← Back
Elevator cooperative
163 EAST 81 STREET
MANHATTAN · Upper East Side-Carnegie Hill · BIN 1047567
💬 Discuss this project
1927Year Built
9Stories
D4Building Class
R8BZoning
59,149 sfGross Floor Area
42Units
LL97 CoveredRent Stabilized3 Open Violations ▸FISP: SWARMP
Elevator cooperative · Owner of record: 165 E 81 ST CP · 8,085 sf lot · 7.32 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingEquipmentGeneral
Roof2p · 1 filing · 3 docs
Penthouse1p · 2 filings · 15 docs
Floor 102 filings · 8 docs
Floor 91 filing · 20 docs
Floor 8
Floor 7
Floor 6
Floor 5
Floor 4
Floor 3
Floor 21p · 2 filings · 19 docs
Floor 11 filing · 3 docs
Sub-Basement1 filing · 13 docs
Site & exterior5 filings · 12 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
163 EAST 81 STREET1003/21/2026
163 E 81ST STREET903/21/2026
163 EAST 81ST STREET603/21/2026
165 EAST 81 STREET503/21/2026
CHARLES H GREENTHAL MANAGEMENT503/21/2026
165 E 81ST STREET503/21/2026
CHARLES H. GREENTHAL403/21/2026
163 EAST 81ST303/21/2026
165 EAST 81ST STREET CORP C O CH203/21/2026
165 E 81 ST CP103/22/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JM ZONING, LLC.1003/21/2026
CONVERSANO ASSOCIATES, INC.603/21/2026
KNA CONSULTING403/21/2026
Rigid Structural Design, LLC403/21/2026
LEE ENGINEERING CONSULTING603/21/2026
AE DESIGN SOLUTION403/21/2026
BOYD CONSULTING203/21/2026
J CALLAHAN CONSULTING203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
NEW AMSTERDAM RESTORATIONGeneral Contractor1007/08/2026
HATCHET WORKS CORPGeneral Contractor707/08/2026
EVEREST SCAFFOLDING INCGeneral Contractor507/08/2026
INTERIOR MASTERS GROUP OFGeneral Contractor407/08/2026
GO PRO PLUMBING AND HEATINGPlumbing307/25/2026
COOLING CONTROLS CORPGeneral Contractor303/21/2026
ESSENTIAL REMODELING INCGeneral Contractor303/21/2026
KNG CONSTRUCTION CO INCGeneral Contractor203/21/2026
PK ELECTRIC INCElectrical103/22/2026
PORRINO, MARINElectrical103/21/2026
ADRIATIC PLBG & HTG CORPPlumbing107/08/2026
FORTE EXPRESS P & H INCPlumbing107/08/2026
H.K. MECHANICAL SVC CORPPlumbing107/08/2026
M&G PLUMBING AND HEATINGPlumbing107/08/2026
ALABAMA IRONWORKS INCElectrical103/21/2026
ZATOS PLBG AND HTG INCPlumbing106/28/2026
ALEXANDRE, JOSEPHElectrical103/21/2026
CARL WEISSElectrical103/21/2026
FRANK FRANCOElectrical103/21/2026
GLENDALE ELECTL CONTNG INElectrical103/22/2026
JEROME KRITZElectrical103/21/2026
KATZ, FElectrical103/21/2026
PANDER, JAMESElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
BFS ARCHITECT PC7477606/26/2026
WINTON GROUP ARCHITECTURE4343603/21/2024
DEAN MENDEZ ARCHITECT, P.8621103/29/2023
MELONE ARCHITECTS2944103/29/2023
Building Lifecycle
All (169)Filed (25)Permit Issued (25)Signed Off (13)Facade (FISP) (12)Violation (50)Inspection (12)Objection (2)Special Inspection (30)
07/23/2026
Permit issued — Plumbing
M00977820-S1-PL
06/26/2026
Filed — Alteration
FILED HEREWITH FOR PLUMBING WORK IN UNIT 9CD, NO CHANGE TO USE EGRESS OR OCCUPANCY
M00977820-P3
06/26/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Belal Salim
06/26/2026
Special inspection requirement — Tenant Protection Plan Compliance
Belal Salim
06/10/2026
Signed off — Alteration
FILED HEREWITH FOR PLUMBING WORK IN UNIT 9CD, NO CHANGE TO USE EGRESS OR OCCUPANCY
M00977820-I1
06/09/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Belal Salim
06/09/2026
Special inspection requirement — Tenant Protection Plan Compliance
05/19/2026
Permit issued — Plumbing
M00977820-S1-PL
05/18/2026
Special inspection requirement — Lighting in dwelling units
Belal Salim
