| Owner | Filings | Most Recent |
|---|---|---|
| LEFKO CAPITAL GROUP | 25 | 07/08/2026 |
| OWNERS REP | 14 | 07/08/2026 |
| DORIA, INC | 7 | 03/22/2026 |
| TOWNSEND PARTNERS LLC | 3 | 03/22/2026 |
| SKYWARD DEVELOPMENT INC | 1 | 03/22/2026 |
| SKYWARD DEVELOPERS | 5 | 03/22/2026 |
| TOWNSEND OARTNERS LLC | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 07/22/2021 | $1.9M | — | Private party → TOWNSEND PARTNERS LLC | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| VASILIOS ARTEMIOU PE | 5 | 11/16/2022 |
| BMG DESIGN BUILD LLC | 4 | 11/10/2022 |
| PAUL PERDEK, PROF. ENG. PLLC | 9 | 09/25/2022 |
| LOMBARDO PROFESSIONAL ENGINEERING | 2 | 07/08/2022 |
| ELEVATED ENGINEERING NYC | 4 | 02/28/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| NYC DESIGN FILE | 13 | 03/21/2026 |
| AE DESIGN SOLUTION | 18 | 03/21/2026 |
| LOMBARDO PROFESSIONAL ENGINEERING | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SKYWARD DEVELOPERS INC | General Contractor | 12 | 07/08/2026 |
| CORE SCAFFOLD SYSTEMS INC. | General Contractor | 10 | 07/08/2026 |
| DORIA, INC | General Contractor | 2 | 03/21/2026 |
| HIVOLTS ELECTRICAL INC 004090 | General Contractor | 2 | 03/22/2026 |
| PRIME PIPING & HEATING IN | Plumbing | 2 | 07/08/2026 |
| BMG ARCHITECT | General Contractor | 2 | 03/22/2026 |
| TRISTATE FIRE SPRINK INC | Fire Protection | 1 | 07/08/2026 |
| BOAZ GOLANI | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HRF SERVICES CORP | 5616 | 12 | 11/16/2022 |
| LEO Y LEE ASSOCIATES | 2481 | 3 | 09/25/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Protection and Mechanical Methods | Signed-off | DORIA, INC | 07/06/2022 |
| DOB NOW | Sprinklers | Signed-off | TRISTATE FIRE SPRINK INC | 06/22/2022 |
| DOB NOW | Sprinklers | Signed-off | PRIME PIPING & HEATING IN | 06/10/2022 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | CORE SCAFFOLD SYSTEMS INC | 06/10/2022 |
| DOB NOW | Plumbing | Signed-off | PRIME PIPING & HEATING IN | 06/01/2022 |
| DOB NOW | Supported Scaffold | Signed-off | CORE SCAFFOLD SYSTEMS INC | 05/09/2022 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | CORE SCAFFOLD SYSTEMS INC | 04/22/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | CORE SCAFFOLD SYSTEMS INC | 04/05/2022 |
| DOB NOW | Mechanical Systems | Signed-off | SKYWARD DEVELOPERS INC | 03/31/2022 |
| DOB NOW | Structural | Signed-off | SKYWARD DEVELOPERS INC | 02/25/2022 |
| DOB NOW | Support of Excavation | Signed-off | SKYWARD DEVELOPERS INC | 02/21/2022 |
| DOB NOW | Foundation | Signed-off | SKYWARD DEVELOPERS INC | 02/19/2022 |
| DOB NOW | General Construction | Permit Issued | SKYWARD DEVELOPERS INC | 02/15/2022 |
| DOB NOW | Construction Fence | Signed-off | SKYWARD DEVELOPERS INC | 11/23/2021 |
| BIS | EQ | ISSUED | SKYWARD DEVELOPERS INC | 12/28/2021 |
| BIS | — | ISSUED | SKYWARD DEVELOPERS INC | 12/28/2021 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 11/16/2022 | Signed-off | SKYWARD DEVELOPERS INC | Air Conditioning Systems, Associated Ducts and Piping, Heating Systems, Ventilation Systems | Cooling Amana PTH073G25 7,600 BTU · Ptac ×78 PTH123G25 12,000 BTU · Ptac ×48 PTH093G35 9,000 BTU · Ptac ×18 PTH153G25 14,700 BTU · Ptac ×12 PTH153G35 14,700 BTU · Ptac ×10 Heating Amana PTH073G25 6,800 BTU · Heat Pump Outdoor ×78 PTH123G25 11,300 BTU · Heat Pump Outdoor ×48 PTH093G35 8,100 BTU · Heat Pump Outdoor ×18 PTH153G25 13,600 BTU · Heat Pump Outdoor ×12 PTH153G35 13,600 BTU · Heat Pump Outdoor ×10 Ventilation Ducts & Piping Masterflow DUCTS Ductwork ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/16/2022 | Signed-off | TRISTATE FIRE SPRINK INC | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/16/2022 | Signed-off | A M B MECHANICAL INC | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/19/2023 | Complete | STAR ELEC'L CONTRACTORS C | — |
