| Owner | Filings | Most Recent |
|---|---|---|
| LE CAPITAL NYC | 57 | 07/08/2026 |
| NEW AMERICAN CONSTRUCTION INC | 10 | 07/08/2026 |
| AVESTA BUILDERS | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 05/04/2022 | $700K | — | — → — | $233/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| CB ENGINEERING PC | 17 | 12/17/2025 |
| CELIN MUNOZ CONSULTING ENGINEER, PC | 14 | 03/06/2025 |
| MJE PROFESSIONAL SERVICES | 3 | 09/09/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| HIGHRISE GROUP | 31 | 03/21/2026 |
| SNR EXPEDITING DESIGN | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| AVESTA BUILDERS INC | General Contractor | 21 | 07/08/2026 |
| JSB WORKS INC | General Contractor | 16 | 07/08/2026 |
| HP BUILDING MANAGEMENT IN | General Contractor | 8 | 07/08/2026 |
| NEW AMERICAN CONSTRUCTION INC | General Contractor | 2 | 07/08/2026 |
| RICHARD NEU | Electrical | 1 | 03/22/2026 |
| RRP PLUMBING CORP | Fire Protection | 1 | 07/08/2026 |
| RRP PLUMBING CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HRF SERVICES CORP | 5616 | 30 | 12/17/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Foundation | Signed-off | AVESTA BUILDERS INC | 07/29/2025 |
| DOB NOW | Earth Work | Signed-off | AVESTA BUILDERS INC | 03/17/2025 |
| DOB NOW | General Construction | Permit Issued | AVESTA BUILDERS INC | 03/10/2025 |
| DOB NOW | Mechanical Systems | Signed-off | AVESTA BUILDERS INC | 10/10/2024 |
| DOB NOW | Structural | Signed-off | AVESTA BUILDERS INC | 10/02/2024 |
| DOB NOW | General Construction | Permit Issued | AVESTA BUILDERS INC | 10/02/2024 |
| DOB NOW | Plumbing | Signed-off | RALPH W. LANDOLFI JR. | 09/13/2024 |
| DOB NOW | Support of Excavation | Signed-off | AVESTA BUILDERS INC | 09/03/2024 |
| DOB NOW | Earth Work | Signed-off | AVESTA BUILDERS INC | 08/21/2024 |
| DOB NOW | Construction Fence | Signed-off | AVESTA BUILDERS INC | 08/07/2024 |
| DOB NOW | General Construction | Permit Issued | AVESTA BUILDERS INC | 08/05/2024 |
| DOB NOW | Supported Scaffold | Signed-off | NEW AMERICAN CONSTRUCTION | 07/31/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | NEW AMERICAN CONSTRUCTION | 07/31/2024 |
| DOB NOW | Structural | Permit Issued | AVESTA BUILDERS INC | 07/29/2024 |
| DOB NOW | Sprinklers | Signed-off | RRP PLUMBING CORP | 05/30/2024 |
| DOB NOW | Construction Fence | Signed-off | JSB WORKS INC | 03/26/2024 |
| DOB NOW | Support of Excavation | Signed-off | JSB WORKS INC | 01/16/2024 |
| DOB NOW | General Construction | Permit Issued | JSB WORKS INC | 01/16/2024 |
| DOB NOW | Support of Excavation | Signed-off | JSB WORKS INC | 03/24/2023 |
| DOB NOW | General Construction | Permit Issued | JSB WORKS INC | 02/27/2023 |
| DOB NOW | Structural | Permit Issued | JSB WORKS INC | 02/24/2023 |
| DOB NOW | Construction Fence | Signed-off | JSB WORKS INC | 02/24/2023 |
| DOB NOW | Foundation | Signed-off | JSB WORKS INC | 02/23/2023 |
| DOB NOW | Foundation | Signed-off | ANGELINE PENA-LEVI | 12/29/2022 |
| DOB NOW | Structural | Permit Issued | ANGELINE PENA-LEVI | 11/04/2022 |
| DOB NOW | General Construction | Permit Issued | ANGELINE PENA-LEVI | 10/29/2022 |
