1969Year Built
2Stories
M1Building Class
R3AZoning
7,920 sfGross Floor Area
1Units
0 Active ViolationsFDNY Report ↗
Church, synagogue, chapel · Owner of record: Cod Education Complex II · 21,489 sf lot · 0.37 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionCivilGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofNew Jerusalem Baptist Church25p · 4 filings · 18 docs
BulkheadNew Jerusalem Baptist Church2p · 1 filing · 14 docs
Floor 2New Jerusalem Baptist Church39p · 4 filings · 18 docs
Floor 1New Jerusalem Baptist Church43p · 7 filings · 18 docs
CellarNew Jerusalem Baptist Church40p · 5 filings · 18 docs
Site & exteriorNew Jerusalem Baptist Church21p · 6 filings · 15 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
New Jerusalem Baptist Church5908/29/2026
NYC Department of Housing Preservation and Development103/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
06/07/2018$1.6M—Private party → COD EDUCATIONAL COMPLEX II, LLC$208/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Barry J. Bank, P.E., Consulting Engineering1103/25/2026
Allen Shinfeld, P.E305/04/2024
Tarek M. Zeid, PE207/01/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JMV Associates403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
DA Hai ConstructionGeneral Contractor3807/08/2026
DA Hai ConstructionScaffold1607/08/2026
Peter Plumbing AssociatesPlumbing407/08/2026
Neptune Signs & AwningsSign hanger207/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
S&S Concrete & Soil Testi1008803/25/2026
Building Lifecycle
All (113)Filed (16)Permit Issued (40)Signed Off (7)Violation (14)Inspection (10)Special Inspection (26)
06/05/2026
Signed off — Alteration
Installation of proposed mini-split Mechanical Systems and associated piping for school filed with associated General Construction application #440652553, which was filed as a new building.
Q01046333-I1
04/30/2026
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
03/26/2026
Special inspection requirement — Shutoff dampers
GLEN LANGER
03/26/2026
Special inspection requirement — Maintenance information
GLEN LANGER
03/26/2026
Special inspection requirement — HVAC-R and service water heating equipment
GLEN LANGER
03/26/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
GLEN LANGER
03/26/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
GLEN LANGER
03/26/2026
Special inspection requirement — Mechanical Systems
GLEN LANGER
03/26/2026
Special inspection requirement — Final
GLEN LANGER
03/26/2026
Special inspection requirement — Energy Code Compliance Inspections
GLEN LANGER
03/26/2026
Special inspection requirement — HVAC-R and service water heating system controls
GLEN LANGER
03/26/2026
Special inspection requirement — Duct leakage testing, insulation and design
GLEN LANGER
03/25/2026
Filed — Alteration
Installation of proposed mini-split Mechanical Systems and associated piping for school filed with associated General Construction application #440652553, which was filed as a new building.
Q01046333-P1
03/10/2026
Violation issued (FDNY_NOV, closed)
01/30/2026
Signed off — Alteration
Filed to propose 18' Curb Cut on Baisley Blvd for enlargement of Community Facility
Q01122925-I1
01/28/2026
Inspection — Pass-Final Curb Cut Non-Directive 14
Pass
View inspection ↗
01/20/2026
Signed off — Alteration
INSTALLATION OF PROPOSED PLUMBING FIXTURES AND PIPING FOR SCHOOL FILED WITH ASSOCIATED GENERAL CONSTRUCTION APPLICATION #440652553 FILED AS A NEW BUILDING.
Q00835784-I1
01/19/2026
Signed off — Alteration
Q00430938-I1
11/26/2025
Inspection — Fail-Final Curb Cut Non-Directive 14
Fail
View inspection ↗
11/10/2025
Violation issued (FDNY_ORDER, closed)
11/10/2025
Violation issued (FDNY_NOV, closed)
04/01/2025
Permit issued — Earth Work
Q00476684-I1-GC
02/21/2025
Permit issued — Curb Cut
Q01122925-I1-CC
01/14/2025
Signed off — Alteration
Filed to propose regular installation of sprinkler system in conjunction with Alteration Application #440652553.
