← Back
Two family converted from one family
164 EAST 81 STREET
MANHATTAN · Upper East Side-Carnegie Hill · BIN 1047529
💬 Discuss this project
1899Year Built
3Stories
B3Building Class
R8BZoning
4,160 sfGross Floor Area
2Units
Two family converted from one family · Owner of record: CASA81 LLC · 2,087 sf lot · 1.99 FAR built · Flood zone X
Locations of Work
MechanicalPlumbingEquipment
Floor 47p · 1 filing · 2 docs
Floor 37p · 1 filing · 2 docs
Floor 27p · 2 filings · 9 docs
Floor 115p · 3 filings · 20 docs
Cellar9p · 3 filings · 20 docs
Basement3p · 2 filings · 20 docs
Sub-Basement11p · 3 filings · 20 docs
Site & exterior21p · 4 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
CASA811907/08/2026
OWNERS REP507/08/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
06/10/2020$8.6M—— → —$2,061/sf building
06/19/2019$8.8M—Private party → Private party$2,103/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
HANINGTON ENGINEERING CONSULTANTS508/24/2023
ANDREW CARACCIOLO204/13/2021
PAUL PERDEK, PROF. ENG. PLLC203/24/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
DVA Advisors703/21/2026
AE DESIGN SOLUTION403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CORE SCAFFOLD SYSTEMS INC.General Contractor407/08/2026
DPH PLUMBING & HTG CORPPlumbing307/08/2026
COMFORT TECH MECHANICAL CGeneral Contractor107/08/2026
GREGG NY PLUMBING, INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
INTEGRITY CONSULTING SERV666508/24/2023
Building Lifecycle
All (40)Filed (9)Permit Issued (7)Signed Off (3)Inspection (2)Objection (8)Special Inspection (11)
10/24/2023
Signed off — Alteration
Gas piping work as shown on the plans
M00436245-I1
10/24/2023
Signed off — Alteration
Mechanical work as shown on the plans.
M00436244-I1
08/24/2023
Filed — Alteration
Gas piping work as shown on the plans
M00436245-P3
08/23/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
ALEKSANDR LEVIN
08/23/2023
Special inspection requirement — Energy Code Compliance Inspections
ALEKSANDR LEVIN
06/05/2023
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
05/16/2023
Permit issued — Plumbing
M00436245-I1-PL
03/29/2023
Filed — Alteration
Gas piping work as shown on the plans
M00436245-P2
03/27/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
ALEKSANDR LEVIN
03/27/2023
Special inspection requirement — Energy Code Compliance Inspections
ALEKSANDR LEVIN
02/27/2023
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
10/12/2022
Filed — Alteration
Gas piping work as shown on the plans
M00436245-P1
10/03/2022
Special inspection requirement — Energy Code Compliance Inspections
ALEKSANDR LEVIN
10/03/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
ALEKSANDR LEVIN
08/19/2022
Permit issued — Mechanical Systems
M00436244-I1-MS
08/09/2022
Signed off — Alteration
Plumbing work as shown on the plans.
M00370158-I1
05/11/2022
Permit issued — Plumbing
M00436245-I1-PL
12/28/2021
Permit issued — Plumbing
M00370158-I1-PL
04/15/2021
Special inspection requirement — Energy Code Compliance Inspections
ANDREW CARACCIOLO
04/13/2021
Filed — Alteration
Plumbing work as shown on the plans.
M00370158-P1
04/06/2021
Special inspection requirement — Energy Code Compliance Inspections
ANDREW CARACCIOLO
03/29/2021
Permit issued — Supported Scaffold
M00491500-I1-SF
03/24/2021
Filed — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00491500-I1
03/24/2021
Filed — Alteration
M00491485-I1
03/24/2021
Permit issued — Sidewalk Shed
M00491485-I1-SH
02/10/2021
Objection raised — Fire_Protection
02/10/2021
Objection resolved — Addressed
02/10/2021
Objection raised — Fire_Protection
02/10/2021
Objection resolved — Addressed
02/10/2021
Objection raised — Fire_Protection
02/10/2021
Objection resolved — Addressed
02/10/2021
Objection raised — Scope
02/10/2021
Objection resolved — Addressed
02/08/2021
Filed — Alteration
Gas piping work as shown on the plans
M00436245-I1
02/08/2021
Filed — Alteration
Mechanical work as shown on the plans.
