One story - permanent living quarter
163-41 83 STREET
QUEENS · BIN 4294217
💬 Discuss this project
1965Year Built
1Stories
A2Building Class
R2Zoning
2,093 sfGross Floor Area
1Units
Rent Stabilized2 Open Violations ▸FDNY Report ↗
One story - permanent living quarter · 4,142 sf lot · 0.51 FAR built · Flood zone X500
Locations of Work
Architecture
Roof1p · 1 filing · 13 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
06/28/2024$990K—91 AVE ELITE LLC → Private party$473/sf building
12/20/2023$550K—Private party → 91 AVE ELITE, LLC$263/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
M-CON ENGINEERING, PC205/01/2025
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SUSTAINABLE STRATEGIESGeneral Contractor203/21/2026
SOURCE ELECTRIC INCElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
M-CON ENGINEERING7341205/01/2025
Building Lifecycle
All (19)Filed (2)Permit Issued (1)Signed Off (1)Violation (5)Special Inspection (10)
11/25/2025
Violation issued (HPD, open)
I
05/06/2025
Signed off — Alteration
INSTALLATION OF SOLAR ELECTRIC GENERATION SYSTEM FOR UTILITY INTERCONNECTION
Q01123714-I1
05/01/2025
Filed — Alteration
INSTALLATION OF SOLAR ELECTRIC GENERATION SYSTEM FOR UTILITY INTERCONNECTION
Q01123714-P1
05/01/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Michelle Contri
05/01/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Michelle Contri
05/01/2025
Special inspection requirement — Final
Michelle Contri
05/01/2025
Special inspection requirement — Energy Code Compliance Inspections
Michelle Contri
05/01/2025
Special inspection requirement — Air barrier - visual inspection
Michelle Contri
01/21/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Michelle Contri
01/21/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Michelle Contri
01/21/2025
Special inspection requirement — Energy Code Compliance Inspections
Michelle Contri
01/21/2025
Special inspection requirement — Final
Michelle Contri
01/21/2025
Special inspection requirement — Air barrier - visual inspection
Michelle Contri
12/05/2024
Violation issued (HPD, open)
I
10/15/2024
Permit issued — Solar
Q01123714-I1-SL
10/08/2024
Filed — Alteration
INSTALLATION OF SOLAR ELECTRIC GENERATION SYSTEM FOR UTILITY INTERCONNECTION
Q01123714-I1
05/15/2023
Violation issued (HPD, closed)
I
05/10/2023
Violation issued (HPD, closed)
C
05/10/2023
Violation issued (HPD, closed)
C
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offSUSTAINABLE STRATEGIES10/15/2024
1 project · most recent 09/11/2024
FiledStatusContractorScope
09/11/2024CompleteSOURCE ELECTRIC INC1 meters
▾Special Inspection Requirements (DOB NOW) — 10
DateRequirementInspectorRole
05/01/2025Structural Stability – Alterations of existing buildingsMichelle Contrispecial
05/01/2025Fire-Resistant Penetrations and JointsMichelle Contrispecial
05/01/2025FinalMichelle Contriprogress
05/01/2025Energy Code Compliance InspectionsMichelle Contriprogress
05/01/2025Air barrier - visual inspectionMichelle Contrienergy_progress
01/21/2025Fire-Resistant Penetrations and JointsMichelle Contrispecial
01/21/2025Structural Stability – Alterations of existing buildingsMichelle Contrispecial
01/21/2025Energy Code Compliance InspectionsMichelle Contriprogress
01/21/2025FinalMichelle Contriprogress
01/21/2025Air barrier - visual inspectionMichelle Contrienergy_progress
▾Documents — 13 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/20/2026Q01123714-I1Request digital key ↗
08/20/2026Q01123714-P1Request digital key ↗
▸Seals & Professional Certifications8
▸DOB NOWProgress Inspector Seal & Signature4
08/29/2026Q01123714-I1Open ↗
08/29/2026Q01123714-I1Open ↗
08/22/2026Q01123714-P1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/13/2026Q01123714-I1Open ↗
08/13/2026Q01123714-P1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/29/2026Q01123714-I1Open ↗
08/22/2026Q01123714-P1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/13/2026Q01123714-P1Open ↗
08/13/2026Q01123714-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01123714-I1Open ↗