Elevator apt, semi-fireproof without stores
1660 CROTONA PARK EAST
BRONX · Crotona Park East · BIN 2009870
💬 Discuss this project
1926Year Built
6Stories
D1Building Class
R7-1Zoning
75,978 sfGross Floor Area
67Units
LL97 CoveredRent Stabilized45 Open Violations 39 unresolved · 6 paperwork only ▸FISP: No Report Filed
Elevator apt, semi-fireproof without stores · Owner of record: PARKVIEW - CROTONA PARK HOUSING DEVELOPM ENT FUND C · 16,500 sf lot · 4.6 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingEquipment
Permit Issued — active, not yet Signed-off
RoofUnder Construction25p · 3 filings · 20 docs
Floor 6Under Construction19p · 1 filing · 10 docs
Floor 5Under Construction19p · 1 filing · 10 docs
Floor 4Under Construction19p · 1 filing · 10 docs
Floor 3Under Construction19p · 1 filing · 10 docs
Floor 2Under Construction19p · 1 filing · 10 docs
Floor 1Under Construction21p · 1 filing · 10 docs
CellarUnder Construction39p · 6 filings · 20 docs
Site & exteriorUnder Construction9p · 2 filings · 5 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
VOLMAR CONSTRUCTION2407/08/2026
PARKVIEW APARTMENTS2303/21/2026
TRIERA CONTRACTING1407/08/2026
PARKVIEW - CROTONA PARK HOUSING DEVELOPM ENT FUND C103/22/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
OCV ARCHITECTS303/21/2026
MEP DESIGNS403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
TRIERA CONTRACTING INCGeneral Contractor1107/08/2026
PHOENIX SUTTON STR INCGeneral Contractor407/08/2026
VOLMAR CONSTRUCTION INCGeneral Contractor407/08/2026
ACCORD POWER INCGeneral Contractor104/09/2026
LEARDON BOILER WORKS INCGeneral Contractor107/08/2026
P.H. WORKS INCPlumbing107/08/2026
PLUMBING NYC INCPlumbing107/08/2026
ELPO ELECTRICAL CONTG INCElectrical103/22/2026
WARD PLUMBING CORPPlumbing107/08/2026
RICHARD NEUElectrical103/22/2026
THOMAS KELLYElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
CROSSCHECK INSPECTION SER544303/19/2026
SYNERGIC DESIGN LLC8561109/30/2025
BAZINI ENGINEERING, P.C.1808311/01/2023
Building Lifecycle
All (176)Filed (15)Permit Issued (18)Signed Off (4)Facade (FISP) (13)Violation (60)Inspection (8)Objection (28)Special Inspection (30)
08/05/2026
Violation issued (ECB, open)
Construction
07/21/2026
Cycle 8 facade report submitted
07/06/2026
Permit issued — Sidewalk Shed
X01032986-I1-SH
06/19/2026
Violation issued (HPD, open)
A
06/19/2026
Violation issued (HPD, open)
C
06/19/2026
Violation issued (HPD, open)
A
05/28/2026
Cycle 8 facade inspection completed
05/27/2026
Violation issued (HPD, open)
B
05/27/2026
Violation issued (HPD, closed)
A
05/27/2026
Violation issued (HPD, closed)
B
05/21/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
05/20/2026
Violation issued (HPD, open)
C
05/20/2026
Violation issued (HPD, closed)
C
05/20/2026
Violation issued (HPD, closed)
C
05/20/2026
Violation issued (HPD, closed)
C
05/20/2026
Violation issued (HPD, closed)
C
05/20/2026
Violation issued (HPD, closed)
C
05/20/2026
Violation issued (HPD, closed)
C
05/20/2026
Violation issued (HPD, open)
C
05/20/2026
Violation issued (HPD, open)
C
05/20/2026
Violation issued (HPD, open)
C
05/19/2026
Violation issued (HPD, closed)
C
05/19/2026
Violation issued (HPD, open)
C
05/15/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
05/05/2026
Permit issued — Plumbing
X01282996-I1-PL
04/20/2026
Violation issued (ECB, open)
Local Law
04/07/2026
Permit issued — Sidewalk Shed
X01032986-I1-SH
03/19/2026
Filed — Alteration
INSTALL WASHER AND DRYERS FOR BUILDING TENANT'S ACCESSORY USE AT CELLAR. WORK INCLUDES PLUMBING PIPING, NEW SPRINKLER HEADS OFF EXISTING DOMESTIC WATER SYSTEM, AND DRYER VENTING. ALL AS PER PLAN. NO CHANGE IN EGRESS USE OR OCCUPANCY.