05/18/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Belal Salim
05/18/2026
Special inspection requirement — Tenant Protection Plan Compliance
Belal Salim
05/18/2026
Special inspection requirement — Final
Belal Salim
05/18/2026
Special inspection requirement — Fire-Resistance Rated Construction
Belal Salim
05/15/2026
Filed — Alteration
FILED HEREWITH FOR PLUMBING WORK IN UNIT 9CD, NO CHANGE TO USE EGRESS OR OCCUPANCY
M00977820-P2
05/15/2026
Filed — Alteration
FILED HEREWITH FOR PLUMBING WORK IN UNIT 9CD, NO CHANGE TO USE EGRESS OR OCCUPANCY
M00977820-P1
07/09/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
06/02/2025
Filed — Alteration
Filing herewith for the renovation of Apt 2C. Plumbing modifications to existing plumbing systems. There is no change in use, egress, or occupancy.
M00870160-P1
04/22/2025
Signed off — Alteration
PROPOSED WORK INCLUDES THE INSTALLATION OF A NEW GAS DRYER AND THE ASSOCIATED NEW GAS DRYER VENT TO CONNECT TO EXISTING EXTERIOR LOUVER. NEW GAS TEE CONNECTION FOR NEW GAS DRYER TO BE MADE FROM EXISTING 3/4" GAS LINE TO EXISTING GAS RANGE.
M01095576-I1
03/27/2025
Special inspection requirement — Tenant Protection Plan Compliance
03/27/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Belal Salim
03/21/2025
Objection raised — Scope
03/21/2025
Objection resolved — Addressed
03/20/2025
Filed — Alteration
PROPOSED WORK INCLUDES THE INSTALLATION OF A NEW GAS DRYER AND THE ASSOCIATED NEW GAS DRYER VENT TO CONNECT TO EXISTING EXTERIOR LOUVER. NEW GAS TEE CONNECTION FOR NEW GAS DRYER TO BE MADE FROM EXISTING 3/4" GAS LINE TO EXISTING GAS RANGE.
M01095576-P2
01/24/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
12/30/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
12/11/2024
Filed — Alteration
PROPOSED WORK INCLUDES THE INSTALLATION OF A NEW GAS DRYER AND THE ASSOCIATED NEW GAS DRYER VENT TO CONNECT TO EXISTING EXTERIOR LOUVER. NEW GAS TEE CONNECTION FOR NEW GAS DRYER TO BE MADE FROM EXISTING 3/4" GAS LINE TO EXISTING GAS RANGE.
M01095576-P1
12/02/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
10/18/2024
Signed off — Alteration
Exterior facade repairs including select masonry repairs as shown on drawings and as specified. No change in use, occupancy, or egress.
M00840682-I1
10/09/2024
Permit issued — Plumbing
M01095576-I1-PL
09/23/2024
Filed — Alteration
PROPOSED WORK INCLUDES THE INSTALLATION OF A NEW GAS DRYER AND THE ASSOCIATED NEW GAS DRYER VENT TO CONNECT TO EXISTING EXTERIOR LOUVER. NEW GAS TEE CONNECTION FOR NEW GAS DRYER TO BE MADE FROM EXISTING 3/4" GAS LINE TO EXISTING GAS RANGE.
M01095576-I1
08/23/2024
Signed off — Alteration
FILING HEREWITH INSTALLATION OF HVAC SYSTEM AS INDICATED ON THE DRAWINGS. NO CHANGE IN USE EGRESS OR OCCUPANCY
M00297851-I1
08/09/2024
Signed off — Alteration
M00860601-I1
08/07/2024
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
08/01/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
07/31/2024
Permit issued — Mechanical Systems
M00297851-I1-MS
07/30/2024
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
07/26/2024
Signed off — Alteration
Installation of a temporarily Material hoist per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M00868588-I1
07/26/2024
Signed off — Alteration
Installation of a temporarily supported scaffold per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M00851404-I1
07/26/2024
Signed off — Alteration
M00851399-I1
07/17/2024
Signed off — Alteration
Mechanical application filed for renovation in PHC. Install new split system ducted and ductless air conditioning.