M00436244-I1
12/24/2020
Permit issued — Plumbing
M00370158-I1-PL
12/08/2020
Special inspection requirement — Fireplaces
ALEKSANDR LEVIN
12/03/2020
Special inspection requirement — Mechanical Systems
ALEKSANDR LEVIN
12/03/2020
Special inspection requirement — Final
ALEKSANDR LEVIN
11/02/2020
Filed — Alteration
Plumbing work as shown on the plans.
M00370158-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offGREGG NY PLUMBING, INC05/16/2023
DOB NOWMechanical SystemsSigned-offCOMFORT TECH MECHANICAL C08/19/2022
DOB NOWPlumbingSigned-offDPH PLUMBING & HTG CORP05/11/2022
DOB NOWPlumbingSigned-offDPH PLUMBING & HTG CORP12/28/2021
DOB NOWSupported ScaffoldPermit IssuedCORE SCAFFOLD SYSTEMS INC03/29/2021
DOB NOWSidewalk ShedPermit IssuedCORE SCAFFOLD SYSTEMS INC03/24/2021
DOB NOWPlumbingSigned-offDPH PLUMBING & HTG CORP12/24/2020
BISOTISSUEDANDALORO CONSTRUCTION LLC08/23/2022
BISOTISSUEDANDALORO CONSTRUCTION LLC08/02/2021
BISOTISSUEDANDALORO CONSTRUCTION LLC04/08/2021
BISOTISSUEDANDALORO CONSTRUCTION LLC02/04/2021
BISOTISSUEDANDALORO CONSTRUCTION LLC08/12/2020
BISPLISSUEDGRAHAM PLUMBING CO09/12/1994
BISOTISSUEDTACONIC BUILDERS,INC.08/23/1994
2 projects · most recent 03/21/2021
General Wiring
FiledStatusContractorScope
03/21/2021Permit IssuedV. VASS ELECTRIC CORP—
09/10/2020CompletePOLYPHASE ELECTRIC INC.General Wiring
1 project · most recent 03/24/2021
Scaffold
FiledStatusContractorScope
03/24/2021Permit IssuedCORE SCAFFOLD SYSTEMS INCScaffold
▾Field Inspections (DOB CAP) — 2
DateTypeResultReport
06/05/2023Fail-Final PL - Up to 3 Requested FloorsFailView ↗
02/27/2023Fail-Final PL - Up to 3 Requested FloorsFailView ↗
▾Special Inspection Requirements (DOB NOW) — 11
DateRequirementInspectorRole
08/23/2023Fire-Resistant Penetrations and JointsALEKSANDR LEVINspecial
08/23/2023Energy Code Compliance InspectionsALEKSANDR LEVINprogress
03/27/2023Fire-Resistant Penetrations and JointsALEKSANDR LEVINspecial
03/27/2023Energy Code Compliance InspectionsALEKSANDR LEVINprogress
10/03/2022Energy Code Compliance InspectionsALEKSANDR LEVINprogress
10/03/2022Fire-Resistant Penetrations and JointsALEKSANDR LEVINspecial
04/15/2021Energy Code Compliance InspectionsANDREW CARACCIOLOprogress
04/06/2021Energy Code Compliance InspectionsANDREW CARACCIOLOprogress
12/08/2020FireplacesALEKSANDR LEVINenergy_progress
12/03/2020Mechanical SystemsALEKSANDR LEVINspecial
12/03/2020FinalALEKSANDR LEVINprogress
▾Documents — 93 on file (BIS + DOB NOW)
▸Plans & Drawings9
▸DOB NOWPlans/Sketch - Plumbing6
09/03/2026M00370158-I1Request digital key ↗
08/31/2026M00436245-P2Request digital key ↗
08/31/2026M00436245-P1Request digital key ↗
Showing 3 of 6 on file for this type
▸DOB NOWPlans/Sketch2
09/04/2026M00491485-I1Request digital key ↗
09/04/2026M00491500-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Mechanical Systems1
09/04/2026M00436244-I1Request digital key ↗
▸Applications & Permits6
▸BISPLAN / WORK APPROVAL APPLICATION4
04/16/2021140921750Open ↗
12/07/2020140975728Open ↗
11/12/2020140975728Open ↗
Showing 3 of 4 on file for this type
▸BISWORK PERMIT APPLICATION2
02/04/2021140975728Open ↗
08/12/2020140921750Open ↗
▸Seals & Professional Certifications23
