← Back
Two stories - detached, small or mid-size
164-10 71 AVENUE
QUEENS · BIN 4150277
💬 Discuss this project
1920Year Built
2.5Stories
A1Building Class
R3-2Zoning
1,360 sfGross Floor Area
1Units
2 Open Violations ▸FDNY Report ↗
Two stories - detached, small or mid-size · Owner of record: SP71 LLC · 4,058 sf lot · 0.34 FAR built · Flood zone X
Locations of Work
ArchitectureMechanical
Permit Issued — active, not yet Signed-off
Floor 2Under Construction8p · 1 filing · 20 docs
Floor 1Under Construction8p · 1 filing · 20 docs
CellarUnder Construction8p · 1 filing · 20 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
03/13/2025$950K—Private party → SP71 LLC$699/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
LI ARCHITECT ASSOCIATE, PLLC410/21/2025
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
IMPACT BUILDERS CORPGeneral Contractor107/29/2026
RECORD GROUP INCGeneral Contractor109/01/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AA BUILDING & INSPECTION1519105/30/2025
WORLD DESIGN ARCHITECTURE9323105/30/2025
Building Lifecycle
All (71)Filed (4)Permit Issued (2)Violation (8)Objection (27)Special Inspection (30)
08/31/2026
Permit issued — General Construction
Q01231082-I1-GC-CX
07/28/2026
Permit issued — Construction Fence
Q01231082-S2-FN
06/25/2026
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
06/08/2026
Special inspection requirement — HVAC-R and service water heating system controls
06/08/2026
Special inspection requirement — Maintenance information
06/08/2026
Special inspection requirement — HVAC-R and service water heating equipment
06/08/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
06/08/2026
Special inspection requirement — Energy Code Compliance Inspections
06/08/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
01/26/2026
Objection resolved — Addressed
12/09/2025
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
Rajasekhar Sakhamuri
12/08/2025
Objection raised — Cost
12/08/2025
Objection resolved — Addressed
12/08/2025
Objection raised — Scope
11/21/2025
Objection resolved — Addressed
11/13/2025
Objection raised — Plumbing
11/13/2025
Objection raised — Other
11/11/2025
Objection raised — Scope
11/11/2025
Objection raised — Zoning
11/10/2025
Objection raised — Other
11/07/2025
Objection raised — Energy
10/21/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
ENLARGEMENT OF EXSITING ONE FAMILY TO CONVERT TO TWO DWELLING UNIT. OBTAIN NEW C OF O.
Q01231082-S2
10/21/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
ENLARGEMENT OF EXSITING ONE FAMILY TO CONVERT TO TWO DWELLING UNIT. OBTAIN NEW C OF O.
Q01231082-S3
10/21/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
ENLARGEMENT OF EXSITING ONE FAMILY TO CONVERT TO TWO DWELLING UNIT. OBTAIN NEW C OF O.
Q01231082-S4
10/02/2025
Objection resolved — Addressed
08/15/2025
Objection resolved — Addressed
08/14/2025
Objection raised — Admin
08/14/2025
Objection resolved — Addressed
08/14/2025
Objection resolved — Addressed
07/31/2025
Objection resolved — Addressed
07/03/2025
Objection resolved — Addressed
07/01/2025
Objection resolved — Addressed
07/01/2025
Objection resolved — Addressed
06/24/2025
Objection raised — Zoning
06/24/2025
Objection raised — Scope
06/24/2025
Objection raised — Structural
06/17/2025
Objection raised — Zoning
06/17/2025
Objection raised — Scope
06/17/2025
Objection raised — Energy
06/17/2025
Objection raised — Structural
05/30/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
ENLARGEMENT OF EXSITING ONE FAMILY TO CONVERT TO TWO DWELLING UNIT. OBTAIN NEW C OF O.
Q01231082-I1
05/27/2025
Special inspection requirement — Electric vehicle service equipment requirements
JEFFREY BELL
05/27/2025
Special inspection requirement — Energy Code Compliance Inspections
JEFFREY BELL
05/27/2025
Special inspection requirement — Fire-Resistance Rated Construction
JEFFREY BELL
05/27/2025
Special inspection requirement — Interior lighting power
JEFFREY BELL
05/27/2025
Special inspection requirement — Duct leakage testing, insulation and design
JEFFREY BELL
05/27/2025
Special inspection requirement — Metering
JEFFREY BELL
05/27/2025
Special inspection requirement — Maintenance information
JEFFREY BELL
05/27/2025
Special inspection requirement — Heating Systems
William Alicea
05/27/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
William Alicea
05/27/2025
Special inspection requirement — Exhaust and Vent Systems in Plenums and Ducts
Younes Abouyaala
05/27/2025
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
William Alicea
05/27/2025
Special inspection requirement — Demolition
Younes Abouyaala
05/27/2025
Special inspection requirement — Concrete - Cast-In-Place
William Alicea
05/27/2025
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
William Alicea
05/23/2025
Special inspection requirement — Mechanical Systems
William Alicea
05/23/2025
Special inspection requirement — Final
RICHARD MUESCH JR.
