← Back
Elevator apt, semi-fireproof without stores
1601 DEKALB AVENUE
BROOKLYN · BIN 3428633
💬 Discuss this project
2024Year Built
9Stories
D1Building Class
R7AZoning
117,424 sfGross Floor Area
128Units
0 Open ViolationsFDNY Report ↗
Elevator apt, semi-fireproof without stores · Owner of record: TWO GUY FROM GLENDALE, INC · 25,000 sf lot · 4.7 FAR built · Flood zone X
Locations of Work
StructuralMechanicalPlumbingFire ProtectionOther
Roof47p · 6 filings · 20 docs
Bulkhead2p · 1 filing · 14 docs
Floor 944p · 6 filings · 20 docs
Floor 846p · 6 filings · 20 docs
Floor 747p · 6 filings · 20 docs
Floor 646p · 6 filings · 20 docs
Floor 545p · 6 filings · 20 docs
Floor 449p · 6 filings · 20 docs
Floor 343p · 5 filings · 20 docs
Floor 245p · 6 filings · 20 docs
Floor 140p · 4 filings · 20 docs
Cellar41p · 4 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
SKYLINE SCAFFOLDING GROUP3007/08/2026
CAMBER PROPERTY GROUP4207/08/2026
VIK XS SERVICES604/09/2026
TWO GUY FROM GLENDALE, INC503/22/2026
FIFTH AVENUE BUILDERS1303/22/2026
BUILDERS LLC FIFTH AVENUE103/22/2026
1601 DEKALB OWNER1503/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
SKYLINE ENGINEERING, LLC1302/27/2026
RIGID STRUCTURAL DESIGN, LLC1307/17/2025
PLAN B ENGINEERING504/10/2025
SEVERUD ASSOCIATES301/08/2025
EG DEVELOPMENT LLC101/16/2024
AUFGANG ARCHITECTS203/31/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JM ZONING, LLC.2103/21/2026
Rigid Structural Design, LLC2103/21/2026
AO CONSULTING AND DRAFTING203/21/2026
A1 EXPEDITING SERVICE1003/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SKYLINE SCAFFOLDING GROUPGeneral Contractor1607/08/2026
FIFTH AVENUE BUILDERS LLCGeneral Contractor1107/08/2026
AURA PLUMBING INCFire Protection307/08/2026
BLETSAS PLBNG & HTG CORPFire Protection307/08/2026
FLINT MECHANICAL CORPFire Protection307/08/2026
BLETSAS P HPlumbing303/22/2026
CENTRIFUGAL ELECTRIC LLCElectrical203/22/2026
PANILI PLUMBING HTGGeneral Contractor104/08/2026
BLETSAS PLBNG & HTG CORPPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
DOMANI INSPECTION SERVICE8431102/27/2026
SKYLINE ENGINEERING, PLLC267306/07/2023
Building Lifecycle
All (189)Filed (38)Permit Issued (32)Signed Off (13)Violation (20)Inspection (11)Objection (45)Special Inspection (30)
07/09/2026
Signed off — Alteration
Install combined sprinkler/standpipe system as per plans filed. No change to use, egress, or occupancy. Filed in conjunction with NB# 321594672.
B00234200-I1
06/11/2026
Signed off — Alteration
Install temporary dry standpipe system during construction as per plans filed. No change to use, egress or occupancy. Filed in conjunction with NB# 321594672
B00233871-I1
06/11/2026
Signed off — Alteration
Structural work as per plans filed. No change to use, egress, or occupancy. Filed in conjunction with NB #321594672.
B00193774-I1
06/11/2026
Signed off — Alteration
Mechanical work as per plans filed. No change to use, egress, or occupancy. Filed in conjunction with NB #321594672.