Q00993409-I1
01/13/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY 8-FT TALL PLYWOOD CONSTRUCTION FENCE FOR PROPOSED DEMOLITION #421575398. CONSTRUCTION FENCE TO BE INSTALLED ON PUBLIC WALKWAY WITHIN 3-FT OF PROPERTY LINE
Q00129205-I1
01/10/2025
Inspection — Pass-Final Sign Permit Inspection
Pass
View inspection ↗
01/08/2025
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
10/29/2024
Filed — No Work
Q01058235-I1
10/21/2024
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
10/08/2024
Filed — Alteration
Filed to propose 18' Curb Cut on Baisley Blvd for enlargement of Community Facility
Q01122925-I1
10/01/2024
Permit issued — Sign
Q01014870-I1-SG
09/30/2024
Permit issued — Sign
Q01012892-I1-SG
09/18/2024
Permit issued — Structural
Q00476684-I1-GC
09/04/2024
Filed — Alteration
INSTALLATION OF PROPOSED PLUMBING FIXTURES AND PIPING FOR SCHOOL FILED WITH ASSOCIATED GENERAL CONSTRUCTION APPLICATION #440652553 FILED AS A NEW BUILDING.
Q00835784-P1
09/04/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
GLEN LANGER
09/04/2024
Special inspection requirement — Maintenance information
GLEN LANGER
09/04/2024
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
GLEN LANGER
09/04/2024
Special inspection requirement — Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities
GLEN LANGER
09/04/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
GLEN LANGER
09/04/2024
Special inspection requirement — Energy Code Compliance Inspections
GLEN LANGER
09/04/2024
Special inspection requirement — HVAC-R and service water heating equipment
GLEN LANGER
09/04/2024
Special inspection requirement — HVAC-R and service water heating system controls
GLEN LANGER
08/23/2024
Permit issued — Construction Fence
Q00430938-I1-FN
08/23/2024
Permit issued — Foundation
Q00476684-I1-ST
07/25/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
GLEN LANGER
07/25/2024
Special inspection requirement — Sprinkler Systems
GLEN LANGER
07/24/2024
Filed — Alteration
Filed to propose regular installation of sprinkler system in conjunction with Alteration Application #440652553.
Q00993409-P1
07/24/2024
Violation issued (FDNY_ORDER, closed)
07/10/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
06/13/2024
Permit issued — Mechanical Systems
Q01046333-I1-MS
06/06/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
GLEN LANGER
06/06/2024
Special inspection requirement — Sprinkler Systems
GLEN LANGER
05/08/2024
Filed — Alteration
Installation of proposed mini-split Mechanical Systems and associated piping for school filed with associated General Construction application #440652553, which was filed as a new building.
Q01046333-I1
05/04/2024
Filed — Alteration
INSTALLATION OF AN ILLUMINATED BUSINESS ACCESSORY SIGN . NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Q01012892-P1
03/14/2024
Filed — Alteration
INSTALLATION OF AN ILLUMINATED BUSINESS ACCESSORY SIGN . NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Q01014870-I1
03/14/2024
Filed — Alteration
INSTALLATION OF AN ILLUMINATED BUSINESS ACCESSORY SIGN . NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Q01012892-I1
03/06/2024
Permit issued — Plumbing
Q00835784-I1-PL
02/13/2024
Permit issued — General Construction
Q00476684-I1-GC
01/30/2024
Inspection — Certified Storm Drainage-ST-Piping-Roughing
Certified
View inspection ↗
01/30/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
Latest 60 of 113 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWEarth WorkPermit IssuedDA Hai Construction04/01/2025
DOB NOWCurb CutSigned-offDA Hai Construction02/21/2025
DOB NOWSignSigned-offNeptune Signs & Awnings10/01/2024
DOB NOWSignSigned-offNeptune Signs & Awnings09/30/2024
