RoofUnder Construction25p · 2 filings · 20 docs
ArchitectureDMMechanicalStructural
Issued Permit Scope
General Construction
CONVERT EXISTING 2 FAMILIES TO 8 FAMILIES USE, HORIZONTAL AND VERTICAL ENLARGEMENT AT CELLAR, 1ST THRU 4TH FLOOR, MEZZANINE AND PENTHOUSE, OBTAIN NEW CERTIFICATE OF OCCUPANCY.
On file for this project
87 documents · 4 drawing sheets
MECHANICAL WORK IN CONJUNCTION WITH GC JOB #B00688825.
On file for this project
11 documents · 2 drawing sheets
Bulkhead2p · 1 filing · 20 docs
Structural
PROPOSED SOE AND STRUCTURAL WORK , IN CONJUNCTION WITH CO JOB#B00688825-I1.
On file for this project
25 documents · 2 drawing sheets
PenthouseUnder Construction21p · 3 filings · 20 docs
ArchitectureFire ProtectionPlumbing
Issued Permit Scope
General Construction
CONVERT EXISTING 2 FAMILIES TO 8 FAMILIES USE, HORIZONTAL AND VERTICAL ENLARGEMENT AT CELLAR, 1ST THRU 4TH FLOOR, MEZZANINE AND PENTHOUSE, OBTAIN NEW CERTIFICATE OF OCCUPANCY.
On file for this project
87 documents
SUBMIT SPRINKLER WORK ON CELLAR, 1ST TO 4TH FLOOR, 3RD FLOOR MEZZANINE, PENTHOUSE AND OSP, IN CONJUNCTION WITH ALT1 #B00688825, NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
7 documents · 1 drawing sheet
SUBMIT PLUMBING WORK ON CELLAR, 1ST~4TH FLOOR, 3RD FL. MEZZANINE, PENTHOUSE AND OPEN SPACE, IN CONJUNCTION WITH ALT1 APPLICATION #B00688825, NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
19 documents · 1 drawing sheet
Floor 4Under Construction25p · 4 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction
CONVERT EXISTING 2 FAMILIES TO 8 FAMILIES USE, HORIZONTAL AND VERTICAL ENLARGEMENT AT CELLAR, 1ST THRU 4TH FLOOR, MEZZANINE AND PENTHOUSE, OBTAIN NEW CERTIFICATE OF OCCUPANCY.
On file for this project
87 documents
SUBMIT SPRINKLER WORK ON CELLAR, 1ST TO 4TH FLOOR, 3RD FLOOR MEZZANINE, PENTHOUSE AND OSP, IN CONJUNCTION WITH ALT1 #B00688825, NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
7 documents · 1 drawing sheet
SUBMIT PLUMBING WORK ON CELLAR, 1ST~4TH FLOOR, 3RD FL. MEZZANINE, PENTHOUSE AND OPEN SPACE, IN CONJUNCTION WITH ALT1 APPLICATION #B00688825, NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
19 documents · 3 drawing sheets
Latest 3 of 4 filings on this floor.
Floor 3Under Construction27p · 4 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction
CONVERT EXISTING 2 FAMILIES TO 8 FAMILIES USE, HORIZONTAL AND VERTICAL ENLARGEMENT AT CELLAR, 1ST THRU 4TH FLOOR, MEZZANINE AND PENTHOUSE, OBTAIN NEW CERTIFICATE OF OCCUPANCY.
On file for this project
87 documents · 3 drawing sheets
SUBMIT SPRINKLER WORK ON CELLAR, 1ST TO 4TH FLOOR, 3RD FLOOR MEZZANINE, PENTHOUSE AND OSP, IN CONJUNCTION WITH ALT1 #B00688825, NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
7 documents · 2 drawing sheets
SUBMIT PLUMBING WORK ON CELLAR, 1ST~4TH FLOOR, 3RD FL. MEZZANINE, PENTHOUSE AND OPEN SPACE, IN CONJUNCTION WITH ALT1 APPLICATION #B00688825, NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
19 documents · 2 drawing sheets
Latest 3 of 4 filings on this floor.
Floor 2Under Construction19p · 1 filing · 20 docs
Architecture
Issued Permit Scope
General Construction
CONVERT EXISTING 2 FAMILIES TO 8 FAMILIES USE, HORIZONTAL AND VERTICAL ENLARGEMENT AT CELLAR, 1ST THRU 4TH FLOOR, MEZZANINE AND PENTHOUSE, OBTAIN NEW CERTIFICATE OF OCCUPANCY.
On file for this project
87 documents
Floor 1Under Construction23p · 4 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction
CONVERT EXISTING 2 FAMILIES TO 8 FAMILIES USE, HORIZONTAL AND VERTICAL ENLARGEMENT AT CELLAR, 1ST THRU 4TH FLOOR, MEZZANINE AND PENTHOUSE, OBTAIN NEW CERTIFICATE OF OCCUPANCY.
On file for this project
87 documents
SUBMIT SPRINKLER WORK ON CELLAR, 1ST TO 4TH FLOOR, 3RD FLOOR MEZZANINE, PENTHOUSE AND OSP, IN CONJUNCTION WITH ALT1 #B00688825, NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
7 documents · 1 drawing sheet
SUBMIT PLUMBING WORK ON CELLAR, 1ST~4TH FLOOR, 3RD FL. MEZZANINE, PENTHOUSE AND OPEN SPACE, IN CONJUNCTION WITH ALT1 APPLICATION #B00688825, NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
19 documents · 2 drawing sheets
Latest 3 of 4 filings on this floor.
MezzanineUnder Construction21p · 1 filing · 20 docs
ArchitectureStructural
Issued Permit Scope
General Construction
CONVERT EXISTING 2 FAMILIES TO 8 FAMILIES USE, HORIZONTAL AND VERTICAL ENLARGEMENT AT CELLAR, 1ST THRU 4TH FLOOR, MEZZANINE AND PENTHOUSE, OBTAIN NEW CERTIFICATE OF OCCUPANCY.
On file for this project
87 documents · 2 drawing sheets
CellarUnder Construction21p · 2 filings · 20 docs
ArchitecturePlumbing
Issued Permit Scope
General Construction
CONVERT EXISTING 2 FAMILIES TO 8 FAMILIES USE, HORIZONTAL AND VERTICAL ENLARGEMENT AT CELLAR, 1ST THRU 4TH FLOOR, MEZZANINE AND PENTHOUSE, OBTAIN NEW CERTIFICATE OF OCCUPANCY.
On file for this project
87 documents · 1 drawing sheet
SUBMIT PLUMBING WORK ON CELLAR, 1ST~4TH FLOOR, 3RD FL. MEZZANINE, PENTHOUSE AND OPEN SPACE, IN CONJUNCTION WITH ALT1 APPLICATION #B00688825, NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
19 documents · 1 drawing sheet