B00193704-I1
05/01/2026
Permit issued — Suspended Scaffold
B01389942-I1-SC
04/30/2026
Objection resolved — Addressed
04/22/2026
Objection raised — Inspections
04/21/2026
Filed — Alteration
Suspended Scaffold Installation for Facade Restoration and Inspection
B01389942-I1
03/26/2026
Objection resolved — Addressed
03/26/2026
Objection resolved — Addressed
03/26/2026
Special inspection requirement — Interior lighting power
JOHN MCMONAGLE
03/26/2026
Special inspection requirement — HVAC insulation and sealing
JOHN MCMONAGLE
03/26/2026
Special inspection requirement — Metering
JOHN MCMONAGLE
03/26/2026
Special inspection requirement — HVAC and service water heating system controls
JOHN MCMONAGLE
03/26/2026
Special inspection requirement — Exterior lighting power
JOHN MCMONAGLE
03/26/2026
Special inspection requirement — Maintenance information
JOHN MCMONAGLE
03/26/2026
Special inspection requirement — Lighting controls
JOHN MCMONAGLE
03/26/2026
Special inspection requirement — Final
JOHN MCMONAGLE
03/26/2026
Special inspection requirement — Energy Code Compliance Inspections
JOHN MCMONAGLE
03/26/2026
Special inspection requirement — Lighting in dwelling units
JOHN MCMONAGLE
03/26/2026
Special inspection requirement — Mechanical Systems
JOHN MCMONAGLE
03/26/2026
Special inspection requirement — Electrical motors and elevators
JOHN MCMONAGLE
03/26/2026
Special inspection requirement — Duct leakage testing, insulation and design
JOHN MCMONAGLE
03/26/2026
Special inspection requirement — Duct leakage testing
JOHN MCMONAGLE
03/26/2026
Special inspection requirement — HVAC and service water heating equipment
JOHN MCMONAGLE
03/26/2026
Special inspection requirement — Electrical motors
JOHN MCMONAGLE
03/26/2026
Special inspection requirement — Shutoff dampers
JOHN MCMONAGLE
03/25/2026
Objection raised — Scope
03/18/2026
Inspection — Pass-Final SD - Up to 9 Requested Floors
Pass
View inspection ↗
03/16/2026
Objection raised — Cost
03/16/2026
Objection raised — Scope
03/16/2026
Objection raised — Admin
03/16/2026
Objection raised — Scope
03/16/2026
Objection resolved — Addressed
03/12/2026
Objection raised — Other
02/27/2026
Filed — Alteration
Plumbing work as per plans filed. No change to use, egress, or occupancy. Filed in conjunction with NB #321594672.
B00193739-P2
02/26/2026
Filed — Alteration
Mechanical work as per plans filed. No change to use, egress, or occupancy. Filed in conjunction with NB #321594672.
B00193704-P5
02/03/2026
Signed off — Alteration
Installation of a temporarily supported scaffold per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
B01031089-S1
01/27/2026
Inspection — Certified StandPipe-SD-Fixtures-Finish-SD
Certified
View inspection ↗
01/22/2026
Special inspection requirement — Metering
JOHN MCMONAGLE
01/22/2026
Special inspection requirement — Interior lighting power
JOHN MCMONAGLE
01/22/2026
Special inspection requirement — Lighting in dwelling units
JOHN MCMONAGLE
01/22/2026
Special inspection requirement — Exterior lighting power
JOHN MCMONAGLE
01/22/2026
Special inspection requirement — Energy Code Compliance Inspections
JOHN MCMONAGLE
01/22/2026
Special inspection requirement — Lighting controls
JOHN MCMONAGLE
01/22/2026
Special inspection requirement — Duct leakage testing, insulation and design
JOHN MCMONAGLE
01/22/2026
Special inspection requirement — Electrical motors and elevators
JOHN MCMONAGLE
01/15/2026
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
JOHN MCMONAGLE
01/15/2026
Special inspection requirement — Maintenance information
JOHN MCMONAGLE
01/15/2026
Special inspection requirement — Shutoff dampers
JOHN MCMONAGLE
01/08/2026
Signed off — Alteration
Install new temporary construction fence as per plans filed. No change to use, egress or occupancy. Filed in conjunction with NB #321594672.