DOB NOWStructuralPermit IssuedDA Hai Construction09/18/2024
DOB NOWConstruction FenceSigned-offDA Hai Construction08/23/2024
DOB NOWFoundationPermit IssuedDA Hai Construction08/23/2024
DOB NOWMechanical SystemsSigned-offDA Hai Construction06/13/2024
DOB NOWPlumbingSigned-offPeter Plumbing Associates03/06/2024
DOB NOWGeneral ConstructionPermit IssuedDA Hai Construction02/13/2024
DOB NOWSprinklersSigned-offPeter Plumbing Associates01/25/2024
DOB NOWFoundationPermit IssuedDA Hai Construction09/01/2023
DOB NOWEarth WorkPermit IssuedDA Hai Construction08/31/2023
DOB NOWConstruction FenceSigned-offDA Hai Construction08/31/2023
DOB NOWFoundationPermit IssuedDA Hai Construction06/21/2023
DOB NOWConstruction FenceSigned-offDA Hai Construction06/16/2023
DOB NOWGeneral ConstructionPermit IssuedDA Hai Construction06/15/2023
DOB NOWConstruction FenceSigned-offDA Hai Construction06/15/2023
DOB NOWPlumbingSigned-offPeter Plumbing Associates03/06/2023
DOB NOWEarth WorkPermit IssuedDA Hai Construction09/02/2022
DOB NOWStructuralPermit IssuedDA Hai Construction09/01/2022
DOB NOWConstruction FenceSigned-offDA Hai Construction09/01/2022
DOB NOWStructuralPermit IssuedDA Hai Construction05/26/2022
DOB NOWStructuralPermit IssuedDA Hai Construction05/26/2022
DOB NOWGeneral ConstructionPermit IssuedDA Hai Construction05/24/2022
DOB NOWEarth WorkPermit IssuedDA Hai Construction05/23/2022
DOB NOWConstruction FenceSigned-offDA Hai Construction05/20/2022
DOB NOWGeneral ConstructionPermit IssuedDA Hai Construction02/22/2022
DOB NOWGeneral ConstructionPermit IssuedDA Hai Construction02/22/2022
DOB NOWEarth WorkPermit IssuedDA Hai Construction02/22/2022
DOB NOWStructuralPermit IssuedDA Hai Construction02/16/2022
DOB NOWConstruction FenceSigned-offDA Hai Construction01/12/2022
DOB NOWConstruction FenceSigned-offDA Hai Construction02/04/2021
DOB NOWConstruction FenceSigned-offDA Hai Construction11/25/2020
DOB NOWConstruction FenceSigned-offDA Hai Construction07/14/2020
DOB NOWConstruction FenceSigned-offDA Hai Construction06/24/2020
DOB NOWPlumbingSigned-offPeter Plumbing Associates12/14/2019
DOB NOWConstruction FenceSigned-offDA Hai Construction09/24/2019
DOB NOWConstruction FenceSigned-offDA Hai Construction06/18/2019
DOB NOWConstruction FenceSigned-offDA Hai Construction02/19/2019
+ 9 more permits on file
1 project · most recent 03/25/2026
Heating and Air Conditioning Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
03/25/2026Signed-offDA Hai ConstructionHeating and Air Conditioning Systems, Ventilation Systems
Heat / Cool
Mitsubishi Electric MITSUBISHI ELECTRIC MXZ-SM36NAMHZ 36,000 BTU · Heat Pump Outdoor ×24
MITSUBISHI ELECTRIC MXZ-3C30NAHZ3 30,000 BTU · Heat Pump Outdoor ×14
Mitsubishi Electric MXZ-SM36NAMHZ 36,000 BTU · Heat Pump Outdoor ×6
Electrolux Electrolux FFRA062WAE 6,000 BTU · Ptac ×2
Ventilation
Mitsubishi Electric LGH-F1200RVX2-E 12,000 CFM · Erv ×2
8 projects · most recent 09/17/2026
General Wiring
FiledStatusContractorScope
09/17/2026CompleteChampion ElectricGeneral Wiring
08/26/2024CompleteChampion ElectricGeneral Wiring
08/26/2024CompleteChampion Electric2 meters, 1 new_meters
03/06/2024CompleteJong Hyun Kim—
03/06/2024CompleteJong Hyun Kim—
08/15/2022CompleteJam Electrical—
04/10/2022CompleteChampion Electric1 meters, 1 new_meters
06/18/2020CompleteChampion ElectricGeneral Wiring
1 project · most recent 07/01/2022
Steel Concrete
FiledStatusContractorScope
07/01/2022Permit IssuedDA Hai ConstructionSteel, Concrete
1 project · most recent 07/01/2022
Earthwork
FiledStatusContractorScope
07/01/2022Permit IssuedDA Hai ConstructionEarthwork
▾Field Inspections (DOB CAP) — 10
DateTypeResultReport