| DOB NOW | Construction Fence | Signed-off | ANGELINE PENA-LEVI | 08/29/2022 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 12/17/2025 | Signed-off | AVESTA BUILDERS INC | Heating and Air Conditioning Systems, Ventilation Systems | Heat / Cool Mitsubishi Electric MSZ-GS09NA-U1 9,000 BTU · Split System ×18 MSZ-GS15NA-U1 15,000 BTU · Split System ×14 MXZ-2C20NAHZ4-U1 22,000 BTU · Split System ×10 MLZ-KP18NA2-U1 18,000 BTU · Vrf Indoor ×2 MSZ-GS06NA-U1 6,000 BTU · Split System ×2 MXZ-3C30NAHZ4-U1 28,600 BTU · Split System ×2 MXZ-SM48NAMHZ2-U1 48,000 BTU · Split System ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/17/2025 | Signed-off | RRP PLUMBING CORP | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/17/2025 | Signed-off | RRP PLUMBING CORP | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/07/2025 | Complete | KENNETH FISK ELECTRIC COR | General Wiring |
| 08/01/2024 | Complete | RICHARD NEU | — |
| 06/21/2024 | Complete | SAFEWAY CONSTRUCTION, INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/17/2025 | Signed-off | AVESTA BUILDERS INC | Steel, Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/17/2025 | Signed-off | AVESTA BUILDERS INC | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 12/05/2025 | Certified Sprinkler-Dry Pipe Valve (SP)-Dry Pipe Valve Test | Certified | View ↗ |
| 12/02/2025 | Certified Sprinkler (SP) - Booster Pump Test | Certified | View ↗ |
| 10/31/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 10/28/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 09/03/2025 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 08/13/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 04/16/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 04/02/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 03/19/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 10/21/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 07/24/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 07/24/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/22/2025 | Structural Stability – Alterations of existing buildings | FAHAD FATEH | special |
| 12/22/2025 | Interior lighting power | FAHAD FATEH | energy_progress |
| 12/22/2025 | Exterior lighting power | FAHAD FATEH | energy_progress |
| 12/22/2025 | Air barrier - visual inspection | FAHAD FATEH | energy_progress |
| 12/22/2025 | Lighting in dwelling units | FAHAD FATEH | energy_progress |
| 12/22/2025 | Protection of exposed foundation insulation | FAHAD FATEH | energy_progress |
| 12/22/2025 | Air barrier — testing | FAHAD FATEH | energy_progress |
| 12/22/2025 | Fenestration air leakage | FAHAD FATEH | energy_progress |
| 12/22/2025 | Fenestration areas | FAHAD FATEH | energy_progress |
| 12/22/2025 | Insulation placement and R values | FAHAD FATEH | energy_progress |
| 12/22/2025 | Lighting controls | FAHAD FATEH | energy_progress |
| 12/22/2025 | Fenestration and door U-factor and product ratings | FAHAD FATEH | energy_progress |
| 12/22/2025 | Maintenance information | FAHAD FATEH | energy_progress |
| 12/22/2025 | Metering | FAHAD FATEH | energy_progress |
| 12/22/2025 | Energy Code Compliance Inspections | FAHAD FATEH | progress |
| 12/22/2025 | Fire-Resistance Rated Construction | FAHAD FATEH | progress |
| 12/22/2025 | Exterior Insulation and Finish Systems (EIFS) | FAHAD FATEH | special |
| 12/22/2025 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 12/15/2025 | Fenestration air leakage | FAHAD FATEH | energy_progress |
| 12/15/2025 | Exterior Insulation and Finish Systems (EIFS) | FAHAD FATEH | special |
| 12/15/2025 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 12/15/2025 | Structural Stability – Alterations of existing buildings | FAHAD FATEH | special |
| 12/15/2025 | Energy Code Compliance Inspections | FAHAD FATEH | progress |
| 12/15/2025 | Fire-Resistance Rated Construction | FAHAD FATEH | progress |
| 12/15/2025 | Lighting controls | FAHAD FATEH | energy_progress |