← Back
BuildNYC
Elevator cooperative
160 WEST 85TH STREET
MANHATTAN · BIN 1032133
💬 Discuss this project
1950Year Built
6Stories
D4Building Class
R8BZoning
56,023 sfGross Floor Area
60Units
LL97 CoveredRent Stabilized65 Active Violations ▸FISP: SAFE
Elevator cooperative · Owner of record: 160 West 85th St Owrs · 12,770 sf lot · 4.39 FAR built · Flood zone X
Locations of Work
ArchitectureElectricalPlumbingEquipmentCivil
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofFacade inspection using rope access11p · 2 filings · 9 docs
Floor 4Unit 4F, Unit 4G, Unit 4J11p · 2 filings · 17 docs
Floor 3
Floor 2
Floor 1Unit 1H7p · 1 filing · 3 docs
Site & exteriorTemporary heavy duty sidewalk shed installationUnder Construction12p · 3 filings · 11 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
160 West 85 St Owners4503/22/2026
Daisy103/22/2026
Shareholder103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
George J. Xerakias, PE109/18/2026
Bone/Levine Architects109/16/2026
Always Fast Services109/15/2026
Kurv Architecture107/15/2024
Anna Jachnik Architect411/03/2023
Green Design102/18/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Pyramid Restoration NY203/21/2026
Agouti Construction Consulting403/21/2026
Municipal Building Consultants103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Phoenix Sutton STRScaffold409/16/2026
Century ElectricElectrical303/21/2026
Superb Plumbing & HeatingPlumbing307/08/2026
Norway ElectricElectrical203/21/2026
Amsterdam ElectricElectrical103/22/2026
Amsterdam ElectricElectrical103/21/2026
KBRNYGeneral Contractor107/08/2026
Sohome WorkGeneral Contractor107/08/2026
Crossfield Plumbing & HeatingPlumbing107/08/2026
Apollo Electric NYGElectrical103/21/2026
Century Electric CoElectrical103/22/2026
Hundertmark RichardElectrical103/21/2026
Murray StanleyElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Bone/Levine Architects307109/16/2026
Sag Engineering & Consulting608109/16/2026
Kurv Architecture8428107/15/2024
Anna Jachnik Architect4202108/22/2023
Building Lifecycle
All (115)Filed (10)Permit Issued (12)Signed Off (6)Facade (FISP) (12)Violation (60)Inspection (3)Objection (4)Special Inspection (8)
09/28/2026
Permit issued — Suspended Scaffold
M01454354-I1-SC
09/18/2026
Filed — Alteration
INSTALLATION OF TEMPORARY SUSPENDED SCAFFOLD EQUIPMENT - NO CHANGES IN THE EGRESS
M01454354-I1
09/16/2026
Filed — Alteration
FACADE AND ROOF PARAPET REPAIRS AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY
M01454319-I1
09/15/2026
Filed — Alteration
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AND PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE.LIVE LOAD 300PSF.
M01458655-I1
09/15/2026
Permit issued — Sidewalk Shed
M01458655-I1-SH
09/15/2026
Permit issued — Supported Scaffold
M01458655-I1-SF
09/01/2026
Special inspection requirement — Final
Kevin Bone
09/01/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Chester Kowalski
09/01/2026
Special inspection requirement — Masonry
Kevin Bone
09/01/2026
Special inspection requirement — Tenant Protection Plan Compliance
Chester Kowalski
07/09/2026
Signed off — Alteration
inspection using industrial rope access techniques and methods. See attached plans designated primary site supervisor: Diego Buri Cumbe
M01282056-I1
12/03/2025
Permit issued — Suspended Scaffold
M01282056-I1-SC
09/22/2025
Permit issued — Suspended Scaffold
M01282056-I1-SC
09/08/2025
Filed — Alteration
inspection using industrial rope access techniques and methods. See attached plans designated primary site supervisor: Diego Buri Cumbe
M01282056-I1
07/24/2025
Signed off — Alteration
M01079362-I1
08/05/2024
Permit issued — General Construction
M01079362-I1-GC
07/15/2024
Filed — Alteration
M01079362-I1
01/05/2024
Signed off — Alteration
Plumbing work filed in conjunction with apartment # 4F and 4G combination and renovation as per plans herewith. No change to use, egress or occupancy.
M00904070-S1
01/05/2024
Signed off — Alteration
Plumbing work filed in conjunction with apartment # 4F and 4G combination and renovation as per plans herewith. No change to use, egress or occupancy.
M00904070-I1
12/23/2023
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
11/03/2023
Filed — Alteration
Plumbing work filed in conjunction with apartment # 4F and 4G combination and renovation as per plans herewith. No change to use, egress or occupancy.