04/30/2026Pass-Final General Construction Non-Directive 14PassView ↗
01/28/2026Pass-Final Curb Cut Non-Directive 14PassView ↗
11/26/2025Fail-Final Curb Cut Non-Directive 14FailView ↗
01/10/2025Pass-Final Sign Permit InspectionPassView ↗
01/08/2025Fail-Final General Construction Non-Directive 14FailView ↗
10/21/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
07/10/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
01/30/2024Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
01/30/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/30/2024Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 26
DateRequirementInspectorRole
03/26/2026Shutoff dampersGLEN LANGERenergy_progress
03/26/2026Maintenance informationGLEN LANGERenergy_progress
03/26/2026HVAC-R and service water heating equipmentGLEN LANGERenergy_progress
03/26/2026HVAC-R and service water piping design and insulationGLEN LANGERenergy_progress
03/26/2026Fire-Resistant Penetrations and JointsGLEN LANGERspecial
03/26/2026Mechanical SystemsGLEN LANGERspecial
03/26/2026FinalGLEN LANGERprogress
03/26/2026Energy Code Compliance InspectionsGLEN LANGERprogress
03/26/2026HVAC-R and service water heating system controlsGLEN LANGERenergy_progress
03/26/2026Duct leakage testing, insulation and designGLEN LANGERenergy_progress
09/04/2024HVAC-R and service water piping design and insulationGLEN LANGERenergy_progress
09/04/2024Maintenance informationGLEN LANGERenergy_progress
09/04/2024Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationGLEN LANGERspecial
09/04/2024Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention FacilitiesGLEN LANGERspecial
09/04/2024Fire-Resistant Penetrations and JointsGLEN LANGERspecial
09/04/2024Energy Code Compliance InspectionsGLEN LANGERprogress
09/04/2024HVAC-R and service water heating equipmentGLEN LANGERenergy_progress
09/04/2024HVAC-R and service water heating system controlsGLEN LANGERenergy_progress
07/25/2024Fire-Resistant Penetrations and JointsGLEN LANGERspecial
07/25/2024Sprinkler SystemsGLEN LANGERspecial
06/06/2024Fire-Resistant Penetrations and JointsGLEN LANGERspecial
06/06/2024Sprinkler SystemsGLEN LANGERspecial
06/21/2022FinalGLEN LANGERprogress
06/21/2022Structural Steel - DetailsGLEN LANGERspecial
06/21/2022Structural Stability – Alterations of existing buildingsGLEN LANGERspecial
Latest 25 of 26.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
New Jerusalem Baptist ChurchReligiousCellar, Floors 1, 2, Roof
Project Q01122925 Alteration · LOC Issued · 10/08/2024
Project Q01012892 Alteration · Permit Entire · 03/14/2024
Project Q01014870 Alteration · Permit Entire · 03/14/2024
Project Q00993409 Alteration · LOC Issued · 01/22/2024
Project Q00835784 Alteration · LOC Issued · 03/03/2023
Project Q00476684 Alteration · Permit Entire · 07/06/2021
Project Q00430938 Alteration · LOC Issued · 11/19/2020
Project Q00248212 Alteration · LOC Issued · 10/18/2019
Project Q00129205 Alteration · LOC Issued · 02/19/2019
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 210 on file (BIS + DOB NOW)
▸Plans & Drawings22
▸DOB NOWPlans/Sketch10
08/25/2026Q00835784-P1Request digital key ↗
08/25/2026Q00835784-I1Request digital key ↗
08/23/2026Q01014870-I1Request digital key ↗
Showing 3 of 10 on file for this type
▸DOB NOWPlans/Sketch - Structural2
08/26/2026Q00476684-I1Request digital key ↗
08/26/2026Q00476684-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Construction Fence2
08/28/2026Q00129205-I1Request digital key ↗
08/27/2026Q00430938-I1Request digital key ↗
▸DOB NOWPlans/Sketch - General Construction2
08/26/2026Q00476684-I1Request digital key ↗
08/26/2026Q00476684-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Foundation2
