| Owner | Filings | Most Recent |
|---|---|---|
| Rodeph Sholom School | 34 | 03/21/2026 |
| KNP Consulting | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Silman | 2 | 04/29/2025 |
| Landmark Facilities Group | 3 | 09/18/2024 |
| Murphy Burnham & Buttrick Architects | 1 | 05/04/2023 |
| Paul Perdek, Prof. Engineering | 2 | 05/28/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| Murphy Burnham & Buttrick Architects | 6 | 03/21/2026 |
| William Vitacco Associates | 4 | 03/21/2026 |
| AE Design Solution | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Everest Scaffolding | Scaffold | 9 | 07/08/2026 |
| Eurostruct | General Contractor | 6 | 07/08/2026 |
| Nationwide Mechanical | Fire Protection | 2 | 07/08/2026 |
| Big Shot Electric | Electrical | 1 | 03/22/2026 |
| Nationwide Mechanical | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| AK Engineering | 678 | 6 | 04/29/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | Eurostruct | 09/03/2024 |
| DOB NOW | Sprinklers | Signed-off | Nationwide Mechanical | 03/26/2024 |
| DOB NOW | Mechanical Systems | Signed-off | Eurostruct | 09/14/2023 |
| DOB NOW | Sprinklers | Signed-off | Nationwide Mechanical | 08/03/2023 |
| DOB NOW | Plumbing | Signed-off | Nationwide Mechanical | 08/03/2023 |
| DOB NOW | General Construction | Permit Issued | Eurostruct | 07/19/2023 |
| DOB NOW | Foundation | Signed-off | Eurostruct | 07/14/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | Everest Scaffolding | 06/25/2021 |
| DOB NOW | Supported Scaffold | Signed-off | Everest Scaffolding | 06/30/2020 |
| DOB NOW | Sidewalk Shed | Signed-off | Everest Scaffolding | 06/30/2020 |
| DOB NOW | Supported Scaffold | Signed-off | Everest Scaffolding | 05/29/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | Everest Scaffolding | 05/22/2019 |
| BIS | PL | ISSUED | WTC Plumbing & Heating | 07/31/2017 |
| BIS | PL | ISSUED | WTC Plumbing & Heating | 06/23/2017 |
| BIS | — | RE-ISSUED | Eurostruct | 06/20/2017 |
| BIS | EQ | ISSUED | Everest Scaffolding | 05/12/2017 |
| BIS | EQ | ISSUED | Everest Scaffolding | 05/11/2017 |
| BIS | OT | ISSUED | Eurostruct | 03/28/2017 |
| BIS | OT | ISSUED | Eurostruct | 03/28/2017 |
| BIS | PL | ISSUED | Champ Plumbing & Heating | 03/16/2017 |
| BIS | OT | ISSUED | Eurostruct | 02/17/2017 |
| BIS | MH | ISSUED | Champion Combustion | 02/17/2017 |
| BIS | OT | ISSUED | Eurostruct | 02/17/2017 |
| BIS | OT | ISSUED | Eurostruct | 11/29/2016 |
| BIS | OT | ISSUED | Eurostruct | 09/29/2016 |
| BIS | EQ | ISSUED | Everest Scaffolding | 10/14/2015 |
| BIS | EQ | ISSUED | Everest Scaffolding | 10/14/2015 |
| BIS | SP | ISSUED | Capitol Fire SPKL Co | 09/19/2013 |
| BIS | OT | ISSUED | Bulado General Contractor | 07/25/2013 |
| BIS | PL | ISSUED | J. Caiazzo Plumbing & Heating | 04/10/2012 |
| BIS | SP | ISSUED | Pilato Brothers & P&H Co | 12/29/2011 |
| BIS | OT | ISSUED | South East Construction G | 12/23/2011 |
| BIS | PL | ISSUED | J. Caiazzo Plumbing & Heating | 04/15/2011 |
| BIS | PL | ISSUED | Pilato Brothers Plumbing & Heating Co | 09/30/2010 |
| BIS | OT | ISSUED | Southeast Construction | 06/29/2009 |
| BIS | MH | ISSUED | Southeast Construction | 06/29/2009 |
| BIS | SP | ISSUED | WTC Plumbing & Heating | 06/17/2009 |
| BIS | PL | ISSUED | WTC Plumbing & Heating | 05/29/2009 |
| BIS | — | ISSUED | Eurostruct | 01/20/2009 |
| BIS | MH | ISSUED | South East Construction | 08/06/2008 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 04/29/2025 | Signed-off | Eurostruct | Air Conditioning Systems, Heating and Air Conditioning Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/29/2025 | Signed-off | Nationwide Mechanical | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/29/2025 | Signed-off | Nationwide Mechanical | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/30/2025 | Permit Issued | Nee Electrical | — |
| 12/08/2023 | Complete | Big Shot Electric | General Wiring |
| 05/21/2019 | Complete | Borowide Elect'l Contractors | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/29/2025 | Signed-off | Eurostruct | Steel, Concrete |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/18/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 11/29/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 11/29/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/23/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/28/2025 | Footing and Foundation | Ari Kamo | progress |
| 05/28/2025 | Final | Ari Kamo | progress |
| 05/28/2025 | Post-installed Anchors | Ari Kamo | special |
| 05/28/2025 | Structural Stability – Alterations of existing buildings | Ari Kamo | special |
| 05/28/2025 | Concrete - Cast-In-Place | Ari Kamo | special |
| 05/28/2025 | Structural Steel - High Strength Bolting | Ari Kamo | special |
| 05/28/2025 | Subsurface Conditions – Fill Placement & In-Place Density | Ari Kamo | special |
| 05/28/2025 | Structural Steel - Details | Ari Kamo | special |
| 05/28/2025 | Structural Steel - Welding | Ari Kamo | special |
| 04/22/2025 | Concrete - Cast-In-Place | Ari Kamo | special |
| 04/22/2025 | Post-installed Anchors | Ari Kamo | special |
| 04/22/2025 | Structural Stability – Alterations of existing buildings | Ari Kamo | special |
| 04/22/2025 | Structural Steel - Details | Ari Kamo | special |
| 04/22/2025 | Structural Steel - High Strength Bolting | Ari Kamo | special |
| 04/22/2025 | Structural Steel - Welding | Ari Kamo | special |
| 04/22/2025 | Subsurface Conditions – Fill Placement & In-Place Density | Ari Kamo | special |
| 04/22/2025 | Final | Ari Kamo | progress |
| 04/22/2025 | Footing and Foundation | Ari Kamo | progress |
| 09/25/2024 | Mechanical Systems | Ari Kamo | special |
| 09/25/2024 | Final | Ari Kamo | progress |
| 09/25/2024 | Heating Systems | Ari Kamo | special |
| 07/12/2024 | Mechanical Systems | Ari Kamo | special |
| 07/12/2024 | Heating Systems | Ari Kamo | special |
| 07/12/2024 | Final | Ari Kamo | progress |
| 05/03/2023 | Fire-Resistant Penetrations and Joints | Ari Kamo | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Rodeph Sholom School | Education | Cellar, Sub-basement, Floors 1, 2 | Project M00863627 |