| Owner | Filings | Most Recent |
|---|---|---|
| PHOENIX BRIDGING INC DBA PHOENIX | 2 | 03/21/2026 |
| 166 COLUMB | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| CES ENGINEERING LLC | 4 | 12/05/2025 |
| MCBRIDE AND ASSOCIATES ARCHITECTS | 3 | 10/29/2025 |
| SILMAN | 2 | 09/08/2025 |
| Rekstur Architecture | 4 | 12/26/2023 |
| MSP ENGINEERING INC. P.C. | 1 | 05/18/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| J CALLAHAN CONSULTING | 18 | 03/21/2026 |
| JAM CONSULTANTS, INC. | 10 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CREO PROJECTS LLC | General Contractor | 11 | 07/01/2026 |
| E S G C CORP | General Contractor | 3 | 07/08/2026 |
| G. & S. PLUMBING & HTG CO | Plumbing | 1 | 07/08/2026 |
| PROCORE MECHANICAL CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| MILROSE CONSULTANTS LLC | 2003 | 9 | 12/05/2025 |
| ACE STRUCTURAL ENGINEERIN | 496 | 4 | 12/26/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | CREO PROJECTS LLC | 06/29/2026 |
| DOB NOW | Structural | Signed-off | CREO PROJECTS LLC | 06/29/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | CREO PROJECTS LLC | 06/29/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | CREO PROJECTS LLC | 03/27/2026 |
| DOB NOW | General Construction | Signed-off | CREO PROJECTS LLC | 03/26/2026 |
| DOB NOW | Structural | Signed-off | CREO PROJECTS LLC | 03/26/2026 |
| DOB NOW | Plumbing | Permit Issued | PROCORE MECHANICAL CORP | 08/13/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | CREO PROJECTS LLC | 08/11/2025 |
| DOB NOW | General Construction | Signed-off | CREO PROJECTS LLC | 08/11/2025 |
| DOB NOW | Structural | Signed-off | CREO PROJECTS LLC | 08/11/2025 |
| DOB NOW | Structural | Signed-off | REYES II CONSTRUCTION CP | 07/10/2023 |
| DOB NOW | Plumbing | Signed-off | G. & S. PLUMBING & HTG CO | 06/28/2023 |
| DOB NOW | General Construction | Signed-off | REYES II CONSTRUCTION CP | 06/27/2023 |
| BIS | EQ | ISSUED | PHOENIX BRIDGING INC | 08/15/2011 |
| BIS | EQ | ISSUED | PHOENIX BRIDGING INC | 08/15/2011 |
| BIS | MH | ISSUED | AIRCON INTERNATIONAL CORP | 08/29/2000 |
| BIS | — | ISSUED | DINEEN CONSTRUCTION CORP | 10/20/1997 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 12/05/2025 | Permit Issued | CREO PROJECTS LLC | Heating and Air Conditioning Systems, Ventilation Systems | Heat / Cool Mitsubishi Electric MXZ-SM36NAMHZ2-U1 36,000 BTU · Vrf Outdoor ×4 SUZ-KA18NAHZ 21,212 BTU · Vrf Outdoor ×2 Ventilation Fantech DBF4XLT 150 CFM · Exhaust Fan ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/05/2025 | Permit Issued | PROCORE MECHANICAL CORP | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/15/2025 | Permit Issued | POWER SURGE ELECTRIC, INC | General Wiring |
| 08/03/2023 | Complete | VALLEY ELECTRIC OF NY INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/08/2025 | Signed-off | CREO PROJECTS LLC | Steel, Wood |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/13/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 02/17/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/31/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/28/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 11/03/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/03/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/01/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/25/2025 | Final | Christopher Drutjons | progress |
| 11/25/2025 | Fire-Resistance Rated Construction | Christopher Drutjons | progress |
| 11/25/2025 | Fire-Resistant Penetrations and Joints | Christopher Drutjons | special |
| 11/25/2025 | Structural Stability – Alterations of existing buildings | Christopher Drutjons | special |
| 11/14/2025 | Structural Steel - Details | Christopher Drutjons | special |
| 11/14/2025 | Structural Steel - Welding | Christopher Drutjons | special |
| 11/14/2025 | Wood – Seismic Resistance | Christopher Drutjons | special |
| 11/14/2025 | Post-installed Anchors | Christopher Drutjons | special |
| 11/14/2025 | Structural Wood Frame | Christopher Drutjons | progress |
| 11/14/2025 | Final | Christopher Drutjons | progress |
| 11/14/2025 | Structural Stability – Alterations of existing buildings | Christopher Drutjons | special |
| 11/12/2025 | Wood – Seismic Resistance | Christopher Drutjons | special |
| 11/03/2025 | Fire-Resistant Penetrations and Joints | Christopher Drutjons | special |
| 11/03/2025 | Fire-Resistant Penetrations and Joints | Christopher Drutjons | special |
| 11/03/2025 | Mechanical Systems | Christopher Drutjons | special |
| 11/03/2025 | Final | Christopher Drutjons | progress |
| 10/27/2025 | Fire-Resistant Penetrations and Joints | Christopher Drutjons | special |
| 10/27/2025 | Structural Stability – Alterations of existing buildings | Christopher Drutjons | special |
| 10/27/2025 | Final | Christopher Drutjons | progress |
| 10/27/2025 | Fire-Resistance Rated Construction | Christopher Drutjons | progress |
| 08/20/2025 | Final | Christopher Drutjons | progress |
| 08/20/2025 | Structural Wood Frame | Christopher Drutjons | progress |
| 08/20/2025 | Fire-Resistance Rated Construction | Christopher Drutjons | progress |
| 08/20/2025 | Final | Christopher Drutjons | progress |
| 08/20/2025 | Structural Stability – Alterations of existing buildings | Christopher Drutjons | special |