| Owner | Filings | Most Recent |
|---|---|---|
| 213 Essex Street | 24 | 07/08/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 08/03/2023 | $320K | — | LIVERPOOL 8 LLC → 163-57 PHROANE LLC | $111/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| Sion Consulting Engineering | 14 | 07/27/2026 |
| Advance Design Group | 2 | 05/08/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| Sion Consulting Engineering | 26 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Mod Consultants | General Contractor | 4 | 07/08/2026 |
| All Pro Plumbing & Heating | specialty_contractor | 3 | 07/08/2026 |
| Helmsley Group | Scaffold | 1 | 04/09/2026 |
| Mod Consultants | Scaffold | 1 | 04/09/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| All State Property Inspec | 4288 | 14 | 07/27/2026 |
| HRF Services | 5616 | 4 | 02/04/2025 |
| Triangle Inspection & Tes | 7495 | 2 | 08/11/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Signed-off | Mod Consultants | 01/15/2025 |
| DOB NOW | General Construction | Permit Issued | Mod Consultants | 01/15/2025 |
| DOB NOW | Plumbing | Signed-off | All Pro Plumbing & Heating | 12/16/2024 |
| DOB NOW | Construction Fence | Signed-off | Mod Consultants | 02/12/2024 |
| DOB NOW | Plumbing | Signed-off | All Pro Plumbing & Heating | 10/17/2023 |
| DOB NOW | Sprinklers | Signed-off | All Pro Plumbing & Heating | 10/11/2023 |
| DOB NOW | General Construction | Permit Issued | Mod Consultants | 10/10/2023 |
| DOB NOW | Structural | Signed-off | Mod Consultants | 10/02/2023 |
| DOB NOW | Construction Fence | Signed-off | Helmsley Group | 07/25/2023 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/08/2024 | Signed-off | All Pro Plumbing & Heating | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/27/2024 | Complete | K.A.B. Electric | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/30/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/18/2025 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 02/20/2025 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 01/13/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 01/07/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 01/19/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 01/19/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 01/19/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/19/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/26/2026 | Fire-Resistance Rated Construction | SEBERT DYER | progress |
| 08/26/2026 | Energy Code Compliance Inspections | SEBERT DYER | progress |
| 08/26/2026 | Subsurface Investigations (Borings/Test Pits) | FAHAD FATEH | special |
| 08/26/2026 | Protection of exposed foundation insulation | SEBERT DYER | energy_progress |
| 08/26/2026 | HVAC-R and service water heating system controls | SEBERT DYER | energy_progress |
| 08/26/2026 | Fenestration air leakage | SEBERT DYER | energy_progress |
| 08/26/2026 | Metering | SEBERT DYER | energy_progress |
| 08/26/2026 | Fire-Resistant Penetrations and Joints | SEBERT DYER | special |
| 08/26/2026 | Permanent certificate | SEBERT DYER | energy_progress |
| 08/26/2026 | HVAC-R and service water piping design and insulation | SEBERT DYER | energy_progress |
| 08/26/2026 | HVAC-R and service water heating equipment | SEBERT DYER | energy_progress |
| 08/26/2026 | Insulation placement and R values | SEBERT DYER | energy_progress |
| 08/26/2026 | Maintenance information | SEBERT DYER | energy_progress |
| 08/26/2026 | Electric vehicle service equipment requirements | SEBERT DYER | energy_progress |
| 08/26/2026 | Fenestration areas | SEBERT DYER | energy_progress |
| 08/26/2026 | Air barrier - visual inspection | SEBERT DYER | energy_progress |
| 08/26/2026 | Fenestration and door U-factor and product ratings | SEBERT DYER | energy_progress |
| 08/26/2026 | Interior lighting power | SEBERT DYER | energy_progress |
| 07/17/2026 | Interior lighting power | SEBERT DYER | energy_progress |
| 07/17/2026 | Maintenance information | SEBERT DYER | energy_progress |
| 07/17/2026 | Fenestration air leakage | SEBERT DYER | energy_progress |
| 07/17/2026 | Fire-Resistant Penetrations and Joints | SEBERT DYER | special |
| 07/17/2026 | Subsurface Investigations (Borings/Test Pits) | FAHAD FATEH | special |
| 07/17/2026 | Energy Code Compliance Inspections | SEBERT DYER | progress |
| 07/17/2026 | Fire-Resistance Rated Construction | SEBERT DYER | progress |