M00904070-P1
09/22/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
09/20/2023
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
08/30/2023
Permit issued — Plumbing
M00904070-S1-PL
08/29/2023
Permit issued — General Construction
M00904070-I1-GC
08/22/2023
Filed — Alteration
Plumbing work filed in conjunction with apartment # 4F and 4G combination and renovation as per plans herewith. No change to use, egress or occupancy.
M00904070-S1
08/22/2023
Filed — Alteration
Plumbing work filed in conjunction with apartment # 4F and 4G combination and renovation as per plans herewith. No change to use, egress or occupancy.
M00904070-I1
07/17/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Anna Jachnik
07/17/2023
Special inspection requirement — Energy Code Compliance Inspections
Anna Jachnik
07/17/2023
Special inspection requirement — Lighting in dwelling units
Anna Jachnik
07/13/2023
Special inspection requirement — Final
Anna Jachnik
07/08/2022
Cycle 9 facade inspection completed
06/07/2022
Cycle 9 facade report signed — SAFE
02/17/2022
Cycle 9 facade report submitted
08/26/2021
Violation issued (HPD, open)
B
08/26/2021
Violation issued (HPD, open)
B
08/26/2021
Violation issued (HPD, open)
C
08/26/2021
Violation issued (HPD, open)
A
08/26/2021
Violation issued (HPD, open)
B
08/26/2021
Violation issued (HPD, open)
A
08/26/2021
Violation issued (HPD, open)
B
08/26/2021
Violation issued (HPD, open)
B
08/26/2021
Violation issued (HPD, open)
A
08/26/2021
Violation issued (HPD, open)
B
08/26/2021
Violation issued (HPD, open)
C
08/26/2021
Violation issued (HPD, open)
A
08/26/2021
Violation issued (HPD, open)
A
08/26/2021
Violation issued (HPD, open)
B
08/26/2021
Violation issued (HPD, open)
A
08/26/2021
Violation issued (HPD, open)
A
07/22/2021
Signed off — Alteration
Plumbing work at the fourth floor in conjunction with the renovation of apartment #4J.
M00400519-I1
06/24/2021
Permit issued — Plumbing
M00400519-I1-PL
06/18/2021
Signed off — Alteration
M00472425-I1
03/10/2021
Permit issued — Plumbing
M00400519-I1-PL
02/18/2021
Filed — Alteration
M00472425-I1
02/18/2021
Permit issued — Sidewalk Shed
M00472425-I1-SH
12/15/2020
Violation issued (HPD, open)
B
12/15/2020
Violation issued (HPD, open)
B
11/19/2020
Permit issued — Plumbing
M00400519-I1-PL
10/26/2020
Objection raised — Inspections
Latest 60 of 115 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSuspended ScaffoldPermit IssuedSPD Construction09/28/2026
DOB NOWSidewalk ShedPermit IssuedPhoenix Sutton STR09/15/2026
DOB NOWSupported ScaffoldPermit IssuedPhoenix Sutton STR09/15/2026
DOB NOWSuspended ScaffoldSigned-offStreamline Consultants NY12/03/2025
DOB NOWSuspended ScaffoldSigned-offStreamline Consultants NY09/22/2025
DOB NOWGeneral ConstructionSigned-offKBRNY08/05/2024
DOB NOWPlumbingSigned-offCrossfield Plumbing & Heating08/30/2023
DOB NOWGeneral ConstructionSigned-offSohome Work08/29/2023
DOB NOWPlumbingSigned-offSuperb Plumbing & Heating06/24/2021
DOB NOWPlumbingSigned-offSuperb Plumbing & Heating03/10/2021
DOB NOWSidewalk ShedSigned-offPhoenix Sutton STR02/18/2021
DOB NOWPlumbingSigned-offSuperb Plumbing & Heating11/19/2020
BISOTISSUEDJRR Contracting03/22/2021
BISOTISSUEDDream Remodeling11/09/2020
BISOTISSUEDJRR Contracting09/04/2020
BISOTISSUEDKBRNY05/26/2020
BISPLISSUEDTMS Plumbing & Heating04/01/2019
BISOTISSUEDKBRNY03/28/2019
BISPLISSUEDA.M.N08/01/2017
BISOTISSUEDGreen Conversions07/24/2017
BISOTISSUEDJG Interior Renovation Co11/06/2015
BISPLISSUEDPrimo Plumbing & Heating02/26/2015
BISOTISSUEDNYCC Renovations02/10/2015
BISPLISSUEDDo Rite Mechanical11/19/2014
BISOTISSUEDJG Interior Renovation Co11/12/2014
BISOTISSUEDJG Interior Renovation Co08/22/2014
BISPLISSUEDWynne Plumbing & Heating02/05/2014
