← Back
Two family converted from one family
163 CRYSTAL STREET
BROOKLYN · East New York-City Line · BIN 3094999
💬 Discuss this project
1930Year Built
2Stories
B3Building Class
R5Zoning
1,320 sfGross Floor Area
2Units
Two family converted from one family · 3,000 sf lot · 0.44 FAR built · Flood zone X
Locations of Work
MechanicalPlumbing
Floor 210p · 2 filings · 6 docs
Floor 110p · 2 filings · 6 docs
Cellar10p · 2 filings · 6 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
MONTE SION CHRISTIAN CHURCH503/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
BRIAN MCDONOUGH, PE207/19/2023
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SUPER COOL HVAC, LLCGeneral Contractor303/21/2026
VICTORY PLBG & HTG INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
COLLECTIF ENGINEERING, PL7799107/19/2023
Building Lifecycle
All (26)Filed (2)Permit Issued (2)Signed Off (2)Inspection (3)Objection (14)Special Inspection (3)
02/07/2024
Signed off — Alteration
Construction of (2) new mini split systems with associated distribution.
B00905921-I1
02/07/2024
Signed off — Alteration
Replacement of existing hot water heater, gas piping replacement
B00906369-I1
10/05/2023
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
10/04/2023
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
09/15/2023
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
08/21/2023
Permit issued — Plumbing
B00906369-I1-PL
08/11/2023
Permit issued — Mechanical Systems
B00905921-I1-MS
07/25/2023
Objection raised — Scope
07/25/2023
Objection resolved — Addressed
07/25/2023
Objection raised — Scope
07/25/2023
Objection resolved — Addressed
07/25/2023
Objection raised — Fire_Protection
07/25/2023
Objection resolved — Addressed
07/25/2023
Objection raised — Other
07/25/2023
Objection resolved — Addressed
07/25/2023
Objection raised — Scope
07/25/2023
Objection resolved — Addressed
07/25/2023
Objection raised — Admin
07/25/2023
Objection resolved — Addressed
07/25/2023
Objection raised — Inspections
07/25/2023
Objection resolved — Addressed
07/19/2023
Filed — Alteration
Construction of (2) new mini split systems with associated distribution.
B00905921-I1
07/19/2023
Filed — Alteration
Replacement of existing hot water heater, gas piping replacement
B00906369-I1
07/19/2023
Special inspection requirement — Energy Code Compliance Inspections
RAFAEL FIGUEROA
07/18/2023
Special inspection requirement — Mechanical Systems
RAFAEL FIGUEROA
07/18/2023
Special inspection requirement — Final
RAFAEL FIGUEROA
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offVICTORY PLBG & HTG INC08/21/2023
DOB NOWMechanical SystemsSigned-offSUPER COOL HVAC, LLC08/11/2023
Nothing on file for this building.
▾Field Inspections (DOB CAP) — 3
DateTypeResultReport
10/05/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
10/04/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
09/15/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 3
DateRequirementInspectorRole
07/19/2023Energy Code Compliance InspectionsRAFAEL FIGUEROAprogress
07/18/2023Mechanical SystemsRAFAEL FIGUEROAspecial
07/18/2023FinalRAFAEL FIGUEROAprogress
▾Documents — 6 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/27/2026B00905921-I1Request digital key ↗
08/15/2026B00906369-I1Request digital key ↗
▸Seals & Professional Certifications4
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/27/2026B00906369-I1Open ↗
08/27/2026B00905921-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature1
09/02/2026B00905921-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
09/02/2026B00905921-I1Open ↗