▸DOB NOWDPL-1: Design Professional Seal & Signature9
09/03/2026M00370158-I1Open ↗
08/31/2026M00436245-P1Open ↗
08/31/2026M00436245-I1Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWProgress Inspector Seal & Signature7
08/31/2026M00370158-I1Open ↗
08/31/2026M00436244-I1Open ↗
08/31/2026M00436244-I1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
08/31/2026M00436244-I1Open ↗
08/25/2026M00436245-P2Open ↗
08/24/2026M00436245-P3Open ↗
Showing 3 of 4 on file for this type
▸BISAPPLICANT OWNER SIGNATURE2
11/12/2020140975728Open ↗
07/09/2020140921750Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
11/12/2020140975728Open ↗
▸Safety & Tenant Protection6
▸BISTenant Protection Plan and Notes2
11/16/2020140975728Open ↗
07/09/2020140921750Open ↗
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM2
12/14/2020140975728Open ↗
08/12/2020140921750Open ↗
▸DOB NOWTenant Protection Plan2
09/03/2026M00370158-I1Open ↗
08/13/2026M00370158-P1Open ↗
▸Environmental & Asbestos10
▸DOB NOWDEP ACP-5: Asbestos Assessment Report7
09/03/2026M00370158-I1Open ↗
08/31/2026M00436245-P1Open ↗
08/31/2026M00436245-P2Open ↗
Showing 3 of 7 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)3
12/14/2020140975728Open ↗
12/07/2020140975728Open ↗
07/09/2020140921750Open ↗
▸Energy Compliance8
▸BISAS-BUILT ENERGY ANALYSIS (EN2)2
10/24/2023140975728Open ↗
10/24/2023140921750Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
11/12/2020140975728Open ↗
07/09/2020140921750Open ↗
▸BISENERGY CODE COMPLIANCE INSPECTIONS2
10/24/2023140975728Open ↗
10/24/2023140921750Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
11/12/2020140975728Open ↗
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026M00436244-I1Open ↗
▸Inspections & Test Reports14
▸BISTECHNICAL REPORT: RESPONSIBILITY5
10/24/2023140921750Open ↗
02/04/2021140975728Open ↗
11/12/2020140975728Open ↗
Showing 3 of 5 on file for this type
▸BISFIRE-RESISTIVE RATED CONSTRUCTION2
10/24/2023140921750Open ↗
10/24/2023140921750Open ↗
▸BISSTRUCTURAL STABILITY - ALTERATIONS OF EXISTING BUILDINGS2
10/24/2023140921750Open ↗
10/16/2023140975728Open ↗
▸BISSTRUCTURAL STEEL - DETAILS1
10/16/2023140975728Open ↗
▸BISSTRUCTURAL STEEL - HIGH STRENGTH BOLTING1
10/16/2023140975728Open ↗
▸BISSTRUCTURAL STEEL - WELDING1
10/16/2023140975728Open ↗
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)1
10/24/2023140921750Open ↗
▸BISPOST-INSTALLED ANCHORS1
10/16/2023140975728Open ↗
▸Approvals, Objections & Sign-offs4
▸BISFINAL2
10/24/2023140921750Open ↗
10/16/2023140975728Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST2
10/25/2023140921750Open ↗
10/25/2023140975728Open ↗
▸Cost, Insurance & Ownership4
▸BISCOST AFFIDAVIT (FINAL): PW32
10/17/2023140921750Open ↗
10/17/2023140975728Open ↗
▸BISCOST AFFIDAVIT2
11/16/2020140975728Open ↗
07/09/2020140921750Open ↗
▸Filing & Intake Forms7
▸BISADDITIONAL INFORMATION5
04/21/2021140921750Open ↗
04/08/2021140921750Open ↗
01/12/2021140921750Open ↗
Showing 3 of 5 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET2
11/12/2020140975728Open ↗
07/09/2020140921750Open ↗
▸Other Documents2
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION2
07/29/2020140921750Open ↗
07/29/2020140921750Open ↗