X01282996-I1
03/17/2026
Special inspection requirement — Tenant Protection Plan Compliance
EUGENE BIFULCO
03/17/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
EUGENE BIFULCO
02/03/2026
Violation issued (HPD, closed)
A
02/02/2026
Violation issued (HPD, closed)
I
10/29/2025
Filed — Alteration
X01287947-I1
10/28/2025
Permit issued — General Construction
X00913467-I1-GC
10/07/2025
Permit issued — Solar
X01286121-I1-SL
10/06/2025
Violation issued (HPD, closed)
B
10/06/2025
Violation issued (HPD, closed)
B
10/06/2025
Violation issued (HPD, closed)
B
10/06/2025
Violation issued (HPD, closed)
B
10/01/2025
Violation issued (HPD, closed)
B
09/30/2025
Filed — Alteration
Installation of 66.825 kw solar energy system on roof. No change of occupancy, use or egress.
X01286121-I1
09/11/2025
Special inspection requirement — Air barrier - visual inspection
Malathi Ananthakrishnan
09/11/2025
Special inspection requirement — Final
Malathi Ananthakrishnan
09/11/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Malathi Ananthakrishnan
09/11/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Malathi Ananthakrishnan
09/11/2025
Special inspection requirement — Energy Code Compliance Inspections
Malathi Ananthakrishnan
06/12/2025
Permit issued — General Construction
X00913467-I1-GC
04/08/2025
Permit issued — Sidewalk Shed
X01032986-I1-SH
04/03/2025
Violation issued (HPD, closed)
C
04/03/2025
Violation issued (HPD, closed)
B
02/24/2025
Violation issued (HPD, closed)
A
02/24/2025
Violation issued (HPD, closed)
C
02/24/2025
Violation issued (HPD, closed)
C
02/24/2025
Violation issued (HPD, closed)
B
02/05/2025
Violation issued (HPD, closed)
I
01/27/2025
Violation issued (HPD, closed)
B
01/27/2025
Violation issued (HPD, closed)
C
12/09/2024
Violation issued (HPD, closed)
A
12/09/2024
Violation issued (HPD, closed)
C
12/09/2024
Violation issued (HPD, closed)
C
Latest 60 of 176 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSidewalk ShedPermit IssuedPHOENIX SUTTON STR INC07/06/2026
DOB NOWPlumbingPermit IssuedPLUMBING NYC INC05/05/2026
DOB NOWSidewalk ShedPermit IssuedPHOENIX SUTTON STR INC04/07/2026
DOB NOWGeneral ConstructionPermit IssuedVOLMAR CONSTRUCTION INC10/28/2025
DOB NOWSolarPermit IssuedACCORD POWER INC10/07/2025
DOB NOWGeneral ConstructionPermit IssuedVOLMAR CONSTRUCTION INC06/12/2025
DOB NOWSidewalk ShedPermit IssuedPHOENIX SUTTON STR INC04/08/2025
DOB NOWGeneral ConstructionPermit IssuedVOLMAR CONSTRUCTION INC07/10/2024
DOB NOWSidewalk ShedPermit IssuedPHOENIX SUTTON STR INC04/11/2024
DOB NOWPlumbingSigned-offP.H. WORKS INC09/15/2023
DOB NOWSidewalk ShedSigned-offTRIERA CONTRACTING INC03/01/2022
DOB NOWSupported ScaffoldPermit IssuedTRIERA CONTRACTING INC10/01/2021
DOB NOWPlumbingSigned-offWARD PLUMBING CORP09/22/2021
DOB NOWMechanical SystemsSigned-offLEARDON BOILER WORKS INC09/21/2021
DOB NOWBoiler EquipmentSigned-offLEARDON BOILER WORKS.INC09/21/2021
DOB NOWSidewalk ShedSigned-offTRIERA CONTRACTING INC03/04/2021
DOB NOWSupported ScaffoldPermit IssuedTRIERA CONTRACTING INC10/02/2020
DOB NOWSidewalk ShedSigned-offTRIERA CONTRACTING INC12/30/2019
BISOTISSUEDVOLMAR CONSTRUCTION INC09/09/2022
BISOTISSUEDVOLMAR CONSTRUCTION INC12/14/2020
BISBLISSUEDWASOFF PLBG & UTILITY CO03/02/2012
BISPLISSUEDWASOFF PLBG & UTILITY CO03/02/2012
BISBLISSUEDLARRY BERGE07/09/2003
BISOTISSUEDNEWTON CONSTRUCTION & DEV. CORP.04/29/2003
BISPLRE-ISSUEDDANICA PLUMBING & HEATING CORP.01/30/2002
BISOTISSUEDNEWTOWN CONSTRUCTION & DEVELOP.05/04/2001
BISEQISSUEDNEWTOWN CONSTRUCTION & DEVELOP.03/27/2001
BISEQISSUEDNEWTOWN CONSTRUCTION & DEVELOP.01/08/2001
BISEQISSUEDCLARK & WILKINS INDUSTRIES INC12/12/2000
