Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingGeneral
Roof14p · 2 filings · 20 docs
Floor 38p · 2 filings · 20 docs
Floor 24p · 2 filings · 20 docs
Floor 12p · 1 filing · 20 docs
Cellar4p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
1616 PROPERTIES1407/08/2026
1616 PROPE103/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
08/26/2022$2.2M—— → —$524/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
JOSHUA ARCHITECT + PLANNER, PC407/16/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JOSHUA ARCHITECT + PLANNER803/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CEDARS CONSTRUCTION CORPGeneral Contractor503/21/2026
GREGG NY PLUMBING, INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
JAY KAVI CORPORATION8500407/16/2024
Building Lifecycle
All (84)Filed (4)Permit Issued (3)Signed Off (2)Violation (2)Inspection (3)Objection (40)Special Inspection (30)
09/18/2024
Signed off — Alteration
Interior renovation for new Plumbing fixtures in existing commercial building. 1- New bathroom with Electric HWH on First, Second and Third floors. New Hand sink each on Cellar, Second and Third Floors. No change in use, egress and occupancy.
B00826968-I1
09/18/2024
Signed off — Alteration
Interior renovation of 1st, 2nd & 3rd Flrs with hand'p Baths, new metal stairs & ST wood girder, Minor work in Cellar. New Dunnage for 6 Roof HVAC Units on 1st Flr Roof . No work on exterior front brick wall. No change in Use, egress & Occupancy.
B00826881-I1
08/19/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Jay Kavi
08/19/2024
Special inspection requirement — Energy Code Compliance Inspections
ADEDOSU JOSHUA
08/19/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
ADEDOSU JOSHUA
08/19/2024
Special inspection requirement — HVAC-R and service water heating equipment
ADEDOSU JOSHUA
08/09/2024
Objection resolved — Addressed
07/25/2024
Objection raised — Scope
07/18/2024
Special inspection requirement — Shutoff dampers
ADEDOSU JOSHUA
07/18/2024
Special inspection requirement — Ventilation and air distribution system
ADEDOSU JOSHUA
07/18/2024
Special inspection requirement — HVAC-R and service water heating system controls
ADEDOSU JOSHUA
07/18/2024
Special inspection requirement — Interior lighting power
ADEDOSU JOSHUA
07/18/2024
Special inspection requirement — HVAC-R and service water heating equipment
ADEDOSU JOSHUA
07/18/2024
Special inspection requirement — Mechanical Systems
Jay Kavi
07/18/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Jay Kavi
07/18/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
Jay Kavi
07/18/2024
Special inspection requirement — Construction Operations Influencing Adjacent Structures
Jay Kavi
07/18/2024
Special inspection requirement — Structural Steel - Details
Jay Kavi
07/18/2024
Special inspection requirement — Exhaust and Vent Systems in Plenums and Ducts
Jay Kavi
07/18/2024
Special inspection requirement — Final
ADEDOSU JOSHUA
07/18/2024
Special inspection requirement — Energy Code Compliance Inspections
ADEDOSU JOSHUA
07/18/2024
Special inspection requirement — Fire-Resistance Rated Construction
ADEDOSU JOSHUA
07/18/2024
Special inspection requirement — Permanent certificate
ADEDOSU JOSHUA
07/18/2024
Special inspection requirement — Fenestration air leakage
ADEDOSU JOSHUA
07/18/2024
Special inspection requirement — Fenestration areas
ADEDOSU JOSHUA
07/18/2024
Special inspection requirement — Fenestration and door U-factor and product ratings
ADEDOSU JOSHUA
07/18/2024
Special inspection requirement — Insulation placement and R values
ADEDOSU JOSHUA
07/18/2024
Special inspection requirement — Lighting controls
ADEDOSU JOSHUA
07/18/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
ADEDOSU JOSHUA
07/18/2024
Special inspection requirement — Air barrier - visual inspection
ADEDOSU JOSHUA
07/16/2024
Filed — Alteration
Interior renovation for new Plumbing fixtures in existing commercial building. 1- New bathroom with Electric HWH on First, Second and Third floors. New Hand sink each on Cellar, Second and Third Floors. No change in use, egress and occupancy.
B00826968-P1
07/16/2024
Filed — Alteration
Interior renovation of 1st, 2nd & 3rd Flrs with hand'p Baths, new metal stairs & ST wood girder, Minor work in Cellar. New Dunnage for 6 Roof HVAC Units on 1st Flr Roof . No work on exterior front brick wall. No change in Use, egress & Occupancy.
