| Owner | Filings | Most Recent |
|---|---|---|
| WESTSIDE GUY REALTY | 4 | 07/08/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| JOSEPH M. MORACE, A.I.A., ARCHITECT | 10 | 08/21/2026 |
| A TECH ENGINEERING NYC, PLLC. | 1 | 09/06/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| BLUE STAR HOLDING | 18 | 03/21/2026 |
| A TECH ENGINEERING NYC | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| BLUE STAR GROUP LLC | General Contractor | 10 | 07/08/2026 |
| DUO PLUMBING & HTG CORP. | Plumbing | 2 | 07/08/2026 |
| DUO PLBG. & HTG. CORP | Fire Protection | 1 | 07/08/2026 |
| R&M PIPING & HTG INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| A TECH ENGINEERING NYC, P | 6738 | 9 | 08/21/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | BLUE STAR GROUP LLC | 11/28/2023 |
| DOB NOW | Construction Fence | Signed-off | BLUE STAR GROUP LLC | 11/17/2022 |
| DOB NOW | Structural | Permit Issued | BLUE STAR GROUP LLC | 11/02/2022 |
| DOB NOW | Construction Fence | Signed-off | BLUE STAR GROUP LLC | 11/01/2022 |
| DOB NOW | Plumbing | Signed-off | DUO PLBG. & HTG. CORP | 10/19/2022 |
| DOB NOW | Sprinklers | Signed-off | DUO PLUMBING & HTG CORP. | 10/19/2022 |
| DOB NOW | Plumbing | Signed-off | R&M PIPING & HTG INC | 09/20/2022 |
| DOB NOW | Plumbing | Signed-off | DUO PLUMBING & HTG CORP. | 08/24/2022 |
| DOB NOW | Construction Fence | Signed-off | BLUE STAR GROUP LLC | 06/24/2022 |
| DOB NOW | Earth Work | Permit Issued | BLUE STAR GROUP LLC | 06/20/2022 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/21/2026 | Signed-off | BLUE STAR GROUP LLC | Air Conditioning Systems, Heating Systems, Ventilation Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/21/2026 | Signed-off | DUO PLUMBING & HTG CORP. | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/30/2022 | Complete | TRUE ELECTRIC CORP. | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/21/2026 | Signed-off | BLUE STAR GROUP LLC | Concrete, Wood |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/21/2026 | Signed-off | BLUE STAR GROUP LLC | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/09/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/06/2025 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 10/09/2024 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 08/01/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 07/05/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/02/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/23/2023 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 05/23/2023 | Pass-Final SP - Up to 3 Requested Floors | Pass | View ↗ |
| 05/19/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 03/20/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 11/17/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/17/2022 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 08/26/2022 | Pass-Final PL - Underground | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/25/2026 | Fenestration areas | anthony santoro | energy_progress |
| 08/25/2026 | Fire-Resistant Penetrations and Joints | anthony santoro | special |
| 08/25/2026 | Mechanical Systems | anthony santoro | special |
| 08/25/2026 | Concrete - Cast-In-Place | anthony santoro | special |
| 08/25/2026 | Subgrade Inspections | anthony santoro | special |
| 08/25/2026 | Wood – Prefabricated I-Joists | anthony santoro | special |
| 08/25/2026 | Subsurface Investigations (Borings/Test Pits) | anthony santoro | special |
| 08/25/2026 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | anthony santoro | special |
| 08/25/2026 | Footing and Foundation | anthony santoro | progress |
| 08/25/2026 | Fire-Resistance Rated Construction | anthony santoro | progress |
| 08/25/2026 | Energy Code Compliance Inspections | anthony santoro | progress |
| 08/25/2026 | Final | anthony santoro | progress |
| 08/25/2026 | Structural Wood Frame | anthony santoro | progress |
| 08/25/2026 | Fenestration and door U-factor and product ratings | anthony santoro | energy_progress |
| 08/25/2026 | Air barrier - visual inspection | anthony santoro | energy_progress |
| 08/25/2026 | Interior lighting power | anthony santoro | energy_progress |
| 08/25/2026 | Fireplaces | anthony santoro | energy_progress |
| 08/25/2026 | Permanent certificate | anthony santoro | energy_progress |
| 08/25/2026 | Metering | anthony santoro | energy_progress |
| 08/25/2026 | Electric vehicle service equipment requirements | anthony santoro | energy_progress |
| 08/25/2026 | Fenestration air leakage | anthony santoro | energy_progress |
| 08/25/2026 | HVAC-R and service water piping design and insulation | anthony santoro | energy_progress |
| 08/25/2026 | HVAC-R and service water heating system controls | anthony santoro | energy_progress |
| 08/25/2026 | Ventilation and air distribution system | anthony santoro | energy_progress |
| 08/25/2026 | Insulation placement and R values | anthony santoro | energy_progress |