← Back
Two stories - detached, small or mid-size
162-23 13 AVENUE
QUEENS · Whitestone-Beechhurst · BIN 4104212
💬 Discuss this project
1955Year Built
1.5Stories
A1Building Class
R2AZoning
1,812 sfGross Floor Area
1Units
Two stories - detached, small or mid-size · 6,000 sf lot · 0.3 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalFire ProtectionGeneral
Permit Issued — active, not yet Signed-off
AtticUnder Construction7p · 1 filing · 20 docs
Floor 2Under Construction7p · 1 filing · 20 docs
Floor 1Under Construction7p · 1 filing · 20 docs
CellarUnder Construction8p · 1 filing · 20 docs
Site & exteriorUnder Construction2p · 1 filing · 2 docs
Filed — no permit issued1p · 1 filing · 3 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
01/10/2025$1.2M—— → —$690/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
N/A109/02/2026
FRANK J QUATELA ARCHITECT P.C407/17/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Manetta architecture design pllc803/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
FK CONSTRUCTION INCGeneral Contractor209/07/2026
GREENGeneral Contractor207/25/2026
CARLIN CONTRACTING OF NYGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HRF SERVICES CORP5616107/08/2025
JSPECS,INC9429207/08/2025
Building Lifecycle
All (67)Filed (5)Permit Issued (5)Objection (27)Special Inspection (30)
09/21/2026
Objection resolved — Resolved
09/21/2026
Objection resolved — Resolved
09/21/2026
Objection resolved — Resolved
09/21/2026
Objection resolved — Resolved
09/21/2026
Objection resolved — Resolved
09/11/2026
Objection resolved — Resolved
09/10/2026
Objection raised — Admin
09/10/2026
Objection raised — Other
09/10/2026
Objection raised — Other
09/10/2026
Objection raised — Other
09/10/2026
Objection raised — Other
09/10/2026
Objection raised — Admin
09/10/2026
Objection raised — Other
09/02/2026
Filed — Alteration
INSTALLATION OF SPRINKLER SYSTEM FILED IN CONJUNCTION WITH ALT APPLICATION Q-01248167 WATER MAIN FILED UNDER ALT APPLICATION
Q01450687-I1
08/24/2026
Special inspection requirement — Sprinkler Systems
08/10/2026
Permit issued — Mechanical Systems
Q01248167-I1-GC-CX
08/10/2026
Permit issued — Construction Fence
Q01249974-I1-FN
07/23/2026
Permit issued — Construction Fence
Q01249974-I1-FN
05/04/2026
Permit issued — Construction Fence
Q01249974-I1-FN
05/01/2026
Permit issued — General Construction
Q01248167-I1-GC-CX
10/01/2025
Objection resolved — Addressed
10/01/2025
Objection resolved — Addressed
08/20/2025
Objection resolved — Addressed
08/19/2025
Objection resolved — Addressed
08/19/2025
Objection resolved — Addressed
08/19/2025
Objection resolved — Addressed
07/30/2025
Objection raised — Cost
07/30/2025
Objection raised — Zoning
07/30/2025
Objection raised — Scope
07/30/2025
Objection resolved — Addressed
07/30/2025
Objection raised — Plumbing
07/30/2025
Objection raised — Plumbing
07/30/2025
Objection raised — Admin
07/28/2025
Objection raised — Energy
07/17/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
NEW 13'-0" (INCLUDING SPLAYS) CURB CUT IN CONJUNCTION WITH GC APPLICATION # Q01248167.
Q01248167-S2
07/08/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
NEW 13'-0" (INCLUDING SPLAYS) CURB CUT IN CONJUNCTION WITH GC APPLICATION # Q01248167.