B00826881-P1
06/19/2024
Special inspection requirement — Energy Code Compliance Inspections
ADEDOSU JOSHUA
06/19/2024
Special inspection requirement — HVAC-R and service water heating equipment
ADEDOSU JOSHUA
06/19/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
ADEDOSU JOSHUA
06/19/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Jay Kavi
06/06/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
04/26/2024
Permit issued — General Construction
B00826881-I1-GC-CX
10/13/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
10/11/2023
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
10/05/2023
Permit issued — Plumbing
B00826968-I1-PL
07/17/2023
Permit issued — General Construction
B00826881-I1-GC-CX
03/02/2023
Objection raised — Admin
03/02/2023
Objection resolved — Addressed
03/02/2023
Objection raised — Scope
03/02/2023
Objection resolved — Addressed
03/02/2023
Objection raised — Admin
03/02/2023
Objection resolved — Addressed
03/02/2023
Objection raised — Cost
03/02/2023
Objection resolved — Addressed
03/02/2023
Objection raised — Fire_Protection
03/02/2023
Objection resolved — Addressed
03/02/2023
Objection raised — Accessibility
03/02/2023
Objection resolved — Addressed
03/02/2023
Objection raised — Zoning
03/02/2023
Objection resolved — Addressed
03/01/2023
Objection raised — Structural
03/01/2023
Objection resolved — Addressed
03/01/2023
Objection raised — Scope
03/01/2023
Objection resolved — Addressed
Latest 60 of 84 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offCEDARS CONSTRUCTION GROUP04/26/2024
DOB NOWPlumbingSigned-offGREGG NY PLUMBING, INC10/05/2023
DOB NOWGeneral ConstructionSigned-offCEDARS CONSTRUCTION GROUP07/17/2023
3 projects · most recent 11/05/2023
General Wiring
FiledStatusContractorScope
11/05/2023CompleteKINGS ELECTRIC CO., INC.General Wiring
10/29/2023CompleteKINGS ELECTRIC CO., INC.6 meters, 5 new_meters
09/21/2023CancelledKINGS ELECTRIC CO., INC.4 meters, 3 new_meters
▾Field Inspections (DOB CAP) — 3
DateTypeResultReport
06/06/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
10/13/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
10/11/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 30
DateRequirementInspectorRole
08/19/2024Fire-Resistant Penetrations and JointsJay Kavispecial
08/19/2024Energy Code Compliance InspectionsADEDOSU JOSHUAprogress
08/19/2024HVAC-R and service water piping design and insulationADEDOSU JOSHUAenergy_progress
08/19/2024HVAC-R and service water heating equipmentADEDOSU JOSHUAenergy_progress
07/18/2024Shutoff dampersADEDOSU JOSHUAenergy_progress
07/18/2024Ventilation and air distribution systemADEDOSU JOSHUAenergy_progress
07/18/2024HVAC-R and service water heating system controlsADEDOSU JOSHUAenergy_progress
07/18/2024Interior lighting powerADEDOSU JOSHUAenergy_progress
07/18/2024HVAC-R and service water heating equipmentADEDOSU JOSHUAenergy_progress
07/18/2024Mechanical SystemsJay Kavispecial
07/18/2024Fire-Resistant Penetrations and JointsJay Kavispecial
07/18/2024Structural Stability – Alterations of existing buildingsJay Kavispecial
07/18/2024Construction Operations Influencing Adjacent StructuresJay Kavispecial
07/18/2024Structural Steel - DetailsJay Kavispecial
07/18/2024Exhaust and Vent Systems in Plenums and DuctsJay Kavispecial
07/18/2024FinalADEDOSU JOSHUAprogress
07/18/2024Energy Code Compliance InspectionsADEDOSU JOSHUAprogress
07/18/2024Fire-Resistance Rated ConstructionADEDOSU JOSHUAprogress
07/18/2024Permanent certificateADEDOSU JOSHUAenergy_progress
07/18/2024Fenestration air leakageADEDOSU JOSHUAenergy_progress
07/18/2024Fenestration areasADEDOSU JOSHUAenergy_progress
07/18/2024Fenestration and door U-factor and product ratingsADEDOSU JOSHUAenergy_progress
07/18/2024Insulation placement and R valuesADEDOSU JOSHUAenergy_progress
07/18/2024Lighting controlsADEDOSU JOSHUAenergy_progress
07/18/2024HVAC-R and service water piping design and insulationADEDOSU JOSHUAenergy_progress
Latest 25 of 30.
▾Documents — 43 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/27/2026B00826881-P1Request digital key ↗
08/27/2026B00826968-P1Request digital key ↗
08/27/2026B00826968-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸Seals & Professional Certifications34
▸DOB NOWProgress Inspector Seal & Signature22
09/01/2026B00826968-I1Open ↗
09/01/2026B00826968-I1Open ↗
09/01/2026B00826968-I1Open ↗
Showing 3 of 22 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature8
09/01/2026B00826968-I1Open ↗
08/29/2026B00826881-I1Open ↗
08/29/2026B00826881-I1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/27/2026B00826881-I1Open ↗
08/27/2026B00826968-P1Open ↗
08/27/2026B00826968-I1Open ↗
Showing 3 of 4 on file for this type
▸Environmental & Asbestos4
▸DOB NOWDEP ACP-5: Asbestos Assessment Report4
08/27/2026B00826968-I1Open ↗
08/27/2026B00826968-P1Open ↗
08/15/2026B00826881-I1Open ↗
Showing 3 of 4 on file for this type
▸Energy Compliance1
▸DOB NOWPreliminary Commissioning Report Certification1
08/13/2026B00826881-I1Open ↗