08/26/2026Q00476684-I1Request digital key ↗
08/26/2026Q00476684-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Earthwork2
08/26/2026Q00476684-I1Request digital key ↗
08/26/2026Q00476684-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing1
08/28/2026Q00248212-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Place of Assembly1
08/21/2026Q01058235-I1Request digital key ↗
▸Applications & Permits22
▸BISPLAN / WORK APPROVAL APPLICATION14
08/26/2025440819063Open ↗
06/24/2025440652553Open ↗
05/28/2025440652553Open ↗
Showing 3 of 14 on file for this type
▸BISWORK PERMIT APPLICATION6
06/13/2024440652553Open ↗
07/16/2019421719858Open ↗
03/01/2019421719858Open ↗
Showing 3 of 6 on file for this type
▸BISIntent to Revoke Approval/Permit1
11/15/2013420534201Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation1
08/30/2024440819063Open ↗
▸Zoning, Tax Lot & Property Records6
▸BISTAX LOT: TENTATIVE LOT NUMBER ISSUED1
01/19/2021440652553Open ↗
▸BISTAX LOT: FINAL LOT NUMBER ISSUED1
03/01/2019421719858Open ↗
▸BISVERIFY TAX LOT1
01/13/2025440652553Open ↗
▸BISADDRESS: NEW HOUSE NUMBER APPROVED1
01/19/2021440652553Open ↗
▸BISCO OBJ: VERIFY ADDRESS-TOPO STAMP1
01/13/2025440652553Open ↗
▸BISZONING DIAGRAM1
06/05/2024440652553Open ↗
▸Seals & Professional Certifications42
▸DOB NOWDPL-1: Design Professional Seal & Signature16
08/27/2026Q00430938-I1Open ↗
08/26/2026Q00476684-I1Open ↗
08/26/2026Q00476684-P1Open ↗
Showing 3 of 16 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature5
09/21/2026Q00993409-P1Open ↗
09/18/2026Q00835784-I1Open ↗
08/24/2026Q00476684-P1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWProgress Inspector Seal & Signature5
09/18/2026Q00835784-I1Open ↗
09/18/2026Q00835784-I1Open ↗
08/24/2026Q00476684-P1Open ↗
Showing 3 of 5 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST4
07/23/2020421719858Open ↗
03/01/2019421719858Open ↗
11/02/2015421178772Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY3
08/16/2024440819063Open ↗
01/19/2021440652553Open ↗
07/12/2016440319111Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT3
03/01/2019421719858Open ↗
07/12/2016440319111Open ↗
11/02/2015421178772Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION3
03/01/2019421719858Open ↗
02/23/2012420534201Open ↗
02/21/2012420534201Open ↗
▸BISAPPLICANT OWNER SIGNATURE2
08/16/2024440819063Open ↗
01/19/2021440652553Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
02/21/2012420534201Open ↗
▸Trade Schedules & Equipment8
▸BISDEP SANITARY SEWER CERTIFICATION (HCP/SCP)2
01/13/2025440652553Open ↗
05/30/2024440652553Open ↗
▸BISEQUIPMENT USE APPLICATION/PERMIT2
02/23/2012420534201Open ↗
02/21/2012420534201Open ↗
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)2
08/13/2026Q00476684-P1Open ↗
08/13/2026Q00476684-I1Open ↗
▸BISHVAC & SERVICE WATER HEATING SYSTEM CONTROLS1
01/10/2025440652553Open ↗
▸BISDEP STORMWATER SEWER CERTIFICATION (HCP/SCP)1
05/30/2024440652553Open ↗
▸Safety & Tenant Protection6
▸BISSTREET TREE CHECKLIST4
06/04/2025440652553Open ↗
08/16/2024440819063Open ↗
01/19/2021440652553Open ↗
Showing 3 of 4 on file for this type
▸BISSTREET TREES: RECEIPT OF STREET TREES SITE PLAN1
08/29/2024440819063Open ↗
▸BISSTREET TREES: RECEIPT OF STREET TREES S1
06/04/2025440652553Open ↗
▸Environmental & Asbestos8
▸DOB NOWDEP ACP-5: Asbestos Assessment Report5
08/26/2026Q00476684-I1Open ↗
08/26/2026Q00476684-P1Open ↗
08/21/2026Q00993409-P1Open ↗
Showing 3 of 5 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)3
01/19/2021440652553Open ↗
03/01/2019421719858Open ↗
07/12/2016440319111Open ↗
▸Energy Compliance21
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
