Three families
162 BAY 29TH STREET
BROOKLYN · Bath Beach · BIN 3430048
💬 Discuss this project
2023Year Built
3Stories
C0Building Class
R5Zoning
3,127 sfGross Floor Area
3Units
1 Open Violation 0 unresolved · 1 paperwork only ▸FDNY Report ↗
Three families · Owner of record: SUPERIOR GLOBE LLC · 2,916 sf lot · 1.07 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbing
Roof5p · 3 filings · 20 docs
Bulkhead1p · 1 filing · 2 docs
Floor 24p · 3 filings · 20 docs
Floor 15p · 3 filings · 20 docs
Cellar3p · 2 filings · 20 docs
Basement5p · 3 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
SUPERIOR GLEN CONSTRUCTION1003/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
12/23/2020$4.9M—— → —— not available
07/01/2019$3.6M—Private party → 156 BAY 29TH STREET, LLC— not available
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
BRICOLAGE DESIGNS1108/18/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
BRICOLAGE DESIGNS1103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SANDHU BUILDERS 1 INCGeneral Contractor1207/08/2026
SITE WORKS NYC INCGeneral Contractor303/21/2026
BRUCHE MECHANICAL NY LLCFire Protection207/08/2026
PLBG P & H INCPlumbing207/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
REGIONAL TESTING CORP.394908/18/2025
Building Lifecycle
All (67)Filed (11)Permit Issued (11)Signed Off (3)Inspection (8)Objection (4)Special Inspection (30)
11/13/2025
Signed off — Alteration
install plumbing fixtures & related piping as shown on drawings submitted herewith in conjunction with new building construction
B00361188-I1
09/10/2025
Special inspection requirement — Sprinkler Systems
Paul Raymond
09/02/2025
Signed off — Alteration
B00388477-I1
09/02/2025
Signed off — Alteration
installation of mechanical equipment in conjunction with new building construction
B00360144-I1
08/21/2025
Special inspection requirement — HVAC and service water heating equipment
Paul Raymond
08/21/2025
Special inspection requirement — HVAC and service water heating system controls
Paul Raymond
08/21/2025
Special inspection requirement — Energy Code Compliance Inspections
Paul Raymond
08/21/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Paul Raymond
08/21/2025
Special inspection requirement — Soil Percolation Test - Individual On-Site Private Sewage Disposal Systems
BRIAN FLYNN
08/21/2025
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
Paul Raymond
08/21/2025
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
BRIAN FLYNN
08/21/2025
Special inspection requirement — HVAC insulation and sealing
Paul Raymond
08/18/2025
Filed — Alteration
install sprinkler heads and siamese connection in conjunction with new building construction
B00359867-P1
08/01/2025
Filed — Alteration
install plumbing fixtures & related piping as shown on drawings submitted herewith in conjunction with new building construction
B00361188-P4
08/01/2025
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
BRIAN FLYNN
08/01/2025
Special inspection requirement — Energy Code Compliance Inspections
Paul Raymond
08/01/2025
Special inspection requirement — HVAC and service water heating equipment
Paul Raymond
08/01/2025
Special inspection requirement — HVAC and service water heating system controls
Paul Raymond
08/01/2025
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
Paul Raymond
08/01/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Paul Raymond
08/01/2025
Special inspection requirement — Soil Percolation Test - Individual On-Site Private Sewage Disposal Systems
BRIAN FLYNN
05/06/2025
Objection resolved — Addressed
05/02/2025
Objection raised — Scope
04/30/2025
Filed — Alteration
install plumbing fixtures & related piping as shown on drawings submitted herewith in conjunction with new building construction
B00361188-P3
04/29/2025
Special inspection requirement — HVAC and service water heating system controls
Paul Raymond
04/29/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Paul Raymond
04/29/2025
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
Paul Raymond
04/29/2025