| 03/27/2022 | Complete | V. VASS ELECTRIC CORP | — |
| 02/09/2022 | Complete | HIVOLTS ELECTRICAL INC | General Wiring |
| 02/09/2022 | Complete | HIVOLTS ELECTRICAL INC | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/16/2022 | Signed-off | TRISTATE FIRE SPRINK INC | Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/16/2022 | Signed-off | TRISTATE FIRE SPRINK INC | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 12/12/2022 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 12/08/2022 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 12/08/2022 | Pass-Final SP - Up to 9 Requested Floors | Pass | View ↗ |
| 12/01/2022 | Pass-Final SP - Up to 9 Requested Floors | Pass | View ↗ |
| 11/28/2022 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 09/06/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/02/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/22/2022 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 06/13/2022 | Pass-Final PL - Underground | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/28/2022 | Insulation placement and R values | FAHAD FATEH | energy_progress |
| 11/28/2022 | Air barrier - visual inspection | FAHAD FATEH | energy_progress |
| 11/28/2022 | HVAC-R and service water piping design and insulation | FAHAD FATEH | energy_progress |
| 11/28/2022 | Fenestration areas | FAHAD FATEH | energy_progress |
| 11/28/2022 | HVAC-R and service water piping design and insulation | FAHAD FATEH | energy_progress |
| 11/28/2022 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 11/28/2022 | Sprinkler Systems | FAHAD FATEH | special |
| 11/28/2022 | Fenestration air leakage | FAHAD FATEH | energy_progress |
| 11/28/2022 | Interior lighting power | FAHAD FATEH | energy_progress |
| 11/28/2022 | Subsurface Investigations (Borings/Test Pits) | FAHAD FATEH | special |
| 11/28/2022 | Masonry | FAHAD FATEH | special |
| 11/28/2022 | Subgrade Inspections | FAHAD FATEH | special |
| 11/28/2022 | Excavations - Sheeting, Shoring, and Bracing | FAHAD FATEH | special |
| 11/28/2022 | Exterior Insulation and Finish Systems (EIFS) | FAHAD FATEH | special |
| 11/28/2022 | Concrete - Cast-In-Place | FAHAD FATEH | special |
| 11/28/2022 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | FAHAD FATEH | special |
| 11/28/2022 | Wall Panels, Curtain Walls, and Veneers | FAHAD FATEH | special |
| 11/28/2022 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 11/28/2022 | Energy Code Compliance Inspections | FAHAD FATEH | progress |
| 11/28/2022 | Preliminary | FAHAD FATEH | progress |
| 11/28/2022 | Fire-Resistance Rated Construction | FAHAD FATEH | progress |
| 11/28/2022 | Metering | FAHAD FATEH | energy_progress |
| 11/28/2022 | Exterior lighting power | FAHAD FATEH | energy_progress |
| 11/28/2022 | Fenestration and door U-factor and product ratings | FAHAD FATEH | energy_progress |
| 11/28/2022 | Air barrier continuity plan testing | FAHAD FATEH | energy_progress |