| Owner | Filings | Most Recent |
|---|---|---|
| DSNY | 40 | 09/15/2026 |
| NYC DEPARTMENT OF SANITATION | 19 | 07/08/2026 |
| NYC DEPT OF DESIGN CONSTRUCTION | 2 | 03/21/2026 |
| DCAS | 2 | 03/21/2026 |
| DEPT OF GENERAL SERVICES | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| YSRAEL A. SEINUK, P.C. | 5 | 08/27/2026 |
| DATTNER ARCHITECTS | 13 | 08/26/2026 |
| SESI | 2 | 07/13/2026 |
| PAUL PERDEK | 1 | 04/07/2026 |
| BURNS ENGINEERING, PC | 17 | 03/10/2026 |
| LANGAN ENGINEERING | 1 | 02/26/2026 |
| KM ASSOCIATES OF NY | 1 | 02/05/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| WILLIAM VITACCO ASSOCIATES | 33 | 03/21/2026 |
| JAM CONSULTANTS, INC. | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| PRISMATIC DEVELOPMENT COR | General Contractor | 7 | 07/08/2026 |
| FORSYTHE PLBG & HTG CORP | Plumbing | 3 | 07/08/2026 |
| WELKIN FIRE PROTECTION LL | Fire Protection | 2 | 07/08/2026 |
| MCGEE, PETER | Electrical | 2 | 03/21/2026 |
| NEW WAN IRON WORK INC | Electrical | 2 | 03/21/2026 |
| R.A.M.S. MECHANICAL INC | General Contractor | 2 | 07/08/2026 |
| TODARO JOSEPH | Electrical | 1 | 03/21/2026 |
| AMG DEMOLITION INC | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| TWIN PEAKS INC. | 317 | 32 | 08/27/2026 |
| SESI CONSULTING ENGINEERS | 414 | 2 | 07/13/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | R.A.M.S. MECHANICAL INC | 05/27/2026 |
| DOB NOW | Earth Work | Permit Issued | PRISMATIC DEVELOPMENT COR | 05/08/2026 |
| DOB NOW | Structural | Permit Issued | PRISMATIC DEVELOPMENT COR | 05/06/2026 |
| DOB NOW | General Construction | Permit Issued | PRISMATIC DEVELOPMENT COR | 05/06/2026 |
| DOB NOW | Structural | Permit Issued | PRISMATIC DEVELOPMENT COR | 05/05/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | AMG DEMOLITION INC | 04/22/2026 |
| DOB NOW | Sprinklers | Permit Issued | WELKIN FIRE PROTECTION LL | 04/15/2026 |
| DOB NOW | Plumbing | Permit Issued | FORSYTHE PLBG & HTG CORP | 04/15/2026 |
| DOB NOW | Sprinklers | Permit Issued | WELKIN FIRE PROTECTION LL | 04/15/2026 |
| DOB NOW | Structural | Permit Issued | PRISMATIC DEVELOPMENT COR | 04/14/2026 |
| DOB NOW | Plumbing | Permit Issued | FORSYTHE PLBG & HTG CORP | 04/14/2026 |
| DOB NOW | Plumbing | Permit Issued | FORSYTHE PLBG & HTG CORP | 04/14/2026 |
| DOB NOW | General Construction | Permit Issued | PRISMATIC DEVELOPMENT COR | 04/14/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | R.A.M.S. MECHANICAL INC | 04/14/2026 |
| DOB NOW | Construction Fence | Permit Issued | PRISMATIC DEVELOPMENT COR | 03/18/2026 |
| BIS | OT | ISSUED | GLASS ARMOR OF NEW YORK I | 06/17/2008 |
| BIS | OT | ISSUED | GLASS ARMOR OF NEW YORK I | 06/30/2006 |
| BIS | OT | ISSUED | ERD ENVIROMENTAL INC | 01/28/1997 |
| BIS | EQ | ISSUED | A. RUSSO WRECKING INC. | 08/29/1994 |
| BIS | — | ISSUED | A. RUSSO WRECKING INC. | 08/29/1994 |
| BIS | PL | ISSUED | BRONXCHESTER G. C. INC. | 05/16/1991 |
| BIS | EQ | ISSUED | UNITED HOISTING CO. | 05/03/1990 |