BISPLISSUEDIHOPE PLUMBING & HEATING CO., IN10/31/2000
BISOTISSUEDVOLMAR CONSTRUCTION INC07/28/2000
BISEQISSUEDNEWTOWN CONSTRUCTION & DEVELOP.07/03/2000
BISOTISSUEDNEWTOWN CONSTRUCTION & DEVELOP.06/16/2000
BISFBISSUEDMARLANDE HEATING CORP.03/07/1991
1 project · most recent 12/12/2023
Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
12/12/2023——Ventilation Systems
Ventilation
Pennbarry Mod. SX11SQ1 1,700 CFM · Exhaust Fan ×1
2 projects · most recent 03/19/2026
Gas Plumbing-Sprinkler Water/Sanitary
FiledStatusContractorScope
03/19/2026Permit IssuedPLUMBING WORKS NYC INCGas, Plumbing-Sprinkler, Water/Sanitary
12/12/2023——Gas
7 projects · most recent 06/23/2026
General Wiring
FiledStatusContractorScope
06/23/2026Permit IssuedLEVIS ELECTR'L CONTR. CORGeneral Wiring
09/30/2025Permit IssuedACCORD POWER ELECTRIC LLC2 meters, 1 new_meters
04/03/2024Permit IssuedELPO ELECTRICAL CONTG INC—
03/20/2024CompleteLEVIS ELECTR'L CONTR. CORGeneral Wiring
02/06/2023CompleteLEVIS ELECTR'L CONTR. CORGeneral Wiring
11/05/2021Permit IssuedMONTE ELECTRIC CO.—
12/21/2019Permit IssuedRICHARD NEU—
1 project · most recent 09/30/2025
FiledStatusContractorScope
09/30/2025Permit IssuedACCORD POWER INC165 panels, 66.82 kw, 12,716.47 roof_area_sqft
1 project · most recent 09/30/2025
Tenant Protection Plan 72 Hour
FiledStatusContractorScope
09/30/2025Permit IssuedACCORD POWER INCTenant Protection Plan 72 Hour
▾Field Inspections (DOB CAP) — 8
DateTypeResultReport
05/21/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
05/15/2026Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
11/08/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
11/08/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/26/2022Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
04/21/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/18/2022Fail-Final PL - Up to 3 Requested FloorsFailView ↗
02/18/2022Pass-Final Boiler Equipment InspectionPassView ↗
▾Special Inspection Requirements (DOB NOW) — 41
DateRequirementInspectorRole
03/17/2026Tenant Protection Plan ComplianceEUGENE BIFULCOspecial
03/17/2026Fire-Resistant Penetrations and JointsEUGENE BIFULCOspecial
09/11/2025Air barrier - visual inspectionMalathi Ananthakrishnanenergy_progress
09/11/2025FinalMalathi Ananthakrishnanprogress
09/11/2025Fire-Resistant Penetrations and JointsMalathi Ananthakrishnanspecial
09/11/2025Structural Stability – Alterations of existing buildingsMalathi Ananthakrishnanspecial
09/11/2025Energy Code Compliance InspectionsMalathi Ananthakrishnanprogress
03/22/2024Fenestration areasEUGENE BIFULCOenergy_progress
03/22/2024Fire-Resistant Penetrations and JointsEUGENE BIFULCOspecial
03/22/2024Fenestration air leakageEUGENE BIFULCOenergy_progress
03/22/2024Interior lighting powerEUGENE BIFULCOenergy_progress
03/22/2024FinalEUGENE BIFULCOprogress
03/22/2024Structural Stability – Alterations of existing buildingsEUGENE BIFULCOspecial
03/22/2024MasonryEUGENE BIFULCOspecial
03/22/2024Tenant Protection Plan ComplianceEUGENE BIFULCOspecial
03/22/2024Fenestration and door U-factor and product ratingsEUGENE BIFULCOenergy_progress
03/22/2024Exterior lighting powerEUGENE BIFULCOenergy_progress
03/14/2024Exterior lighting power—energy_progress
03/14/2024Tenant Protection Plan Compliance—special
03/14/2024Fire-Resistant Penetrations and Joints—special
03/14/2024Masonry—special
03/14/2024Structural Stability – Alterations of existing buildings—special
03/14/2024Final—progress
03/14/2024Fenestration and door U-factor and product ratings—energy_progress
03/14/2024Fenestration air leakage—energy_progress
Latest 25 of 41.