Q01248167-I1
07/08/2025
Filed — Alteration
ERECT CONSTRUCTION FENCE TO SAFE GUARD PROPERTY AT FRONT. IN CONJUNCTION WITH GC APPLICATION Q01248167. NO CHANGE TO THE USE, EGRESS, AND OCCUPANCY
Q01249974-I1
07/08/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
NEW 13'-0" (INCLUDING SPLAYS) CURB CUT IN CONJUNCTION WITH GC APPLICATION # Q01248167.
Q01248167-S1
07/03/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Jeffrey Stones
07/03/2025
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
Jeffrey Stones
07/03/2025
Special inspection requirement — Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities
SHAHRIAR QUAYYUM
07/03/2025
Special inspection requirement — Energy Code Compliance Inspections
Jeffrey Stones
07/03/2025
Special inspection requirement — HVAC-R and service water heating system controls
Jeffrey Stones
07/03/2025
Special inspection requirement — HVAC-R and service water heating equipment
Jeffrey Stones
07/03/2025
Special inspection requirement — Permanent certificate
Jeffrey Stones
07/03/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Jeffrey Stones
07/03/2025
Special inspection requirement — Maintenance information
Jeffrey Stones
06/27/2025
Special inspection requirement — Energy Code Compliance Inspections
Jeffrey Stones
06/27/2025
Special inspection requirement — Fire-Resistance Rated Construction
Jeffrey Stones
06/27/2025
Special inspection requirement — Structural Wood Frame
Jeffrey Stones
06/27/2025
Special inspection requirement — Final
Jeffrey Stones
06/27/2025
Special inspection requirement — Footing and Foundation
Jeffrey Stones
06/27/2025
Special inspection requirement — Fenestration air leakage
Jeffrey Stones
06/27/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
Jeffrey Stones
06/27/2025
Special inspection requirement — Air barrier — testing
Jeffrey Stones
06/27/2025
Special inspection requirement — HVAC-R and service water heating system controls
Jeffrey Stones
06/27/2025
Special inspection requirement — Maintenance information
Jeffrey Stones
06/27/2025
Special inspection requirement — Fenestration areas
Jeffrey Stones
06/27/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Jeffrey Stones
06/27/2025
Special inspection requirement — Air barrier - visual inspection
Jeffrey Stones
Latest 60 of 67 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsPermit IssuedFK CONSTRUCTION INC08/10/2026
DOB NOWConstruction FencePermit IssuedFK CONSTRUCTION INC08/10/2026
DOB NOWConstruction FencePermit IssuedGREEN07/23/2026
DOB NOWConstruction FencePermit IssuedGREEN05/04/2026
DOB NOWGeneral ConstructionPermit IssuedCARLIN CONTRACTING OF NY05/01/2026
1 project · most recent 07/17/2025
Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
07/17/2025Permit IssuedFK CONSTRUCTION INCHeating and Air Conditioning Systems
Heat / Cool
Goodman GSZB404810 48,000 BTU · Condensing Unit ×3
1 project · most recent 09/02/2026
FiledStatusContractorScope
09/02/2026——63 heads
2 projects · most recent 09/02/2026
Gas Storm Water/Sanitary
FiledStatusContractorScope
09/02/2026———
07/17/2025——Gas, Storm, Water/Sanitary
1 project · most recent 07/17/2025
Steel Wood
FiledStatusContractorScope
07/17/2025Permit IssuedFK CONSTRUCTION INCSteel, Wood
1 project · most recent 07/08/2025
Fence
FiledStatusContractorScope
07/08/2025Permit IssuedFK CONSTRUCTION INCFence
▾Special Inspection Requirements (DOB NOW) — 42
DateRequirementInspectorRole
08/24/2026Sprinkler Systems—special
07/03/2025Fire-Resistant Penetrations and JointsJeffrey Stonesspecial
07/03/2025Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationJeffrey Stonesspecial
