| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/12/2026 | Permit Issued | TARGET PIPING NY LLC | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/12/2026 | Permit Issued | B&B MECH PLBG & HTG LLC | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/23/2026 | Permit Issued | RICHARD NEU | — |
| 05/27/2026 | Permit Issued | LIGHTFORCE ELECL CONTNG I | General Wiring |
| 12/16/2025 | Permit Issued | LIGHTFORCE ELECL CONTNG I | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/12/2026 | Permit Issued | B&B MECH PLBG & HTG LLC | Steel, Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/13/2026 | Permit Issued | PLATINUM SERVICES NY LLC | Scaffold, Sidewalk Shed |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/12/2026 | Permit Issued | B&B MECH PLBG & HTG LLC | Earthwork |
| Owner | Filings | Most Recent |
|---|---|---|
| PLATINUM SERVICES NY | 2 | 07/25/2026 |
| CITYSCAPE BUILDERS | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| ALWAYS FAST SERVICES CORP | 2 | 08/13/2026 |
| R & O ENGINEERING | 4 | 03/12/2026 |
| ASHER ARCHITECT | 3 | 02/26/2026 |
| EYAL LEVITT ARCHITECT PC | 1 | 11/21/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| AVALON DESIGN | 2 | 03/21/2026 |
| ERETZ BUILDERS ASSISTANCE. | 10 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CITYSCAPE BUILDERS LLC | General Contractor | 15 | 08/30/2026 |
| YOEL TAUBER | Electrical | 2 | 03/21/2026 |
| PLATINUM SERVICES NY LLC | General Contractor | 2 | 07/25/2026 |
| TARGET PIPING NY LLC | Fire Protection | 1 | 09/25/2026 |
| B&B MECH PLBG & HTG LLC | Plumbing | 1 | 08/30/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| BIG APPLE GROUP NY A RMA | 9168 | 2 | 03/12/2026 |
| BIG APPLE GROUP NY, LLC | 1258 | 5 | 02/26/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sprinklers | Permit Issued | TARGET PIPING NY LLC | 09/24/2026 |
| DOB NOW | Construction Fence | Permit Issued | CITYSCAPE BUILDERS LLC | 08/27/2026 |
| DOB NOW | Plumbing | Permit Issued | B&B MECH PLBG & HTG LLC | 08/27/2026 |
| DOB NOW | Supported Scaffold | Permit Issued | PLATINUM SERVICES NY LLC | 07/23/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | PLATINUM SERVICES NY LLC | 07/23/2026 |
| DOB NOW | Structural | Permit Issued | CITYSCAPE BUILDERS LLC | 06/29/2026 |
| DOB NOW | Foundation | Signed-off | CITYSCAPE BUILDERS LLC | 02/23/2026 |
| DOB NOW | Support of Excavation | Signed-off | CITYSCAPE BUILDERS LLC | 02/10/2026 |
| DOB NOW | General Construction | Permit Issued | CITYSCAPE BUILDERS LLC | 02/10/2026 |
| DOB NOW | Foundation | Permit Issued | CITYSCAPE BUILDERS LLC | 02/10/2026 |
| DOB NOW | Construction Fence | Permit Issued | CITYSCAPE BUILDERS LLC | 09/09/2025 |
| DOB NOW | Construction Fence | Permit Issued | CITYSCAPE BUILDERS LLC | 09/12/2024 |
| DOB NOW | Construction Fence | Permit Issued | CITYSCAPE BUILDERS LLC | 07/24/2019 |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/24/2026 | Certified StandPipe-SD-Fixtures-Finish-SD | Certified | View ↗ |
| 04/21/2026 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 03/30/2026 | Certified StandPipe - SD - Alarm Sys 64/09 - Finish | Certified | View ↗ |
| 03/30/2026 | Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet) | Certified | View ↗ |
| 09/25/2025 | Certified StandPipe - SD - Alarm Sys 64/09 - Finish | Certified | View ↗ |
| 09/25/2025 | Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet) | Certified | View ↗ |
| 03/12/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 09/23/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/01/2026 | Fenestration air leakage | SOORJBALLY HARILALL | energy_progress |
| 07/01/2026 | Interior lighting power | SOORJBALLY HARILALL | energy_progress |
| 07/01/2026 | Permanent certificate | SOORJBALLY HARILALL | energy_progress |
| 07/01/2026 | Air barrier — testing | SOORJBALLY HARILALL | energy_progress |
| 07/01/2026 | Air barrier - visual inspection | SOORJBALLY HARILALL | energy_progress |
| 07/01/2026 | Maintenance information | SOORJBALLY HARILALL | energy_progress |
| 07/01/2026 | Protection of exposed foundation insulation | SOORJBALLY HARILALL | energy_progress |
| 07/01/2026 | Insulation placement and R values | SOORJBALLY HARILALL | energy_progress |
| 07/01/2026 | Fenestration and door U-factor and product ratings | SOORJBALLY HARILALL | energy_progress |
| 07/01/2026 | Fire-Resistant Penetrations and Joints | SOORJBALLY HARILALL | special |
| 07/01/2026 | Energy Code Compliance Inspections | SOORJBALLY HARILALL | progress |
| 07/01/2026 | Fire-Resistance Rated Construction | SOORJBALLY HARILALL | progress |
| 07/01/2026 | Metering | SOORJBALLY HARILALL | energy_progress |
| 07/01/2026 | Fenestration areas | SOORJBALLY HARILALL | energy_progress |
| 12/26/2025 | Subsurface Investigations (Borings/Test Pits) | SOORJBALLY HARILALL | special |
| 12/26/2025 | Concrete - Cast-In-Place | SOORJBALLY HARILALL | special |
| 12/26/2025 | Construction Operations Influencing Adjacent Structures | SOORJBALLY HARILALL | special |
| 12/26/2025 | Excavations - Sheeting, Shoring, and Bracing | SOORJBALLY HARILALL | special |
| 12/26/2025 | Structural Steel - Details | SOORJBALLY HARILALL | special |
| 12/26/2025 | Structural Steel - Welding | SOORJBALLY HARILALL | special |
| 12/26/2025 | Subgrade Inspections | SOORJBALLY HARILALL | special |
| 12/26/2025 | Underpinning and alternate methods of support of buildings and adjacent property | SOORJBALLY HARILALL | special |
| 12/24/2025 | Excavations - Sheeting, Shoring, and Bracing | SOORJBALLY HARILALL | special |
| 12/24/2025 | Subsurface Investigations (Borings/Test Pits) | SOORJBALLY HARILALL | special |
| 12/23/2025 | Concrete - Cast-In-Place | SOORJBALLY HARILALL | special |