← Back
Two stories - detached, small or mid-size
1603 HERING AVENUE
BRONX · BIN 2045115
💬 Discuss this project
1925Year Built
2Stories
A1Building Class
R4AZoning
1,476 sfGross Floor Area
1Units
1 Open Violation ▸FDNY Report ↗
Two stories - detached, small or mid-size · 7,500 sf lot · 0.2 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalPlumbing
Permit Issued — active, not yet Signed-off
Floor 2Under Construction14p · 1 filing · 20 docs
Floor 1Under Construction13p · 1 filing · 20 docs
CellarUnder Construction18p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
INNOVATIVE CONSTRUCTION103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
12/20/2023$710K—Private party → Private party$481/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
CHANDA ENGINEERING CONSULTANT PC501/20/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
INNOVATIVE CONSTRUCTION &General Contractor307/08/2026
KISHAN PLUMBING INCPlumbing207/17/2026
FALCO ELEC'L SERVICES INCElectrical103/22/2026
PADMA CONTRACTING CORPGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
CHANDA ENG. CONSULTANT PC6842410/19/2025
Building Lifecycle
All (74)Filed (5)Permit Issued (6)Violation (2)Inspection (11)Objection (20)Special Inspection (30)
07/16/2026
Permit issued — Plumbing
X01143379-S1-PL
06/25/2026
Inspection — Certified Storm Drainage-ST-Piping-Water Test
Certified
View inspection ↗
06/03/2026
Permit issued — General Construction
X01143379-I1-GC
05/29/2026
Permit issued — Curb Cut
X01320826-I1-CC
04/19/2026
Objection resolved — Addressed
04/19/2026
Objection resolved — Addressed
04/19/2026
Objection resolved — Addressed
04/19/2026
Objection resolved — Addressed
04/19/2026
Objection resolved — Addressed
02/06/2026
Objection raised — Other
02/06/2026
Objection raised — Other
02/06/2026
Objection raised — Scope
02/06/2026
Objection raised — Zoning
02/06/2026
Objection raised — Admin
01/29/2026
Permit issued — General Construction
X01143379-I1-GC
01/20/2026
Filed — Alteration
X01320826-I1
01/07/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
11/21/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
11/05/2025
Violation issued (ECB, closed)
Construction
11/03/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
10/22/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
KARTIK CHANDA
10/22/2025
Special inspection requirement — Maintenance information
KARTIK CHANDA
10/22/2025
Special inspection requirement — HVAC-R and service water heating system controls
KARTIK CHANDA
10/22/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
KARTIK CHANDA
10/22/2025
Special inspection requirement — HVAC-R and service water heating equipment
KARTIK CHANDA
10/22/2025
Special inspection requirement — Energy Code Compliance Inspections
KARTIK CHANDA
10/21/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
10/19/2025
Filed — Alteration CO
APPLICATION IS BEING FILLED TO CONVERT ONE FAMILY TO TWO FAMILY DWELLING UNITS AND OBTAIN NEW CERTIFICATE OF OCCUPANCY. AND COMPLY ECB VIOLATION#39120648M. NO CHANGE EXISTING BULK.
X01143379-P2
10/19/2025
Special inspection requirement — HVAC-R and service water heating system controls
KARTIK CHANDA
10/19/2025
Special inspection requirement — HVAC-R and service water heating equipment
KARTIK CHANDA
10/19/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
KARTIK CHANDA
10/19/2025
Special inspection requirement — Maintenance information
KARTIK CHANDA
10/19/2025
Special inspection requirement — Energy Code Compliance Inspections
KARTIK CHANDA
10/19/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
KARTIK CHANDA
08/05/2025
Inspection — Certified Storm Drainage-ST-Piping-Roughing
Certified
View inspection ↗
08/05/2025
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
07/31/2025
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
07/31/2025
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
07/31/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
07/31/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
06/03/2025
Permit issued — Plumbing
X01143379-S1-PL
05/19/2025
Permit issued — General Construction
X01143379-I1-GC
05/19/2025
Objection resolved — Addressed
05/16/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
KARTIK CHANDA
05/16/2025
Special inspection requirement — Fire-Resistance Rated Construction
KARTIK CHANDA
05/16/2025
Special inspection requirement — Energy Code Compliance Inspections
KARTIK CHANDA
05/16/2025
Special inspection requirement — Insulation placement and R values
KARTIK CHANDA
05/16/2025
Special inspection requirement — Air barrier - visual inspection
KARTIK CHANDA
05/16/2025
Special inspection requirement — Metering
KARTIK CHANDA
05/16/2025
Special inspection requirement — Interior lighting power
KARTIK CHANDA
05/16/2025
Special inspection requirement — Fenestration air leakage
KARTIK CHANDA
05/16/2025
Special inspection requirement — Fenestration areas
KARTIK CHANDA
05/16/2025
Special inspection requirement — Permanent certificate
KARTIK CHANDA
05/16/2025
Special inspection requirement — Electric vehicle service equipment requirements
KARTIK CHANDA
05/16/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
KARTIK CHANDA
05/13/2025
Objection resolved — Addressed
04/27/2025
Filed — Alteration CO
APPLICATION IS BEING FILLED TO CONVERT ONE FAMILY TO TWO FAMILY DWELLING UNITS AND OBTAIN NEW CERTIFICATE OF OCCUPANCY. AND COMPLY ECB VIOLATION#39120648M. NO CHANGE EXISTING BULK.