B00627162-I1
01/08/2026
Signed off — Alteration
B00989209-I1
01/06/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
12/29/2025
Signed off — Alteration
Installation of a temporarily heavy-duty sidewalk shed posts in the street per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
B01046504-I1
12/29/2025
Signed off — Alteration
Installation of a temporarily supported scaffold per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
B01031089-I1
12/29/2025
Signed off — Alteration
Installation of a temporary roof protection and overhead protection per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application
B01064846-I1
12/29/2025
Signed off — Alteration
Installation of a temporary construction fence per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
B01046521-I1
12/23/2025
Permit issued — Standpipe
B00233871-I1-EW-SD
12/23/2025
Permit issued — Standpipe
B00234200-I1-EW-SD
12/22/2025
Violation issued (ECB, closed)
Unknown
Latest 60 of 189 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSuspended ScaffoldPermit IssuedSPYDER WINDOW CLEANING IN05/01/2026
DOB NOWStandpipeSigned-offBLETSAS P&H CORP12/23/2025
DOB NOWStandpipeSigned-offBLETSAS P&H CORP12/23/2025
DOB NOWSprinklersSigned-offBLETSAS P&H CORP12/11/2025
DOB NOWSupported ScaffoldSigned-offSKYLINE SCAFFOLDING GROUP07/28/2025
DOB NOWProtection and Mechanical MethodsSigned-offSKYLINE SCAFFOLDING GROUP06/10/2025
DOB NOWProtection and Mechanical MethodsSigned-offSKYLINE SCAFFOLDING GROUP05/15/2025
DOB NOWProtection and Mechanical MethodsSigned-offSKYLINE SCAFFOLDING GROUP05/15/2025
DOB NOWConstruction FenceSigned-offSKYLINE SCAFFOLDING GROUP04/30/2025
DOB NOWSuspended ScaffoldSigned-offCRISTINA MICHAELS CONS MN03/06/2025
DOB NOWStandpipeSigned-offAURA PLUMBING INC12/31/2024
DOB NOWSprinklersSigned-offAURA PLUMBING INC12/31/2024
DOB NOWSprinklersSigned-offAURA PLUMBING INC12/31/2024
DOB NOWStructuralSigned-offFIFTH AVENUE BUILDERS LLC12/11/2024
DOB NOWConstruction FenceSigned-offFIFTH AVENUE BUILDERS LLC12/11/2024
DOB NOWSuspended ScaffoldSigned-offVIK XS SERVICES INC09/10/2024
DOB NOWProtection and Mechanical MethodsSigned-offSKYLINE SCAFFOLDING GROUP07/05/2024
DOB NOWProtection and Mechanical MethodsSigned-offSKYLINE SCAFFOLDING GROUP07/05/2024
DOB NOWProtection and Mechanical MethodsSigned-offSKYLINE SCAFFOLDING GROUP06/14/2024
DOB NOWSupported ScaffoldSigned-offSKYLINE SCAFFOLDING GROUP05/23/2024
DOB NOWConstruction FenceSigned-offSKYLINE SCAFFOLDING GROUP05/09/2024
DOB NOWSidewalk ShedSigned-offSKYLINE SCAFFOLDING GROUP05/09/2024
DOB NOWStructuralSigned-offFIFTH AVENUE BUILDERS LLC04/22/2024
DOB NOWMechanical SystemsSigned-offFIFTH AVENUE BUILDERS LLC03/25/2024
DOB NOWStandpipeSigned-offBLETSAS PLBNG & HTG CORP03/22/2024
DOB NOWPlumbingPermit IssuedBLETSAS PLBNG & HTG CORP03/22/2024
DOB NOWStandpipeSigned-offBLETSAS PLBNG & HTG CORP03/22/2024
DOB NOWConstruction FenceSigned-offFIFTH AVENUE BUILDERS LLC02/08/2024
DOB NOWConstruction FenceSigned-offFIFTH AVENUE BUILDERS LLC01/18/2024
DOB NOWStandpipeSigned-offBLETSAS PLBNG & HTG CORP12/29/2023
DOB NOWConstruction FenceSigned-offFIFTH AVENUE BUILDERS LLC03/09/2023
DOB NOWConstruction FenceSigned-offFIFTH AVENUE BUILDERS LLC04/08/2022
BIS—ISSUEDFIFTH AVENUE BUILDERS LLC12/11/2025
BIS—ISSUEDFIFTH AVENUE BUILDERS LLC12/11/2025
BIS—ISSUEDFIFTH AVENUE BUILDERS LLC03/11/2025