Special inspection requirement — Soil Percolation Test - Individual On-Site Private Sewage Disposal Systems
BRIAN FLYNN
04/29/2025
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
BRIAN FLYNN
04/29/2025
Special inspection requirement — Energy Code Compliance Inspections
Paul Raymond
04/29/2025
Special inspection requirement — HVAC insulation and sealing
Paul Raymond
04/29/2025
Special inspection requirement — HVAC and service water heating equipment
Paul Raymond
04/08/2025
Special inspection requirement — Permanent certificate
Paul Raymond
04/08/2025
Special inspection requirement — HVAC and service water heating system controls
Paul Raymond
04/08/2025
Special inspection requirement — Maintenance information
Paul Raymond
04/08/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Paul Raymond
04/08/2025
Special inspection requirement — Heating Systems
Paul Raymond
04/08/2025
Special inspection requirement — Mechanical Systems
Paul Raymond
04/01/2025
Objection resolved — Addressed
03/31/2025
Filed — Alteration
installation of mechanical equipment in conjunction with new building construction
B00360144-P2
03/31/2025
Objection raised — Scope
03/28/2025
Filed — Alteration
install plumbing fixtures & related piping as shown on drawings submitted herewith in conjunction with new building construction
B00361188-P2
02/19/2025
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
02/10/2025
Permit issued — Sprinklers
B00359867-I1-EW-SP
02/07/2025
Permit issued — Plumbing
B00361188-I1-PL
01/15/2025
Inspection — Pass-Final Curb Cut Non-Directive 14
Pass
View inspection ↗
01/05/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
09/26/2024
Permit issued — Sprinklers
B00359867-I1-EW-SP
09/24/2024
Permit issued — Curb Cut
B00388477-I1-CC
04/01/2024
Permit issued — Mechanical Systems
B00360144-I1-MS
02/28/2024
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
02/28/2024
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
02/28/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
11/09/2023
Permit issued — Construction Fence
B00389904-I1-FN
04/25/2023
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
04/25/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
04/19/2023
Permit issued — Structural
B00359255-I1-ST
04/13/2023
Permit issued — Plumbing
B00361188-I1-PL
03/29/2023
Permit issued — Mechanical Systems
B00360144-I1-MS
12/07/2022
Permit issued — Construction Fence
B00389904-I1-FN
Latest 60 of 67 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSprinklersSigned-offBRUCHE MECHANICAL NY LLC02/10/2025
DOB NOWPlumbingSigned-offPLBG P & H INC02/07/2025
DOB NOWSprinklersSigned-offBRUCHE MECHANICAL NY LLC09/26/2024
DOB NOWCurb CutSigned-offSANDHU BUILDERS 1 INC09/24/2024
DOB NOWMechanical SystemsSigned-offSANDHU BUILDERS 1 INC04/01/2024
DOB NOWConstruction FencePermit IssuedSANDHU BUILDERS 1 INC11/09/2023
DOB NOWStructuralSigned-offSANDHU BUILDERS 1 INC04/19/2023
DOB NOWPlumbingSigned-offPLBG P & H INC04/13/2023
DOB NOWMechanical SystemsSigned-offSANDHU BUILDERS 1 INC03/29/2023
DOB NOWConstruction FencePermit IssuedSANDHU BUILDERS 1 INC12/07/2022
DOB NOWConstruction FencePermit IssuedSITE WORKS NYC INC10/13/2020
BIS—ISSUEDSANDHU BUILDERS 1 INC03/04/2024
BIS—ISSUEDSANDHU BUILDERS 1 INC01/31/2024
BIS—ISSUEDSANDHU BUILDERS 1 INC08/18/2023
BIS—ISSUEDSANDHU BUILDERS 1 INC12/20/2022
BIS—ISSUEDBNA SERVICES INC10/21/2020
1 project · most recent 08/18/2025
FiledStatusContractorScope
08/18/2025Signed-offPLBG P & H INC42 heads
2 projects · most recent 12/12/2023
General Wiring
FiledStatusContractorScope
12/12/2023CompleteERIC & NG ELEC'L, INC.General Wiring
09/15/2023CompleteERIC & NG ELEC'L, INC.—
▾Field Inspections (DOB CAP) — 8
DateTypeResultReport
02/19/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
01/15/2025Pass-Final Curb Cut Non-Directive 14PassView ↗
01/05/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
02/28/2024Certified Gas-Gas-Piping-RoughingCertifiedView ↗
02/28/2024Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
02/28/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