| BIS | — | ISSUED | GROVE CONTRACTING CORP | 11/21/1989 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 03/06/2026 | Permit Issued | R.A.M.S. MECHANICAL INC | Associated Ducts and Piping | Ducts & Piping Ruskin ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/06/2026 | Permit Issued | WELKIN FIRE PROTECTION LL | 2 heads, 2 outlets |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/26/2026 | Permit Issued | FORSYTHE PLBG & HTG CORP | Storm |
| 03/06/2026 | Permit Issued | FORSYTHE PLBG & HTG CORP | Storm, Water/Sanitary |
| 03/06/2026 | — | — | — |
| 02/26/2026 | Permit Issued | FORSYTHE PLBG & HTG CORP | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/24/2026 | Permit Issued | SCHLESINGER ELECT'L CONTR | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/27/2026 | Permit Issued | AMG DEMOLITION INC | Steel, Concrete |
| 08/26/2026 | Permit Issued | PRISMATIC DEVELOPMENT COR | 6 scope_items |
| 03/13/2026 | Permit Issued | PRISMATIC DEVELOPMENT COR | 1 scope_items |
| 03/10/2026 | Permit Issued | PRISMATIC DEVELOPMENT COR | Steel, Concrete |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/05/2026 | Fenestration and door U-factor and product ratings | Maxim Korngold | energy_progress |
| 08/05/2026 | Fenestration air leakage | Maxim Korngold | energy_progress |
| 08/05/2026 | Insulation placement and R values | Maxim Korngold | energy_progress |
| 08/05/2026 | Air barrier - visual inspection | Maxim Korngold | energy_progress |
| 08/05/2026 | Structural Stability – Alterations of existing buildings | Maxim Korngold | special |
| 08/05/2026 | Masonry | Maxim Korngold | special |
| 08/05/2026 | Concrete - Cast-In-Place | Maxim Korngold | special |
| 08/05/2026 | Final | Maxim Korngold | progress |
| 08/05/2026 | Structural Steel - Welding | Maxim Korngold | special |
| 08/05/2026 | Structural Steel - High Strength Bolting | Maxim Korngold | special |
| 08/05/2026 | Structural Steel - Details | Maxim Korngold | special |
| 08/05/2026 | Concrete - Cast-In-Place | Maxim Korngold | special |
| 08/05/2026 | Fire-Resistant Penetrations and Joints | Maxim Korngold | special |
| 08/05/2026 | Sprayed fire-resistant materials | Maxim Korngold | special |
| 08/05/2026 | Structural Stability – Alterations of existing buildings | Maxim Korngold | special |
| 08/05/2026 | Energy Code Compliance Inspections | Maxim Korngold | progress |
| 08/05/2026 | Final | Maxim Korngold | progress |
| 07/24/2026 | Subsurface Conditions – Fill Placement & In-Place Density | MICHAEL ST. PIERRE | special |
| 07/24/2026 | Excavations - Sheeting, Shoring, and Bracing | MICHAEL ST. PIERRE | special |
| 07/10/2026 | Subsurface Conditions – Fill Placement & In-Place Density | MICHAEL ST. PIERRE | special |
| 07/10/2026 | Excavations - Sheeting, Shoring, and Bracing | MICHAEL ST. PIERRE | special |
| 04/17/2026 | Structural Stability – Alterations of existing buildings | MAXIM KORNGOLD | special |
| 04/17/2026 | Structural Steel - Details | MAXIM KORNGOLD | special |
| 04/17/2026 | Final | MAXIM KORNGOLD | progress |
| 03/25/2026 | HVAC-R and service water heating system controls | MAXIM KORNGOLD | energy_progress |