BIS—ISSUEDFIFTH AVENUE BUILDERS LLC03/11/2025
BIS—RE-ISSUEDFIFTH AVENUE BUILDERS LLC04/01/2024
BIS—ISSUEDFIFTH AVENUE BUILDERS LLC04/01/2024
BIS—RE-ISSUEDFIFTH AVENUE BUILDERS LLC02/15/2024
BIS—RE-ISSUEDFIFTH AVENUE BUILDERS LLC02/15/2024
+ 5 more permits on file
1 project · most recent 02/27/2026
Gas Storm Water/Sanitary
FiledStatusContractorScope
02/27/2026Permit IssuedBLETSAS PLBNG & HTG CORPGas, Storm, Water/Sanitary
6 projects · most recent 04/08/2026
General Wiring
FiledStatusContractorScope
04/08/2026Permit IssuedCENTRIFUGAL ELECTRIC LLCGeneral Wiring
05/07/2025Permit IssuedTUXEDO ELEC'L CONTR'G INC—
10/02/2024Permit IssuedTUXEDO ELEC'L CONTR'G INC—
06/11/2024Permit IssuedCENTRIFUGAL ELECTRIC LLC—
06/11/2024CompleteCENTRIFUGAL ELECTRIC LLC—
05/24/2024CompleteTOP SHELF ELECTRIC CORP—
1 project · most recent 04/21/2026
Suspended Scaffold (SC)
FiledStatusContractorScope
04/21/2026Permit IssuedSPYDER WINDOW CLEANING INSuspended Scaffold (SC)
▾Field Inspections (DOB CAP) — 11
DateTypeResultReport
03/18/2026Pass-Final SD - Up to 9 Requested FloorsPassView ↗
01/27/2026Certified StandPipe-SD-Fixtures-Finish-SDCertifiedView ↗
01/06/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
12/16/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
08/27/2025Pass-Final SD - Fire PumpPassView ↗
08/14/2025Certified StandPipe-SD-Piping-Hydrostatic TestCertifiedView ↗
09/19/2024Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
08/01/2024Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
08/01/2024Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
07/31/2024Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet)CertifiedView ↗
09/06/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 103
DateRequirementInspectorRole
03/26/2026Lighting in dwelling unitsJOHN MCMONAGLEenergy_progress
03/26/2026Electrical motorsJOHN MCMONAGLEenergy_progress
03/26/2026Duct leakage testing, insulation and designJOHN MCMONAGLEenergy_progress
03/26/2026MeteringJOHN MCMONAGLEenergy_progress
03/26/2026Maintenance informationJOHN MCMONAGLEenergy_progress
03/26/2026Energy Code Compliance InspectionsJOHN MCMONAGLEprogress
03/26/2026FinalJOHN MCMONAGLEprogress
03/26/2026Mechanical SystemsJOHN MCMONAGLEspecial
03/26/2026Duct leakage testing JOHN MCMONAGLEenergy_progress
03/26/2026Exterior lighting powerJOHN MCMONAGLEenergy_progress
03/26/2026HVAC and service water heating equipment JOHN MCMONAGLEenergy_progress
03/26/2026HVAC insulation and sealing JOHN MCMONAGLEenergy_progress
03/26/2026Shutoff dampersJOHN MCMONAGLEenergy_progress
03/26/2026Interior lighting powerJOHN MCMONAGLEenergy_progress
03/26/2026HVAC and service water heating system controls JOHN MCMONAGLEenergy_progress
03/26/2026Electrical motors and elevatorsJOHN MCMONAGLEenergy_progress
03/26/2026Lighting controlsJOHN MCMONAGLEenergy_progress
01/22/2026Lighting in dwelling unitsJOHN MCMONAGLEenergy_progress
01/22/2026MeteringJOHN MCMONAGLEenergy_progress
01/22/2026Duct leakage testing, insulation and designJOHN MCMONAGLEenergy_progress
01/22/2026Interior lighting powerJOHN MCMONAGLEenergy_progress
01/22/2026Electrical motors and elevatorsJOHN MCMONAGLEenergy_progress
01/22/2026Exterior lighting powerJOHN MCMONAGLEenergy_progress
01/22/2026Lighting controlsJOHN MCMONAGLEenergy_progress
01/22/2026Energy Code Compliance InspectionsJOHN MCMONAGLEprogress
Latest 25 of 103.