04/25/2023Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
04/25/2023Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 56
DateRequirementInspectorRole
09/10/2025Sprinkler SystemsPaul Raymondspecial
08/21/2025HVAC and service water heating equipment Paul Raymondenergy_progress
08/21/2025HVAC and service water heating system controls Paul Raymondenergy_progress
08/21/2025Energy Code Compliance InspectionsPaul Raymondprogress
08/21/2025Fire-Resistant Penetrations and JointsPaul Raymondspecial
08/21/2025Soil Percolation Test - Individual On-Site Private Sewage Disposal SystemsBRIAN FLYNNspecial
08/21/2025Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationPaul Raymondspecial
08/21/2025Subsurface Investigations (Borings/Test Pits)BRIAN FLYNNspecial
08/21/2025HVAC insulation and sealing Paul Raymondenergy_progress
08/01/2025Subsurface Investigations (Borings/Test Pits)BRIAN FLYNNspecial
08/01/2025Energy Code Compliance InspectionsPaul Raymondprogress
08/01/2025HVAC and service water heating equipment Paul Raymondenergy_progress
08/01/2025HVAC and service water heating system controls Paul Raymondenergy_progress
08/01/2025Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationPaul Raymondspecial
08/01/2025Fire-Resistant Penetrations and JointsPaul Raymondspecial
08/01/2025Soil Percolation Test - Individual On-Site Private Sewage Disposal SystemsBRIAN FLYNNspecial
04/29/2025HVAC and service water heating system controls Paul Raymondenergy_progress
04/29/2025Fire-Resistant Penetrations and JointsPaul Raymondspecial
04/29/2025Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationPaul Raymondspecial
04/29/2025Soil Percolation Test - Individual On-Site Private Sewage Disposal SystemsBRIAN FLYNNspecial
04/29/2025Subsurface Investigations (Borings/Test Pits)BRIAN FLYNNspecial
04/29/2025Energy Code Compliance InspectionsPaul Raymondprogress
04/29/2025HVAC insulation and sealing Paul Raymondenergy_progress
04/29/2025HVAC and service water heating equipment Paul Raymondenergy_progress
04/08/2025Permanent certificatePaul Raymondenergy_progress
Latest 25 of 56.
▾Documents — 163 on file (BIS + DOB NOW)
▸Plans & Drawings11
▸DOB NOWPlans/Sketch - Plumbing4
08/22/2026B00361188-I1Request digital key ↗
08/22/2026B00361188-P4Request digital key ↗
08/15/2026B00361188-P3Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - Sprinkler2
09/02/2026B00359867-I1Request digital key ↗
08/15/2026B00359867-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Mechanical Systems2
09/02/2026B00360144-P2Request digital key ↗
09/02/2026B00360144-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Curb Cut1
09/02/2026B00388477-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Construction Fence1
09/02/2026B00389904-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Structural1
09/02/2026B00359255-I1Request digital key ↗
▸Applications & Permits10
▸BISPLAN / WORK APPROVAL APPLICATION7
03/18/2025322071002Open ↗
03/15/2024322071002Open ↗
10/28/2020322071002Open ↗
Showing 3 of 7 on file for this type
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
01/14/2025322071002Open ↗
▸BISWORK PERMIT APPLICATION1
10/21/2020322071002Open ↗
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION1
10/21/2020322071002Open ↗
▸Zoning, Tax Lot & Property Records5
▸BISZONING EXHIBIT III:DESC. & OWNRSHP.STMNT1
08/20/2020322071002Open ↗
▸BISADDRESS: NEW HOUSE NUMBER APPROVED1
04/15/2020322071002Open ↗
▸BISEASEMENT AND RESTRICTIVE DECLARATIONS - SUPPPORTING DOCUMENTATION1
08/20/2020322071002Open ↗
▸BISZONING DIAGRAM1
09/02/2020322071002Open ↗
▸BISZONING EXHIBIT I: CERTIFICATION1
08/20/2020322071002Open ↗
▸Seals & Professional Certifications68
▸DOB NOWProgress Inspector Seal & Signature33
09/01/2026B00361188-I1Open ↗
09/01/2026B00361188-I1Open ↗
09/01/2026B00361188-I1Open ↗
Showing 3 of 33 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature23
09/01/2026B00361188-I1Open ↗
09/01/2026B00361188-I1Open ↗
09/01/2026B00361188-I1Open ↗
Showing 3 of 23 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature11