07/13/2020421719858Open ↗
07/12/2016440319111Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS2
01/19/2021440652553Open ↗
07/12/2016440319111Open ↗
▸BISTECHNICAL REPORT: ENERGY2
02/23/2012420534201Open ↗
02/21/2012420534201Open ↗
▸DOB NOWPreliminary Commissioning Report Certification2
08/17/2026Q01046333-I1Open ↗
08/13/2026Q01046333-I1Open ↗
▸BISFENESTRATION U-FACTOR & PRODUCT RATING1
01/10/2025440652553Open ↗
▸BISFENESTRATION AREAS1
01/10/2025440652553Open ↗
▸BISAIR SEALING AND INSULATION - TESTING1
01/10/2025440652553Open ↗
▸BISINSULATION PLACEMENT & R VALUES1
01/10/2025440652553Open ↗
▸BISENERGY CODE COMPLIANCE INSPECTIONS1
01/10/2025440652553Open ↗
▸BISELECTRIC MOTORS1
01/10/2025440652553Open ↗
▸BISLIGHTING CONTROLS1
01/10/2025440652553Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
03/01/2019421719858Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
07/13/2020421719858Open ↗
▸BISELECTRICAL ENERGY CONSUMPTION1
01/10/2025440652553Open ↗
▸BISPRELIMINARY COMMISSIONING REPORT CERTIFICATION1
12/17/2025440652553Open ↗
▸BIS_ENERGY PLANS REVIEW AND APPROVAL1
06/04/2025440652553Open ↗
▸BISEXTERIOR LIGHTING POWER1
01/10/2025440652553Open ↗
▸Inspections & Test Reports3
▸BISTECHNICAL REPORT: RESPONSIBILITY2
07/13/2020421719858Open ↗
07/12/2016440319111Open ↗
▸BISFIRE-RESISTIVE RATED CONSTRUCTION1
01/10/2025440652553Open ↗
▸Approvals, Objections & Sign-offs18
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter11
08/21/2026Q00993409-P1Open ↗
08/21/2026Q00993409-I1Open ↗
08/13/2026Q01046333-P1Open ↗
Showing 3 of 11 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE3
06/24/2025440652553Open ↗
05/28/2025440652553Open ↗
01/19/2021440652553Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST2
07/30/2020421719858Open ↗
02/23/2012420534201Open ↗
▸BISADMINISTRATIVE OBJECTIONS2
11/02/2015421178772Open ↗
02/21/2012420534201Open ↗
▸Cost, Insurance & Ownership8
▸BISCOST AFFIDAVIT4
03/01/2019421719858Open ↗
07/12/2016440319111Open ↗
02/23/2012420534201Open ↗
Showing 3 of 4 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW32
01/16/2025440652553Open ↗
07/13/2020421719858Open ↗
▸DOB NOWCertification by Insurance Broker or Agency1
08/13/2026Q00476684-I1Open ↗
▸DOB NOWCertificate of Insurance1
08/13/2026Q00476684-I1Open ↗
▸Filing & Intake Forms13
▸BISADDITIONAL INFORMATION7
11/14/2025440819063Open ↗
07/02/2025440652553Open ↗
01/15/2025440652553Open ↗
Showing 3 of 7 on file for this type
▸BISEFILING COVER SHEET3
03/01/2019421719858Open ↗
11/02/2015421178772Open ↗
02/21/2012420534201Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET3
08/16/2024440819063Open ↗
01/19/2021440652553Open ↗
07/12/2016440319111Open ↗
▸Other Documents17
▸BISSupporting Document: Fee Exempt2
08/16/2024440819063Open ↗
01/19/2021440652553Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/13/2026Q00476684-I1Open ↗
08/13/2026Q00476684-P1Open ↗
▸DOB NOWPlot Diagram2
08/13/2026Q00476684-P1Open ↗
08/13/2026Q00476684-I1Open ↗
▸BISMAINTENANCE INFORMATION1
01/10/2025440652553Open ↗
▸BISRECORDS MGMT FEE PAYMENT RECEIPT1
08/30/2024440819063Open ↗
▸BISHVAC & SERVICE WATER PIPING DESIGN AND INSULATION1
01/10/2025440652553Open ↗
▸BISDUCT DESIGN, INSULATION AND LEAKAGE TESTING1
01/10/2025440652553Open ↗
▸BISPROTECTION OF EXPOSED FOUNDATION INSULATION1
01/10/2025440652553Open ↗
▸BISBPP - SUPPORTING DOCUMENTATION1
08/16/2024440819063Open ↗
▸BISPLOT DIAGRAM1
01/19/2021440652553Open ↗
▸BISAIR BARRIER CONTINUITY PLAN1
01/10/2025440652553Open ↗
▸DOB NOWSite Survey: Initial1
08/13/2026Q00476684-P1Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026Q00476684-I1Open ↗
▸DOB NOWAdditional Insured Authorizations1
08/13/2026Q00476684-I1Open ↗