BISPLISSUEDGanic Plumbing & Heating03/25/2013
BISOTISSUEDNeba Construction03/05/2013
BISOTISSUEDBrend Renovation11/04/2010
BISEQISSUEDBrend Renovation08/17/2010
BISPLISSUEDCJ Heating & Mechanical04/28/2010
BISOTISSUEDGim Construction04/28/2010
BISPLISSUEDM. Farbman & Sons11/18/2009
BISOTISSUEDGrenfell Construction05/23/2007
BISOTISSUEDBuild Urban01/12/2007
BISPLISSUEDC.R.U. Mechan & Heating12/04/2006
BISPLISSUEDAriana Contracting12/03/2004
BISOTISSUEDAstoria Paint Revnov11/17/2004
BISOTISSUEDRRS Construction10/15/2004
+ 13 more permits on file
10 projects · most recent 09/15/2026
General Wiring
FiledStatusContractorScope
09/15/2026Permit IssuedRichard Neu—
10/09/2025Permit IssuedCentury ElectricGeneral Wiring
09/20/2024CompleteAmsterdam ElectricGeneral Wiring
08/15/2023CompleteW 8 ElectricGeneral Wiring
01/30/2023CompleteMadison ElectricGeneral Wiring
02/10/2021CompleteElpo Electrical Contg—
11/24/2020CompleteBerger Quality Electrical ConGeneral Wiring
10/29/2019CompleteGsa ElectricGeneral Wiring
05/14/2019CompleteWatts ElectricalGeneral Wiring
05/23/2018Permit IssuedWCK ElectricGeneral Wiring
1 project · most recent 09/15/2026
Scaffold Sidewalk Shed
FiledStatusContractorScope
09/15/2026Permit IssuedPhoenix Sutton STRScaffold, Sidewalk Shed
2 projects · most recent 09/18/2026
Suspended Scaffold (SC)
FiledStatusContractorScope
09/18/2026Permit IssuedSPD ConstructionSuspended Scaffold (SC)
09/08/2025Signed-offStreamline Consultants NY—
▾Field Inspections (DOB CAP) — 3
DateTypeResultReport
12/23/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
09/22/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
09/20/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 8
DateRequirementInspectorRole
09/01/2026FinalKevin Boneprogress
09/01/2026Structural Stability – Alterations of existing buildingsChester Kowalskispecial
09/01/2026MasonryKevin Bonespecial
09/01/2026Tenant Protection Plan ComplianceChester Kowalskispecial
07/17/2023Fire-Resistant Penetrations and JointsAnna Jachnikspecial
07/17/2023Energy Code Compliance InspectionsAnna Jachnikprogress
07/17/2023Lighting in dwelling unitsAnna Jachnikenergy_progress
07/13/2023FinalAnna Jachnikprogress
▾Documents — 203 on file (BIS + DOB NOW)
▸Plans & Drawings10
▸DOB NOWPlans/Sketch8
10/13/2026M01458655-I1Request digital key ↗
10/07/2026M01454319-I1Request digital key ↗
10/04/2026M01454354-I1Request digital key ↗
Showing 3 of 8 on file for this type
▸DOB NOWPlans/Sketch - Plumbing1
08/15/2026M00400519-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sidewalk Shed1
09/04/2026M00472425-I1Request digital key ↗
▸Applications & Permits33
▸BISPLAN / WORK APPROVAL APPLICATION17
11/01/2021123773354Open ↗
10/22/2020140954288Open ↗
01/13/2020140837263Open ↗
Showing 3 of 17 on file for this type
▸BISWORK PERMIT APPLICATION16
11/09/2020140954288Open ↗
09/04/2020123773354Open ↗
04/01/2019140837263Open ↗
Showing 3 of 16 on file for this type
▸Seals & Professional Certifications40
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION17
09/09/2019123773354Open ↗
08/14/2018123045695Open ↗
07/31/2017123045695Open ↗
Showing 3 of 17 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature9
10/07/2026M01454319-I1Open ↗
09/29/2026M01454354-I1Open ↗
09/16/2026M01458655-I1Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWProgress Inspector Seal & Signature4
10/08/2026M01454319-I1Open ↗
08/31/2026M00904070-I1Open ↗
08/31/2026M00904070-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
10/08/2026M01454319-I1Open ↗
10/08/2026M01454319-I1Open ↗
10/08/2026M01454319-I1Open ↗
Showing 3 of 4 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST2
01/22/2013121500492Open ↗