M00880818-I1
07/17/2024
Permit issued — General Construction
M00870160-I1-GC
06/23/2024
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/20/2024
Signed off — Alteration
INSTALLATION OF A SUSPENDED SCAFFOLD FOR FACADE INSPECTION AND REPAIR AS PER THE PLANS SUBMITTED. NO CHANGE TO EGRESS OR OCCUPANCY.
M01017898-I1
06/18/2024
Signed off — Alteration
Interior renovations of apartment PHC on the 10th floor of an existing residential building. No change in use, occupancy or egress.
M00860619-I1
05/01/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
04/16/2024
Permit issued — Plumbing
M00870160-S1-PL
04/08/2024
Permit issued — General Construction
M00870160-I1-GC
03/25/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Vladimir Kaushansky
03/21/2024
Filed — Alteration
Interior renovations of apartment PHC on the 10th floor of an existing residential building. No change in use, occupancy or egress.
M00860619-P2
03/19/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Vladimir Kaushansky
03/18/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
03/12/2024
Permit issued — Suspended Scaffold
M01017898-I1-SC
03/11/2024
Filed — Alteration
INSTALLATION OF A SUSPENDED SCAFFOLD FOR FACADE INSPECTION AND REPAIR AS PER THE PLANS SUBMITTED. NO CHANGE TO EGRESS OR OCCUPANCY.
M01017898-I1
03/11/2024
Filed — Alteration
Interior renovations of apartment PHC on the 10th floor of an existing residential building. No change in use, occupancy or egress.
M00860619-P1
02/21/2024
Permit issued — Plumbing
M00977820-S1-PL
02/08/2024
Permit issued — Plumbing
M00977820-S1-PL
01/26/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Vladimir Kaushansky
01/25/2024
Permit issued — General Construction
M00977820-I1-GC
01/25/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
01/24/2024
Filed — Alteration
FILED HEREWITH FOR PLUMBING WORK IN UNIT 9CD, NO CHANGE TO USE EGRESS OR OCCUPANCY
M00977820-S1
Latest 60 of 169 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offGO PRO PLUMBING AND HEATING07/23/2026
DOB NOWPlumbingSigned-offGO PRO PLUMBING AND HEATING05/19/2026
DOB NOWPlumbingSigned-offADRIATIC PLBG & HTG CORP10/09/2024
DOB NOWMechanical SystemsSigned-offHATCHET WORKS CORP07/31/2024
DOB NOWGeneral ConstructionPermit IssuedKNG CONSTRUCTION CO INC07/17/2024
DOB NOWPlumbingSigned-offM&G PLUMBING AND HEATING04/16/2024
DOB NOWGeneral ConstructionPermit IssuedKNG CONSTRUCTION CO INC04/08/2024
DOB NOWSuspended ScaffoldSigned-offNEW AMSTERDAM RESTORATION03/12/2024
DOB NOWPlumbingSigned-offGO PRO PLUMBING AND HEATI02/21/2024
DOB NOWPlumbingSigned-offZATOS PLBG AND HTG INC02/08/2024
DOB NOWGeneral ConstructionSigned-offESSENTIAL REMODELING INC01/25/2024
DOB NOWGeneral ConstructionSigned-offINTERIOR MASTERS GROUP OF12/19/2023
DOB NOWMechanical SystemsSigned-offHATCHET WORKS CORP07/19/2023
DOB NOWMechanical SystemsSigned-offCOOLING CONTROLS CORP07/12/2023
DOB NOWGeneral ConstructionSigned-offINTERIOR MASTERS GROUP OF07/07/2023
DOB NOWPlumbingSigned-offH.K. MECHANICAL SVC CORP07/07/2023
DOB NOWGeneral ConstructionSigned-offNEW AMSTERDAM RESTORATION05/18/2023
DOB NOWSidewalk ShedSigned-offNEW AMSTERDAM RESTORATION05/11/2023
DOB NOWProtection and Mechanical MethodsSigned-offNEW AMSTERDAM RESTORATION05/05/2023
DOB NOWSupported ScaffoldSigned-offNEW AMSTERDAM RESTORATION05/05/2023
DOB NOWMechanical SystemsSigned-offHATCHET WORKS CORP04/18/2022