X01143379-P1
04/27/2025
Special inspection requirement — Metering
KARTIK CHANDA
04/27/2025
Special inspection requirement — Fenestration air leakage
KARTIK CHANDA
04/27/2025
Special inspection requirement — Permanent certificate
KARTIK CHANDA
Latest 60 of 74 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedKISHAN PLUMBING INC07/16/2026
DOB NOWGeneral ConstructionPermit IssuedINNOVATIVE CONSTRUCTION &06/03/2026
DOB NOWCurb CutPermit IssuedPADMA CONTRACTING CORP05/29/2026
DOB NOWGeneral ConstructionPermit IssuedINNOVATIVE CONSTRUCTION &01/29/2026
DOB NOWPlumbingPermit IssuedN AND S PLUMBING INC06/03/2025
DOB NOWGeneral ConstructionPermit IssuedINNOVATIVE CONSTRUCTION &05/19/2025
1 project · most recent 10/19/2025
Gas Storm Water/Sanitary
FiledStatusContractorScope
10/19/2025Permit IssuedKISHAN PLUMBING INCGas, Storm, Water/Sanitary
2 projects · most recent 12/22/2024
General Wiring
FiledStatusContractorScope
12/22/2024Permit IssuedFALCO ELEC'L SERVICES INCGeneral Wiring
08/05/2024Permit IssuedL J ELEC'L SERV. INC.3 meters, 2 new_meters
▾Field Inspections (DOB CAP) — 11
DateTypeResultReport
06/25/2026Certified Storm Drainage-ST-Piping-Water TestCertifiedView ↗
01/07/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
11/21/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
11/03/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
10/21/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
08/05/2025Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
08/05/2025Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
07/31/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
07/31/2025Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
07/31/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
07/31/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 36
DateRequirementInspectorRole
10/22/2025Fire-Resistant Penetrations and JointsKARTIK CHANDAspecial
10/22/2025Maintenance informationKARTIK CHANDAenergy_progress
10/22/2025HVAC-R and service water heating system controlsKARTIK CHANDAenergy_progress
10/22/2025HVAC-R and service water piping design and insulationKARTIK CHANDAenergy_progress
10/22/2025HVAC-R and service water heating equipmentKARTIK CHANDAenergy_progress
10/22/2025Energy Code Compliance InspectionsKARTIK CHANDAprogress
10/19/2025HVAC-R and service water heating system controlsKARTIK CHANDAenergy_progress
10/19/2025HVAC-R and service water heating equipmentKARTIK CHANDAenergy_progress
10/19/2025HVAC-R and service water piping design and insulationKARTIK CHANDAenergy_progress
10/19/2025Maintenance informationKARTIK CHANDAenergy_progress
10/19/2025Energy Code Compliance InspectionsKARTIK CHANDAprogress
10/19/2025Fire-Resistant Penetrations and JointsKARTIK CHANDAspecial
05/16/2025Fire-Resistant Penetrations and JointsKARTIK CHANDAspecial
05/16/2025Fire-Resistance Rated ConstructionKARTIK CHANDAprogress
05/16/2025Energy Code Compliance InspectionsKARTIK CHANDAprogress
05/16/2025Insulation placement and R valuesKARTIK CHANDAenergy_progress
05/16/2025Air barrier - visual inspectionKARTIK CHANDAenergy_progress
05/16/2025MeteringKARTIK CHANDAenergy_progress
05/16/2025Interior lighting powerKARTIK CHANDAenergy_progress
05/16/2025Fenestration air leakageKARTIK CHANDAenergy_progress
05/16/2025Fenestration areasKARTIK CHANDAenergy_progress
05/16/2025Permanent certificateKARTIK CHANDAenergy_progress
05/16/2025Electric vehicle service equipment requirementsKARTIK CHANDAenergy_progress
05/16/2025Fenestration and door U-factor and product ratingsKARTIK CHANDAenergy_progress
04/27/2025MeteringKARTIK CHANDAenergy_progress
Latest 25 of 36.
▾Documents — 55 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch5
08/18/2026X01143379-S1Request digital key ↗
08/18/2026X01143379-I1Request digital key ↗
08/18/2026X01143379-P1Request digital key ↗
Showing 3 of 5 on file for this type
▸Seals & Professional Certifications41
▸DOB NOWProgress Inspector Seal & Signature32
08/29/2026X01143379-I1Open ↗
08/29/2026X01143379-I1Open ↗
08/29/2026X01143379-I1Open ↗
Showing 3 of 32 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature5
08/13/2026X01143379-P2Open ↗
08/13/2026X01143379-P1Open ↗
08/13/2026X01320826-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
08/29/2026X01143379-I1Open ↗
08/28/2026X01143379-P2Open ↗
08/27/2026X01143379-S1Open ↗
Showing 3 of 4 on file for this type
▸Safety & Tenant Protection3
▸DOB NOWStreet Tree Checklist2
08/13/2026X01143379-I1Open ↗
08/13/2026X01143379-P1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026X01143379-I1Open ↗
▸Environmental & Asbestos4
▸DOB NOWDEP ACP-5: Asbestos Assessment Report4
08/13/2026X01143379-I1Open ↗
08/13/2026X01143379-P1Open ↗
08/13/2026X01143379-P2Open ↗
Showing 3 of 4 on file for this type
▸Other Documents2
▸DOB NOWProperty Ownership Certification2
08/13/2026X01143379-I1Open ↗
08/13/2026X01143379-P1Open ↗