08/13/2026B00359255-I1Open ↗
08/13/2026B00361188-P3Open ↗
08/13/2026B00361188-P2Open ↗
Showing 3 of 11 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION1
03/04/2020322071002Open ↗
▸Trade Schedules & Equipment3
▸BISHVAC & SERVICE WATER HEATING EQUIPMENT1
12/19/2025322071002Open ↗
▸BISHVAC & SERVICE WATER HEATING SYSTEM CONTROLS1
12/19/2025322071002Open ↗
▸BIS* SEWER CONNECTION: DEP SD1 & SD21
08/20/2020322071002Open ↗
▸Safety & Tenant Protection4
▸BISEXCAVATION OR DEMOLITION: 5-DAY NOTICE1
10/21/2020322071002Open ↗
▸BISSTREET TREES: RECEIPT OF STREET TREES SITE PLAN1
10/21/2020322071002Open ↗
▸BISSTREET TREE CHECKLIST1
08/07/2020322071002Open ↗
▸BISEXCAVATION - SHEETING, SHORING, AND BRACING1
11/04/2025322071002Open ↗
▸Energy Compliance22
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY4
12/26/2025322071002Open ↗
12/19/2025322071002Open ↗
10/21/2020322071002Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWEN2: As Built Energy Analysis.2
08/13/2026B00360144-I1Open ↗
08/13/2026B00361188-I1Open ↗
▸BISENERGY CODE COMPLIANCE FEE1
01/06/2026322071002Open ↗
▸BISAIR SEALING AND INSULATION - VISUAL1
12/19/2025322071002Open ↗
▸BISTR8: ENERGY CODE PROGRESS INSPS TECHNICAL REPORT1
01/06/2026322071002Open ↗
▸BISINTERIOR LIGHTING POWER1
12/19/2025322071002Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
12/31/2025322071002Open ↗
▸BISFENESTRATION U-FACTOR & PRODUCT RATING1
12/19/2025322071002Open ↗
▸BISFENESTRATION AREAS1
11/04/2025322071002Open ↗
▸BISAIR SEALING AND INSULATION - TESTING1
11/10/2025322071002Open ↗
▸BISINSULATION PLACEMENT & R VALUES1
12/19/2025322071002Open ↗
▸BISLIGHTING IN DWELLING UNITS1
12/19/2025322071002Open ↗
▸BISENERGY CODE COMPLIANCE INSPECTIONS1
12/19/2025322071002Open ↗
▸BISLIGHTING CONTROLS1
12/19/2025322071002Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
03/04/2020322071002Open ↗
▸BISELECTRICAL ENERGY CONSUMPTION1
12/19/2025322071002Open ↗
▸BISEXTERIOR LIGHTING POWER1
12/19/2025322071002Open ↗
▸BISFENESTRATION AIR LEAKAGE1
11/04/2025322071002Open ↗
▸Inspections & Test Reports23
▸BISTECHNICAL REPORT: RESPONSIBILITY7
12/26/2025322071002Open ↗
11/04/2025322071002Open ↗
10/21/2020322071002Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWSOIL REPORT4
08/13/2026B00361188-P2Open ↗
08/13/2026B00361188-P4Open ↗
08/13/2026B00361188-P3Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT: SOIL INSPECTION2
08/20/2020322071002Open ↗
04/15/2020322071002Open ↗
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER2
12/03/2025322071002Open ↗
10/21/2020322071002Open ↗
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)1
11/04/2025322071002Open ↗
▸BISFIRE-RESISTIVE RATED CONSTRUCTION1
11/04/2025322071002Open ↗
▸BISFOOTING AND FOUNDATION INSPECTION1
11/04/2025322071002Open ↗
▸BISMASONRY1
11/04/2025322071002Open ↗
▸BISSUBGRADE INSP / SOILS-SITE PREP1
11/04/2025322071002Open ↗
▸BISSOIL REPORT1
04/15/2020322071002Open ↗
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX1
10/21/2020322071002Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026B00361188-I1Open ↗
▸Approvals, Objections & Sign-offs4
▸BISSCHEDULE A - OCCUPANCY / USE4
03/15/2024322071002Open ↗
08/24/2020322071002Open ↗
08/17/2020322071002Open ↗
Showing 3 of 4 on file for this type
▸Cost, Insurance & Ownership1
▸BISPROJECT-SPECIFIC GL INSURANCE1
10/21/2020322071002Open ↗
▸Filing & Intake Forms4
▸BISEFILING COVER SHEET2
10/28/2020322071002Open ↗
03/04/2020322071002Open ↗
▸BISADDITIONAL INFORMATION2
10/22/2020322071002Open ↗
10/22/2020322071002Open ↗
▸Other Documents8
▸BISSHUTOFF DAMPERS1
12/19/2025322071002Open ↗
▸BISSUSTAINABLE ROOF ZONE FORM1
08/20/2020322071002Open ↗
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
08/07/2020322071002Open ↗
▸BISMAINTENANCE INFORMATION1
12/19/2025322071002Open ↗
▸BISHVAC & SERVICE WATER PIPING DESIGN AND INSULATION1
12/19/2025322071002Open ↗
▸BISPERMANENT CERTIFICATE1
12/19/2025322071002Open ↗
▸BISPROTECTION OF EXPOSED FOUNDATION INSULATION1
12/19/2025322071002Open ↗
▸BISPLOT DIAGRAM1
03/04/2020322071002Open ↗