DOB NOWPlumbingSigned-offFORTE EXPRESS P & H INC01/17/2020
DOB NOWSidewalk ShedSigned-offEVEREST SCAFFOLDING INC07/26/2018
DOB NOWSupported ScaffoldSigned-offEVEREST SCAFFOLDING INC04/12/2018
DOB NOWSidewalk ShedSigned-offEVEREST SCAFFOLDING INC04/11/2018
BISOTISSUEDHATCHET WORKS CORP07/19/2023
BISOTISSUEDHATCHET WORKS CORP08/22/2022
BISPLISSUEDAJC PLUMBING & HTG CORP06/23/2022
BISOTISSUEDHATCHET WORKS CORP02/28/2022
BISPLISSUEDCODE MECHANICAL INC08/21/2020
BISOTISSUEDARCH 2 STUDIO LLC07/01/2020
BISOTISSUEDLICO CONTRACTING INC01/07/2020
BISOTISSUEDROMANOV INC07/06/2018
BISOTISSUEDETNA CONTRACTING INC05/15/2018
BISPLISSUEDPRECISION PLBG SVCS., INC05/04/2018
BISOTISSUEDETNA CONTRACTING INC02/22/2018
BISPLISSUEDCOSME PLBG & HTG CORP01/29/2018
BISOTISSUEDROMANOV INC10/02/2017
BISPLISSUEDPRECISION PLBG SVCS., INC02/01/2017
BISOTISSUEDALL DIMENSION HOME IMPROVEMENT01/30/2017
+ 35 more permits on file
3 projects · most recent 06/26/2026
Water/Sanitary Gas
FiledStatusContractorScope
06/26/2026Signed-offGO PRO PLUMBING AND HEATIGas, Water/Sanitary
06/02/2025Signed-offM&G PLUMBING AND HEATINGGas, Water/Sanitary
11/25/2019Signed-offFORTE EXPRESS P & H INCWater/Sanitary
17 projects · most recent 08/04/2026
General Wiring
FiledStatusContractorScope
08/04/2026Permit IssuedCENTURY ELECTRIC LLCGeneral Wiring
06/10/2026Permit IssuedK & G ELECTRIC CO., INCGeneral Wiring
01/29/2026CompleteETRICITY ELECTRICAL CO INGeneral Wiring
04/29/2025Permit IssuedSOURCE ELECTRIC INCGeneral Wiring
11/05/2024Permit IssuedBRANDL ELECTRIC INC.General Wiring
08/05/2024Permit IssuedALL WAYS ELECTRIC CORP.WGeneral Wiring
01/26/2024CompletePREMIUM ELECTRIC INCGeneral Wiring
09/14/2023CompletePK ELECTRIC INCGeneral Wiring
06/15/2023CompleteGLENDALE ELECTL CONTNG INGeneral Wiring
05/17/2023Permit IssuedPOWER SURGE ELECTRIC, INCGeneral Wiring
05/12/2023CompleteGLENDALE ELECTL CONTNG IN—
03/10/2022Permit IssuedMLS ELECTRIC LLCGeneral Wiring
10/01/2021CompleteWARREN OSTROFF ELEC., INCGeneral Wiring
12/27/2019Permit IssuedJOSEPH SGROI & SONS, INC.General Wiring
06/27/2019Permit IssuedGRX EURO ELECTRIC CORPGeneral Wiring
▾Field Inspections (DOB CAP) — 12
DateTypeResultReport
07/09/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
01/24/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
12/30/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/02/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
08/07/2024Pass-Final General Construction Non-Directive 14PassView ↗
08/01/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
07/30/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
05/01/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
03/18/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/25/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
11/13/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
09/21/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 35
DateRequirementInspectorRole
06/26/2026Fire-Resistant Penetrations and JointsBelal Salimspecial
06/26/2026Tenant Protection Plan ComplianceBelal Salimspecial
06/09/2026Fire-Resistant Penetrations and JointsBelal Salimspecial
06/09/2026Tenant Protection Plan Compliance—special
05/18/2026Lighting in dwelling unitsBelal Salimenergy_progress
05/18/2026Fire-Resistant Penetrations and JointsBelal Salimspecial
05/18/2026Tenant Protection Plan ComplianceBelal Salimspecial
05/18/2026FinalBelal Salimprogress