▾Documents — 80 on file (BIS + DOB NOW)
▸Plans & Drawings13
▸DOB NOWPlans/Sketch11
08/25/2026X00579841-P1Request digital key ↗
08/25/2026X00579841-I1Request digital key ↗
08/25/2026X00579849-I1Request digital key ↗
Showing 3 of 11 on file for this type
▸DOB NOWPlans/Sketch - Supported Scaffold1
08/25/2026X00407430-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sidewalk Shed1
08/26/2026X00286073-I1Request digital key ↗
▸Applications & Permits7
▸BISWORK PERMIT APPLICATION3
12/14/2020240290029Open ↗
03/02/2012220171739Open ↗
03/02/2012220171739Open ↗
▸BISPLAN / WORK APPROVAL APPLICATION2
11/10/2020240290029Open ↗
03/02/2012220171739Open ↗
▸BISSIDEWALK SHED APPLICATION & PERMIT1
12/04/2020240290029Open ↗
▸BISSCAFFOLD APPLICATION & PERMIT1
12/04/2020240290029Open ↗
▸Seals & Professional Certifications27
▸DOB NOWDPL-1: Design Professional Seal & Signature13
08/25/2026X00407430-I1Open ↗
08/25/2026X00579841-I1Open ↗
08/25/2026X00579841-P1Open ↗
Showing 3 of 13 on file for this type
▸DOB NOWProgress Inspector Seal & Signature6
09/23/2026X00579834-I1Open ↗
08/31/2026X01286121-I1Open ↗
08/31/2026X01286121-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
08/31/2026X01286121-I1Open ↗
08/31/2026X01286121-I1Open ↗
08/30/2026X01282996-I1Open ↗
Showing 3 of 4 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
11/10/2020240290029Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
03/02/2012220171739Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
03/02/2012220171739Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION1
03/02/2012220171739Open ↗
▸Trade Schedules & Equipment3
▸BISSCHEDULE B - PLUMBING2
03/02/2012220171739Open ↗
03/02/2012220171739Open ↗
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT1
03/02/2012220171739Open ↗
▸Safety & Tenant Protection3
▸DOB NOWTenant Protection Plan2
08/13/2026X00286073-I1Open ↗
08/13/2026X00407430-I1Open ↗
▸BISTENANT PROTECTION PLAN AND NOTES1
11/10/2020240290029Open ↗
▸Environmental & Asbestos8
▸DOB NOWDEP ACP-5: Asbestos Assessment Report5
08/25/2026X00579841-I1Open ↗
08/25/2026X00579841-P1Open ↗
08/25/2026X00579834-I1Open ↗
Showing 3 of 5 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'1
03/02/2012220171739Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
12/04/2020240290029Open ↗
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form1
08/18/2026X01287947-I1Open ↗
▸Energy Compliance5
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
11/19/2020240290029Open ↗
▸BISTECHNICAL REPORT: ENERGY1
03/02/2012220171739Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
12/02/2022240290029Open ↗
▸DOB NOWPreliminary Commissioning Report Certification1
08/13/2026X00579834-I1Open ↗
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026X00579834-I1Open ↗
▸Inspections & Test Reports2
▸BISTECHNICAL REPORT: RESPONSIBILITY2
12/10/2020240290029Open ↗
11/10/2020240290029Open ↗
▸Approvals, Objections & Sign-offs5
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
12/05/2022240290029Open ↗
▸BISFINAL1
12/02/2022240290029Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
03/02/2012220171739Open ↗
▸DOB NOWDEP Variance (V5) letter1
08/13/2026X00913467-I1Open ↗
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter1
08/18/2026X01287947-I1Open ↗
▸Cost, Insurance & Ownership4
▸BISCOST AFFIDAVIT2
11/11/2020240290029Open ↗
03/02/2012220171739Open ↗
▸BISCOST AFFIDAVIT ESTIMATE: (PW3)1
11/19/2020240290029Open ↗
▸BISCOST AFFIDAVIT (FINAL): PW31
12/02/2022240290029Open ↗
▸Filing & Intake Forms3
▸BISADDITIONAL INFORMATION1
11/19/2020240290029Open ↗
▸BISEFILING COVER SHEET1
03/02/2012220171739Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
11/10/2020240290029Open ↗