bell & Gossett SUB4-2 2,250,000 BTU · Heat Exchanger ×1 Alfa Laval AQBT-BFG Heat Exchanger ×1 Cooling Tower Evapco AT 29-3K24 9,448,800 BTU · Cooling Tower ×2 |
| 09/12/2023 | — | — | Air Conditioning Systems | Cooling Above Air MCE-042S-4-000-00-1D-EC-UF2-A 42,300 BTU ×3 XP1-042S-7-00-00-00-VF-P6 52,600 BTU · Condensing Unit ×3 |
| 06/21/2021 | Permit Issued | GDC CONTRACTING LLC | Air Conditioning Systems, Heating Systems | Cooling Simon-Aire SSWSWFC 13,000 tons ×9 Heating Simon-Aire SSWSWFC 21,500 BTU · Heat Pump Outdoor ×9 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/17/2023 | Signed-off | UNITED PLBG MECHANICAL IN | — |
| 08/27/2020 | Signed-off | STANDARD FIRE SUPP CORP | 44 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/26/2026 | Signed-off | TAP PLUMBING CORP | Gas, Water/Sanitary |
| 04/30/2026 | Permit Issued | A&H EXPRESS PLBG&HTG CORP | Water/Sanitary |
| 04/28/2026 | Permit Issued | A&H EXPRESS PLBG&HTG CORP | Water/Sanitary |
| 11/11/2025 | — | — | Water/Sanitary |
| 10/23/2025 | Signed-off | DYNAMIC BLUE WATER MECH | Gas, Water/Sanitary |
| 04/21/2025 | Permit Issued | PROCORE MECHANICAL CORP | Gas, Water/Sanitary |
| 03/14/2025 | Permit Issued | DONATO PLUMBING, INC | Gas, Water/Sanitary |
| 10/17/2023 | Signed-off | TRISTATE PLBG SVCS CORP | Water/Sanitary |
| 10/04/2023 | Signed-off | A&H EXPRESS PLBG&HTG CORP | Gas, Water/Sanitary |
| 08/12/2020 | Signed-off | ETHOS PLUMBING CORP | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/14/2026 | Permit Issued | FIU CORP DBA FIU ELECTRIC | General Wiring |
| 09/04/2026 | Complete | CAVAN ELECTRIC CORP. | — |
| 08/11/2026 | Complete | THE METRO GROUP ELECTRIC | General Wiring |
| 07/27/2026 | Permit Issued | AMOR ELECTRIC CORP | General Wiring |
| 06/09/2026 | Complete | CAVAN ELECTRIC CORP. | — |
| 06/02/2026 | Permit Issued | SHUIR ELEC'L CONTR'S CORP | General Wiring |
| 06/02/2026 | Permit Issued | SHUIR ELEC'L CONTR'S CORP | General Wiring |
| 04/23/2026 | Complete | THE METRO GROUP ELECTRIC | General Wiring |
| 12/19/2025 | Permit Issued | CAVAN ELECTRIC CORP. | General Wiring |
| 12/16/2025 | Permit Issued | DCE CORPORATION | General Wiring |
| 12/09/2025 | Complete | SHUIR ELEC'L CONTR'S CORP | General Wiring |
| 11/23/2025 | Complete | J.G.C. ELECTRIC, LLC | General Wiring |
| 06/10/2025 | Permit Issued | TOWER ELECTRIC INC. | — |
| 03/07/2025 | Complete | ULTRA ELECTRIC CORP | General Wiring |
| 03/05/2025 | Complete | ROBERT B SAMUELS, INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/23/2024 | Permit Issued | THE METRO GROUP, INC | Steel |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/09/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/12/2026 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 06/12/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/24/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/20/2026 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 03/17/2026 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 03/09/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 11/18/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/16/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/22/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/18/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/10/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/04/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/17/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/11/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 07/02/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 06/30/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 06/04/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 06/04/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 06/04/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 05/15/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 05/15/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/09/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/22/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/21/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/15/2026 | Fire-Resistant Penetrations and Joints | Luis Pichardo | special |
| 04/22/2026 | Lighting in dwelling units | Luis Pichardo | energy_progress |
| 04/08/2026 | Lighting controls | Luis Pichardo | energy_progress |
| 04/08/2026 | Final | Juan Ramos | progress |
| 04/08/2026 | Final | Juan Ramos | progress |
| 04/08/2026 | Lighting in dwelling units | Luis Pichardo | energy_progress |
| 11/06/2025 | Post-installed Anchors | Joe Lieberman | special |
| 11/06/2025 | Fire-Resistant Penetrations and Joints | Joe Lieberman | special |
| 11/06/2025 | Lighting in dwelling units | Joe Lieberman | energy_progress |
| 11/06/2025 | Final | Joe Lieberman | progress |
| 11/06/2025 | Energy Code Compliance Inspections | Joe Lieberman | progress |
| 11/04/2025 | Final | Joe Lieberman | progress |
| 11/04/2025 | Fire-Resistant Penetrations and Joints | Joe Lieberman | special |
| 11/04/2025 | Lighting in dwelling units | Joe Lieberman | energy_progress |
| 11/04/2025 | Energy Code Compliance Inspections | Joe Lieberman | progress |
| 10/14/2025 | Energy Code Compliance Inspections | JACK GREEN | progress |
| 10/14/2025 | Fire-Resistant Penetrations and Joints | JACK GREEN | special |
| 08/22/2025 | Fire-Resistant Penetrations and Joints | Ari Kamo | special |
| 08/22/2025 | Tenant Protection Plan Compliance | — | special |
| 08/13/2025 | Tenant Protection Plan Compliance | — | special |
| 08/13/2025 | Fire-Resistant Penetrations and Joints | Ari Kamo | special |
| 07/30/2025 | Lighting in dwelling units | Shawn Meindl | energy_progress |
| 07/30/2025 | Final | Shawn Meindl | progress |
| 06/23/2025 | Fire-Resistant Penetrations and Joints | Ari Kamo | special |
| 06/23/2025 | Sprinkler Systems | Ari Kamo | special |