05/18/2026Fire-Resistance Rated ConstructionBelal Salimprogress
03/27/2025Tenant Protection Plan Compliance—special
03/27/2025Fire-Resistant Penetrations and JointsBelal Salimspecial
03/25/2024Fire-Resistant Penetrations and JointsVladimir Kaushanskyspecial
03/19/2024Fire-Resistant Penetrations and JointsVladimir Kaushanskyspecial
01/26/2024Fire-Resistant Penetrations and JointsVladimir Kaushanskyspecial
05/24/2023Lighting in dwelling unitsKRISTIN LUKSenergy_progress
05/04/2023Energy Code Compliance Inspectionstyler ellisprogress
05/04/2023Lighting in dwelling unitstyler ellisenergy_progress
05/04/2023Lighting controlstyler ellisenergy_progress
05/04/2023Finaltyler ellisprogress
04/17/2023Fire-Resistant Penetrations and JointsVladimir Kaushanskyspecial
03/08/2023Construction Operations Influencing Adjacent StructuresNicholas Melonespecial
03/08/2023Structural Stability – Alterations of existing buildingsNicholas Melonespecial
03/08/2023Tenant Protection Plan ComplianceDean Mendezspecial
03/08/2023MasonryNicholas Melonespecial
03/08/2023FinalNicholas Meloneprogress
Latest 25 of 35.
▾Documents — 422 on file (BIS + DOB NOW)
▸Plans & Drawings25
▸DOB NOWPlans/Sketch23
09/06/2026M00029847-I1Request digital key ↗
09/06/2026M00029848-I1Request digital key ↗
08/31/2026M00840682-I1Request digital key ↗
Showing 3 of 23 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems1
09/05/2026M00297851-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing1
09/05/2026M00244150-I1Request digital key ↗
▸Applications & Permits66
▸BISWORK PERMIT APPLICATION36
06/23/2022123156182Open ↗
03/01/2022123156182Open ↗
03/01/2022123156182Open ↗
Showing 3 of 36 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION29
06/28/2024123156182Open ↗
06/28/2024123156182Open ↗
06/28/2024123156182Open ↗
Showing 3 of 29 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION1
01/10/2017122977154Open ↗
▸Seals & Professional Certifications99
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION37
01/08/2020123739785Open ↗
11/04/2019123739785Open ↗
10/01/2019123333641Open ↗
Showing 3 of 37 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature24
09/06/2026M00029847-I1Open ↗
08/31/2026M00840682-I1Open ↗
08/31/2026M00851399-I1Open ↗
Showing 3 of 24 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature17
09/23/2026M00977820-P3Open ↗
09/01/2026M00860601-I1Open ↗
09/01/2026M00977820-P2Open ↗
Showing 3 of 17 on file for this type
▸DOB NOWProgress Inspector Seal & Signature15
09/01/2026M00860601-I1Open ↗
08/31/2026M00870160-I1Open ↗
08/31/2026M00870160-I1Open ↗
Showing 3 of 15 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST3
02/19/2016121793416Open ↗
Showing 1 of 3 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT3
02/19/2016121793416Open ↗
Showing 1 of 3 on file for this type
▸Trade Schedules & Equipment30
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE11
04/19/2019123156182Open ↗
11/08/2018122861527Open ↗
02/16/2018123333641Open ↗
Showing 3 of 11 on file for this type
▸BISSELF-CERT PLUMBING NOTICE10
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 10 on file for this type
▸BISSCHEDULE B - PLUMBING7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT2
02/19/2016121793416Open ↗
Showing 1 of 2 on file for this type
▸Safety & Tenant Protection12
▸BISTenant Protection Plan and Notes10
11/25/2019123739785Open ↗
11/04/2019123739785Open ↗
04/19/2019123156182Open ↗