05/23/2025
Special inspection requirement — Footing and Foundation
JEFFREY BELL
05/23/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
JEFFREY BELL
05/23/2025
Special inspection requirement — Fenestration areas
JEFFREY BELL
Latest 60 of 71 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedRECORD GROUP INC08/31/2026
DOB NOWConstruction FencePermit IssuedIMPACT BUILDERS CORP07/28/2026
BIS—ISSUEDTHREE STAR CONSTR COMP INC08/24/2007
1 project · most recent 10/21/2025
Heating and Air Conditioning Systems Ventilation Systems
FiledStatusContractorScope
10/21/2025Permit IssuedRECORD GROUP INCHeating and Air Conditioning Systems, Ventilation Systems
1 project · most recent 10/21/2025
Storm Water/Sanitary
FiledStatusContractorScope
10/21/2025——Storm, Water/Sanitary
1 project · most recent 10/21/2025
FiledStatusContractorScope
10/21/2025Permit IssuedRECORD GROUP INC1 scope_items
▾Special Inspection Requirements (DOB NOW) — 36
DateRequirementInspectorRole
06/25/2026Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation—special
06/08/2026HVAC-R and service water heating system controls—energy_progress
06/08/2026Maintenance information—energy_progress
06/08/2026HVAC-R and service water heating equipment—energy_progress
06/08/2026HVAC-R and service water piping design and insulation—energy_progress
06/08/2026Energy Code Compliance Inspections—progress
06/08/2026Fire-Resistant Penetrations and Joints—special
12/09/2025Subsurface Investigations (Borings/Test Pits)Rajasekhar Sakhamurispecial
05/27/2025Electric vehicle service equipment requirementsJEFFREY BELLenergy_progress
05/27/2025Energy Code Compliance InspectionsJEFFREY BELLprogress
05/27/2025Fire-Resistance Rated ConstructionJEFFREY BELLprogress
05/27/2025Interior lighting powerJEFFREY BELLenergy_progress
05/27/2025Duct leakage testing, insulation and designJEFFREY BELLenergy_progress
05/27/2025MeteringJEFFREY BELLenergy_progress
05/27/2025Maintenance informationJEFFREY BELLenergy_progress
05/27/2025Heating SystemsWilliam Aliceaspecial
05/27/2025Fire-Resistant Penetrations and JointsWilliam Aliceaspecial
05/27/2025Exhaust and Vent Systems in Plenums and DuctsYounes Abouyaalaspecial
05/27/2025Excavations - Sheeting, Shoring, and BracingWilliam Aliceaspecial
05/27/2025DemolitionYounes Abouyaalaspecial
05/27/2025Concrete - Cast-In-PlaceWilliam Aliceaspecial
05/27/2025Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationWilliam Aliceaspecial
05/23/2025Mechanical SystemsWilliam Aliceaspecial
05/23/2025FinalRICHARD MUESCH JR.progress
05/23/2025Footing and FoundationJEFFREY BELLprogress
Latest 25 of 36.
▾Documents — 38 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch5
08/18/2026Q01231082-S4Request digital key ↗
08/18/2026Q01231082-S5Request digital key ↗
08/18/2026Q01231082-S3Request digital key ↗
Showing 3 of 5 on file for this type
▸Applications & Permits6
▸BISPLAN / WORK APPROVAL APPLICATION6
05/06/2025402038282Open ↗
03/16/2025402038282Open ↗
02/10/2025402038282Open ↗
Showing 3 of 6 on file for this type
▸Zoning, Tax Lot & Property Records2
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026Q01231082-I1Open ↗
▸DOB NOWZD1: DOB Zoning Diagram1
08/13/2026Q01231082-I1Open ↗
▸Seals & Professional Certifications16
▸DOB NOWSpecial Inspector Seal & Signature8
08/25/2026Q01231082-I1Open ↗
08/25/2026Q01231082-I1Open ↗
08/25/2026Q01231082-I1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature5
08/18/2026Q01231082-S2Open ↗
08/13/2026Q01231082-I1Open ↗
08/13/2026Q01231082-S3Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWProgress Inspector Seal & Signature3
08/25/2026Q01231082-I1Open ↗
08/25/2026Q01231082-I1Open ↗
08/25/2026Q01231082-I1Open ↗
▸Environmental & Asbestos5
▸DOB NOWDEP ACP-5: Asbestos Assessment Report5
08/18/2026Q01231082-S5Open ↗
08/13/2026Q01231082-S2Open ↗
08/13/2026Q01231082-S4Open ↗
Showing 3 of 5 on file for this type
▸Inspections & Test Reports1
▸DOB NOWSOIL REPORT1
08/13/2026Q01231082-I1Open ↗
▸Other Documents3
▸DOB NOWSite Survey: Initial1
08/13/2026Q01231082-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/13/2026Q01231082-I1Open ↗
▸DOB NOWProperty Ownership Certification1
08/13/2026Q01231082-I1Open ↗