▾Documents — 282 on file (BIS + DOB NOW)
▸Plans & Drawings41
▸DOB NOWPlans/Sketch22
08/26/2026B00989209-I1Request digital key ↗
08/25/2026B01046504-P2Request digital key ↗
08/25/2026B01046504-I1Request digital key ↗
Showing 3 of 22 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems5
08/18/2026B00193704-P4Request digital key ↗
08/18/2026B00193704-P2Request digital key ↗
08/18/2026B00193704-I1Request digital key ↗
Showing 3 of 5 on file for this type
▸DOB NOWPlans/Sketch - Standpipe4
09/02/2026B00233871-I1Request digital key ↗
08/20/2026B00234200-I1Request digital key ↗
08/20/2026B00234200-P2Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - Structural3
08/23/2026B00193774-P2Request digital key ↗
08/15/2026B00193774-I1Request digital key ↗
08/15/2026B00193774-P3Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing3
08/27/2026B00193739-I1Request digital key ↗
08/27/2026B00193739-P2Request digital key ↗
08/15/2026B00193739-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Sprinkler3
08/20/2026B00234200-P2Request digital key ↗
08/20/2026B00234200-I1Request digital key ↗
08/14/2026B00234200-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Boiler Equipment1
09/02/2026B00341971-I1Request digital key ↗
▸Applications & Permits45
▸BISPLAN / WORK APPROVAL APPLICATION27
10/16/2025321594672Open ↗
10/08/2025321594672Open ↗
08/01/2025321700824Open ↗
Showing 3 of 27 on file for this type
▸BISWORK PERMIT APPLICATION12
04/02/2024321594672Open ↗
04/02/2024321594672Open ↗
04/02/2024321594672Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWState DEC Permit3
08/13/2026B00193739-I1Open ↗
08/13/2026B00193739-P2Open ↗
08/13/2026B00193739-P1Open ↗
▸BISHPD: PERMIT NOTICE1
04/15/2022321594672Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation1
10/09/2019340698551Open ↗
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
07/23/2025321594672Open ↗
▸Zoning, Tax Lot & Property Records5
▸BISTAX LOT: TENTATIVE LOT NUMBER ISSUED2
11/16/2020321594672Open ↗
01/15/2020340698551Open ↗
▸BISZONING EXHIBIT III:DESC. & OWNRSHP.STMNT1
08/24/2020321594672Open ↗
▸BISZONING DIAGRAM1
06/29/2021321594672Open ↗
▸BISZONING EXHIBIT I: CERTIFICATION1
08/24/2020321594672Open ↗
▸Seals & Professional Certifications88
▸DOB NOWDPL-1: Design Professional Seal & Signature39
08/31/2026B00627162-I1Open ↗
08/31/2026B00627162-P1Open ↗
08/26/2026B00989209-I1Open ↗
Showing 3 of 39 on file for this type
▸DOB NOWProgress Inspector Seal & Signature29
08/29/2026B00193774-I1Open ↗
08/27/2026B00193704-I1Open ↗
08/27/2026B00193704-I1Open ↗
Showing 3 of 29 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature18
09/01/2026B00234200-P2Open ↗
09/01/2026B00193739-P1Open ↗
08/29/2026B00193774-I1Open ↗
Showing 3 of 18 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
10/09/2019340698551Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION1
01/26/2018321700824Open ↗
▸Trade Schedules & Equipment2
▸BIS* SEWER CONNECTION: DEP SD1 & SD21