Showing 3 of 10 on file for this type
▸BISDS1-Demolition Submittal Certification Form1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWTenant Protection Plan1
08/13/2026M00297851-I1Open ↗
▸Environmental & Asbestos39
▸DOB NOWDEP ACP-5: Asbestos Assessment Report17
08/31/2026M00840682-I1Open ↗
08/23/2026M00870160-S1Open ↗
08/17/2026M00977820-P3Open ↗
Showing 3 of 17 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)13
11/26/2019123739785Open ↗
04/19/2019123156182Open ↗
10/26/2017123300463Open ↗
Showing 3 of 13 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form2
08/17/2026M00977820-I1Open ↗
08/17/2026M00977820-S1Open ↗
▸BISDEP ASBESTOS PROJECT COMPLETION FORM1
12/01/2016122861527Open ↗
▸Energy Compliance37
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS22
01/08/2020123739785Open ↗
11/04/2019123739785Open ↗
10/01/2019123333641Open ↗
Showing 3 of 22 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS8
03/21/2024123156182Open ↗
10/01/2019123333641Open ↗
03/19/2019123300463Open ↗
Showing 3 of 8 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY3
06/10/2024123156182Open ↗
03/20/2024123156182Open ↗
06/30/2020123156182Open ↗
▸BISENERGY CODE COMPLIANCE INSPECTIONS1
12/21/2020123739785Open ↗
▸BISLIGHTING IN DWELLING UNITS1
12/21/2020123739785Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
12/21/2020123739785Open ↗
▸BISTECHNICAL REPORT: ENERGY1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Inspections & Test Reports12
▸BISTECHNICAL REPORT: RESPONSIBILITY9
07/10/2024123156182Open ↗
07/05/2024123156182Open ↗
06/10/2024123156182Open ↗
Showing 3 of 9 on file for this type
▸BISSTRUCTURAL STABILITY - EXISTING BUILDINGS1
12/21/2020123739785Open ↗
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)1
12/21/2020123739785Open ↗
▸BISTECHNICAL REPORT: PILE DRIVING1
01/10/2017122977154Open ↗
▸Approvals, Objections & Sign-offs33
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST16
02/19/2025123156182Open ↗
12/21/2020123739785Open ↗
10/01/2019123333641Open ↗
Showing 3 of 16 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION6
06/24/2022123156182Open ↗
04/19/2019123156182Open ↗
06/15/2017121793416Open ↗
Showing 3 of 6 on file for this type
▸BISADMINISTRATIVE OBJECTIONS6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISSUPERSEDING LETTER4
03/29/2024123156182Open ↗
03/01/2022123156182Open ↗
03/01/2022123156182Open ↗
Showing 3 of 4 on file for this type
▸BISFINAL1
12/21/2020123739785Open ↗
▸Cost, Insurance & Ownership33
▸BISCOST AFFIDAVIT31
06/10/2024123156182Open ↗
11/04/2019123739785Open ↗
10/01/2019123333641Open ↗
Showing 3 of 31 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW31
12/21/2020123739785Open ↗
▸BISHIC LICENSE OR AFFIDAVIT1
12/13/2016122861527Open ↗
▸Filing & Intake Forms33
▸BISEFILING COVER SHEET17
11/01/2019123739785Open ↗
04/19/2019123156182Open ↗
08/13/2018123471787Open ↗
Showing 3 of 17 on file for this type
▸BISADDITIONAL INFORMATION9
06/28/2024123156182Open ↗
11/15/2018122861527Open ↗
02/20/2018123333641Open ↗
Showing 3 of 9 on file for this type
▸BISBOROUGH INTAKE FORM7
10/01/2019123333641Open ↗
03/19/2019123300463Open ↗
01/18/2019122861527Open ↗
Showing 3 of 7 on file for this type
▸Other Documents3
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
06/28/2024123156182Open ↗
▸DOB NOWManufacturer's Specifications1
08/13/2026M01017898-I1Open ↗
▸DOB NOWCalculations1
08/13/2026M01017898-I1Open ↗