07/03/2025Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention FacilitiesSHAHRIAR QUAYYUMspecial
07/03/2025Energy Code Compliance InspectionsJeffrey Stonesprogress
07/03/2025HVAC-R and service water heating system controlsJeffrey Stonesenergy_progress
07/03/2025HVAC-R and service water heating equipmentJeffrey Stonesenergy_progress
07/03/2025Permanent certificateJeffrey Stonesenergy_progress
07/03/2025HVAC-R and service water piping design and insulationJeffrey Stonesenergy_progress
07/03/2025Maintenance informationJeffrey Stonesenergy_progress
06/27/2025Energy Code Compliance InspectionsJeffrey Stonesprogress
06/27/2025Fire-Resistance Rated ConstructionJeffrey Stonesprogress
06/27/2025Structural Wood FrameJeffrey Stonesprogress
06/27/2025FinalJeffrey Stonesprogress
06/27/2025Footing and FoundationJeffrey Stonesprogress
06/27/2025Fenestration air leakageJeffrey Stonesenergy_progress
06/27/2025Fenestration and door U-factor and product ratingsJeffrey Stonesenergy_progress
06/27/2025Air barrier — testing Jeffrey Stonesenergy_progress
06/27/2025HVAC-R and service water heating system controlsJeffrey Stonesenergy_progress
06/27/2025Maintenance informationJeffrey Stonesenergy_progress
06/27/2025Fenestration areasJeffrey Stonesenergy_progress
06/27/2025HVAC-R and service water piping design and insulationJeffrey Stonesenergy_progress
06/27/2025Air barrier - visual inspectionJeffrey Stonesenergy_progress
06/27/2025MeteringJeffrey Stonesenergy_progress
06/27/2025HVAC-R and service water heating equipmentJeffrey Stonesenergy_progress
Latest 25 of 42.
▾Documents — 36 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch5
09/15/2026Q01450687-I1Request digital key ↗
08/19/2026Q01248167-S2Request digital key ↗
08/19/2026Q01248167-I1Request digital key ↗
Showing 3 of 5 on file for this type
▸Applications & Permits2
▸BISBPP-5 - Authorization to the Department of Transportation1
07/29/2025440824413Open ↗
▸BISPLAN / WORK APPROVAL APPLICATION1
07/29/2025440824413Open ↗
▸Zoning, Tax Lot & Property Records2
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026Q01248167-I1Open ↗
▸DOB NOWZD1: DOB Zoning Diagram1
08/13/2026Q01248167-I1Open ↗
▸Seals & Professional Certifications16
▸DOB NOWProgress Inspector Seal & Signature5
08/25/2026Q01248167-S1Open ↗
08/25/2026Q01248167-S1Open ↗
08/23/2026Q01248167-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature5
09/15/2026Q01450687-I1Open ↗
08/19/2026Q01249974-I1Open ↗
08/13/2026Q01248167-S2Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
08/25/2026Q01248167-S1Open ↗
08/25/2026Q01248167-S1Open ↗
08/23/2026Q01248167-I1Open ↗
Showing 3 of 4 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
07/29/2025440824413Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
07/29/2025440824413Open ↗
▸Trade Schedules & Equipment1
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)1
08/13/2026Q01248167-I1Open ↗
▸Safety & Tenant Protection1
▸BISSTREET TREE CHECKLIST1
07/29/2025440824413Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form2
09/15/2026Q01450687-I1Open ↗
08/19/2026Q01248167-I1Open ↗
▸Inspections & Test Reports2
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026Q01248167-I1Open ↗
▸DOB NOWSOIL REPORT1
08/13/2026Q01248167-I1Open ↗
▸Filing & Intake Forms1
▸BISEFILING JOB APPLICATION COVER SHEET1
07/29/2025440824413Open ↗
▸Other Documents4
▸BISBPP - SUPPORTING DOCUMENTATION1
07/29/2025440824413Open ↗
▸DOB NOWSite Survey: Initial1
08/13/2026Q01248167-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/13/2026Q01248167-I1Open ↗
▸DOB NOWProperty Ownership Certification1
08/13/2026Q01248167-I1Open ↗