| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/28/2022 | Complete | HI-RITE ELECTRIC CORP | General Wiring |
| Owner | Filings | Most Recent |
|---|---|---|
| SYMPLER | 20 | 07/08/2026 |
| STRUCTURELINE | 2 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 01/21/2022 | $2.4M | — | Private party → Private party | $1,270/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| ALEXALLEN STUDIO ARCHITECTS | 4 | 02/25/2026 |
| YORKOS ENGINEERING DESIGN CONSULT | 5 | 12/04/2024 |
| CELIN MUNOZ CONSULTING ENGINEER, PC | 1 | 06/29/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| ANZALONE ARCHITECTURE | 20 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| HENG YIP CONSTRUCTION COR | General Contractor | 5 | 07/08/2026 |
| STRUCTURELINE INC | General Contractor | 4 | 03/21/2026 |
| FLYTIGER P & H LTD | Plumbing | 3 | 07/08/2026 |
| HI-RITE ELECTRIC CORP | Electrical | 1 | 03/22/2026 |
| FLYTIGER PLB & HTG LTD | Fire Protection | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SD TESTING & INSPECTION S | 7010 | 4 | 02/25/2026 |
| YORKOS ENGINEERING, DESIG | 6991 | 5 | 12/04/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | FLYTIGER P & H LTD | 10/08/2024 |
| DOB NOW | Mechanical Systems | Signed-off | HENG YIP CONSTRUCTION COR | 09/03/2024 |
| DOB NOW | General Construction | Permit Issued | HENG YIP CONSTRUCTION COR | 08/16/2023 |
| DOB NOW | Plumbing | Signed-off | FLYTIGER P & H LTD | 04/05/2023 |
| DOB NOW | Plumbing | Signed-off | FLYTIGER PLB & HTG LTD | 04/05/2023 |
| DOB NOW | Construction Fence | Signed-off | HENG YIP CONSTRUCTION COR | 03/01/2023 |
| DOB NOW | General Construction | Signed-off | STRUCTURELINE INC | 02/22/2023 |
| DOB NOW | Plumbing | Signed-off | FLYTIGER P & H LTD | 01/05/2023 |
| DOB NOW | General Construction | Permit Issued | STRUCTURELINE INC | 12/13/2022 |
| BIS | EQ | ISSUED | SPRING SCAFFOLDING INC. | 05/25/2001 |
| Date | Type | Result | Report |
|---|---|---|---|
| 10/28/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 10/28/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/25/2024 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 10/16/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/27/2023 | Pass-Final SP - Up to 9 Requested Floors | Pass | View ↗ |
| 10/23/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/24/2023 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/03/2026 | Air barrier - visual inspection | XIUCHENG LI | energy_progress |
| 03/03/2026 | Metering | XIUCHENG LI | energy_progress |
| 03/03/2026 | Fenestration and door U-factor and product ratings | XIUCHENG LI | energy_progress |
| 03/03/2026 | Lighting in dwelling units | XIUCHENG LI | energy_progress |
| 03/03/2026 | Fenestration areas | XIUCHENG LI | energy_progress |
| 03/03/2026 | Permanent certificate | XIUCHENG LI | energy_progress |
| 03/03/2026 | Fenestration air leakage | XIUCHENG LI | energy_progress |
| 03/03/2026 | Fire-Resistant Penetrations and Joints | XIUCHENG LI | special |
| 03/03/2026 | Chimneys and vents | XIUCHENG LI | special |
| 03/03/2026 | Structural Stability – Alterations of existing buildings | XIUCHENG LI | special |
| 03/03/2026 | Fire-Resistance Rated Construction | XIUCHENG LI | progress |
| 03/03/2026 | Energy Code Compliance Inspections | XIUCHENG LI | progress |
| 03/03/2026 | Insulation placement and R values | XIUCHENG LI | energy_progress |
| 11/26/2024 | Energy Code Compliance Inspections | BALTU YORKOS | progress |
| 11/26/2024 | HVAC-R and service water heating equipment | BALTU YORKOS | energy_progress |
| 11/26/2024 | HVAC-R and service water piping design and insulation | BALTU YORKOS | energy_progress |
| 11/26/2024 | HVAC-R and service water heating system controls | BALTU YORKOS | energy_progress |
| 11/26/2024 | Maintenance information | BALTU YORKOS | energy_progress |
| 11/26/2024 | Fire-Resistant Penetrations and Joints | BALTU YORKOS | special |