08/19/2010120444616Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM2
01/22/2013121500492Open ↗
08/19/2010120444616Open ↗
▸BISAPPLICANT OWNER SIGNATURE2
10/22/2020140954288Open ↗
03/18/2019140837263Open ↗
▸Trade Schedules & Equipment17
▸BISSELF-CERT PLUMBING NOTICE7
12/30/2015120310911Open ↗
11/03/2015120310911Open ↗
09/15/2015120310911Open ↗
Showing 3 of 7 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE5
01/13/2020140837263Open ↗
07/26/2017123045695Open ↗
09/15/2015120310911Open ↗
Showing 3 of 5 on file for this type
▸BISSCHEDULE B - PLUMBING5
03/18/2019140837263Open ↗
10/03/2013121753655Open ↗
04/25/2013121500492Open ↗
Showing 3 of 5 on file for this type
▸Safety & Tenant Protection4
▸BISTenant Protection Plan and Notes3
10/22/2020140954288Open ↗
09/09/2019123773354Open ↗
03/18/2019140837263Open ↗
▸DOB NOWTenant Protection Plan1
08/13/2026M00400519-I1Open ↗
▸Environmental & Asbestos15
▸BISASBESTOS: CERTIFICATION (DEP ACP5)6
10/22/2020140954288Open ↗
09/09/2019123773354Open ↗
03/18/2019140837263Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report6
10/07/2026M01454319-I1Open ↗
08/28/2026M00904070-S1Open ↗
08/28/2026M00904070-P1Open ↗
Showing 3 of 6 on file for this type
▸BISASBESTOS-EXEMPTION (ASB4)1
08/19/2010120444616Open ↗
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'1
04/05/2010120310911Open ↗
▸BISACP5 ASBESTOS: CERTIFICATION (DEP ACP5)1
01/22/2013121500492Open ↗
▸Energy Compliance22
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS9
10/17/2019123773354Open ↗
10/04/2019123773354Open ↗
09/09/2019123773354Open ↗
Showing 3 of 9 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS5
12/13/2021123773354Open ↗
07/17/2020140837263Open ↗
08/14/2018123045695Open ↗
Showing 3 of 5 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY4
12/13/2021123773354Open ↗
10/22/2020140954288Open ↗
07/17/2020140837263Open ↗
Showing 3 of 4 on file for this type
▸BISTR8: Energy Code Progress Inspections2
10/03/2013121753655Open ↗
01/22/2013121500492Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
07/07/2021140954288Open ↗
▸BISLIGHTING IN DWELLING UNITS1
07/07/2021140954288Open ↗
▸Inspections & Test Reports10
▸BISTECHNICAL REPORT: RESPONSIBILITY10
12/14/2021123773354Open ↗
12/14/2021123773354Open ↗
12/13/2021123773354Open ↗
Showing 3 of 10 on file for this type
▸Approvals, Objections & Sign-offs11
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST7
12/14/2021123773354Open ↗
07/07/2021140954288Open ↗
07/17/2020140837263Open ↗
Showing 3 of 7 on file for this type
▸BISADMINISTRATIVE OBJECTIONS3
08/24/2010120449372Open ↗
08/19/2010120444616Open ↗
04/05/2010120310911Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION1
07/02/2013120449372Open ↗
▸Cost, Insurance & Ownership20
▸BISCOST AFFIDAVIT18
12/13/2021123773354Open ↗
11/12/2021123773354Open ↗
11/01/2021123773354Open ↗
Showing 3 of 18 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW31
07/07/2021140954288Open ↗
▸BISHIC LICENSE OR AFFIDAVIT1
03/07/2013121500492Open ↗
▸Filing & Intake Forms17
▸BISEFILING COVER SHEET8
09/09/2019123773354Open ↗
07/26/2017123045695Open ↗
07/29/2014122071042Open ↗
Showing 3 of 8 on file for this type
▸BISADDITIONAL INFORMATION5
11/12/2021123773354Open ↗
09/03/2020123773354Open ↗
03/28/2019140837263Open ↗
Showing 3 of 5 on file for this type
▸BISBOROUGH INTAKE FORM2
01/13/2020140837263Open ↗
08/14/2018123045695Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET2
10/22/2020140954288Open ↗
03/18/2019140837263Open ↗
▸Other Documents4
▸BISDepartment of Consumer Affairs (DCA) Form1
07/31/2017123045695Open ↗
▸DOB NOWManufacturer's Specifications1
09/29/2026M01454354-I1Open ↗
▸DOB NOWIRA Certification1
08/13/2026M01282056-I1Open ↗
▸DOB NOWCalculations1
09/29/2026M01454354-I1Open ↗