08/24/2020321594672Open ↗
▸BISSTANDPIPE ALARM DRAWINGS & AI1 (OR AI1 PROOF)1
04/15/2022321594672Open ↗
▸Safety & Tenant Protection5
▸BISSTREET TREE CHECKLIST3
06/29/2021321594672Open ↗
01/15/2020340698551Open ↗
01/26/2018321700824Open ↗
▸BISEXCAVATION - SHEETING, SHORING, AND BRACING1
04/15/2022321594672Open ↗
▸BISSTREET TREES: RECEIPT OF STREET TREES SITE PLAN1
06/29/2021321594672Open ↗
▸Environmental & Asbestos20
▸DOB NOWOER: Notice to Proceed16
08/15/2026B00193774-I1Open ↗
08/13/2026B00193739-P1Open ↗
08/13/2026B00193739-I1Open ↗
Showing 3 of 16 on file for this type
▸DOB NOWOER: Notice of Satisfaction3
08/18/2026B00193704-I1Open ↗
08/15/2026B00193774-I1Open ↗
08/13/2026B00193739-I1Open ↗
▸BISENVIRONMENTAL RESTRICTIONS - OER NOTICE TO PROCEED1
06/04/2021321594672Open ↗
▸Energy Compliance4
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY3
01/05/2024321594672Open ↗
10/12/2022321594672Open ↗
06/29/2021321594672Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
01/26/2018321700824Open ↗
▸Inspections & Test Reports23
▸BISTECHNICAL REPORT: RESPONSIBILITY14
06/17/2025321594672Open ↗
06/10/2025321594672Open ↗
01/04/2024321594672Open ↗
Showing 3 of 14 on file for this type
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX4
03/15/2024321594672Open ↗
03/15/2024321594672Open ↗
01/05/2024321594672Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER2
01/05/2024321594672Open ↗
05/07/2022321594672Open ↗
▸BISTECHNICAL REPORT: SOIL INSPECTION2
10/12/2022321594672Open ↗
06/29/2021321594672Open ↗
▸BISSOIL REPORT1
11/21/2019321594672Open ↗
▸Approvals, Objections & Sign-offs20
▸BISSCHEDULE A - OCCUPANCY / USE16
10/16/2025321594672Open ↗
10/08/2025321594672Open ↗
06/25/2025321594672Open ↗
Showing 3 of 16 on file for this type
▸BISSUPERSEDING LETTER2
04/01/2024321594672Open ↗
02/21/2024321594672Open ↗
▸BISSUSTAINABLE ROOF ZONE FORM (SIGNOFF)1
01/30/2026321594672Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION1
06/29/2021321594672Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT1
01/26/2018321700824Open ↗
▸BISPROJECT-SPECIFIC GL INSURANCE1
05/07/2022321594672Open ↗
▸Filing & Intake Forms16
▸BISADDITIONAL INFORMATION12
08/26/2025321594672Open ↗
01/30/2024321594672Open ↗
07/14/2023321594672Open ↗
Showing 3 of 12 on file for this type
▸BISEFILING COVER SHEET3
09/17/2019321594672Open ↗
09/17/2019321594672Open ↗
01/26/2018321700824Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
10/09/2019340698551Open ↗
▸Other Documents11
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION3
06/29/2021321594672Open ↗
06/29/2021321594672Open ↗
06/29/2021321594672Open ↗
▸BISPLOT DIAGRAM2
06/29/2021321594672Open ↗
01/26/2018321700824Open ↗
▸BISBPP - SUPPORTING DOCUMENTATION2
01/24/2020340698551Open ↗
01/24/2020340698551Open ↗
▸DOB NOWManufacturer's Specifications2
08/17/2026B01389942-I1Open ↗
08/13/2026B01031089-S1Open ↗
▸DOB NOWCalculations2
08/17/2026B01389942-I1Open ↗
08/13/2026B01031089-S1Open ↗