← Back
QUEENS
162-38 97 STREET
QUEENS · Howard Beach-Lindenwood · BIN 4295810
💬 Discuss this project
—Year Built
—Stories
—Building Class
—Zoning
—Gross Floor Area
—Units
0 Open ViolationsFDNY Report ↗
Locations of Work
Electrical
Roof1p · 1 filing · 8 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
PARKER AND WEST ENGINEERING, PLLC106/12/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SUNRUN INSTALLATION SVCGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
PARKER AND WEST ENGINEERI5272106/12/2026
Building Lifecycle
All (8)Filed (1)Permit Issued (1)Violation (1)Special Inspection (5)
06/18/2026
Permit issued — Solar
Q01415582-I1-SL
06/12/2026
Filed — Alteration
FILING HEREWITH TAX ABATEMENT APPLICATION FOR INSTALLATION OF ROOF-MOUNTED SOLAR PANELS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
Q01415582-I1
06/12/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Walid Abdulla
06/12/2026
Special inspection requirement — Air barrier - visual inspection
Walid Abdulla
06/11/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Walid Abdulla
06/11/2026
Special inspection requirement — Energy Code Compliance Inspections
Walid Abdulla
06/11/2026
Special inspection requirement — Final
Walid Abdulla
04/12/2010
Violation issued (ECB, closed)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offSUNRUN INSTALLATION SVC06/18/2026
BISOTISSUEDRCDOLNER CONSTRUCTION08/05/2003
1 project · most recent 06/12/2026
FiledStatusContractorScope
06/12/2026CompleteSUNRUN SOLAR ELECTL CORP—
1 project · most recent 06/12/2026
FiledStatusContractorScope
06/12/2026Signed-offSUNRUN INSTALLATION SVC18 panels, 8.1 kw, 378.4 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
06/12/2026Structural Stability – Alterations of existing buildingsWalid Abdullaspecial
06/12/2026Air barrier - visual inspectionWalid Abdullaenergy_progress
06/11/2026Fire-Resistant Penetrations and JointsWalid Abdullaspecial
06/11/2026Energy Code Compliance InspectionsWalid Abdullaprogress
06/11/2026FinalWalid Abdullaprogress
▾Documents — 8 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/16/2026Q01415582-I1Request digital key ↗
▸Seals & Professional Certifications6
▸DOB NOWProgress Inspector Seal & Signature3
08/28/2026Q01415582-I1Open ↗
08/28/2026Q01415582-I1Open ↗
08/28/2026Q01415582-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/28/2026Q01415582-I1Open ↗
08/28/2026Q01415582-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/16/2026Q01415582-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/16/2026Q01415582-I1Open ↗