← Back
Three families
1679 GROVE STREET
QUEENS · BIN 4082269
💬 Discuss this project
1901Year Built
3Stories
C0Building Class
R6BZoning
—Gross Floor Area
3Units
5 Open Violations ▸
Three families · 1.53 FAR built · Flood zone X
Locations of Work
Architecture
Floor 33p · 1 filing · 6 docs
Floor 23p · 1 filing · 6 docs
Floor 13p · 1 filing · 6 docs
Cellar3p · 1 filing · 6 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
URENA CONSTRUCTION & DESIGN404/09/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
HANY DEMETRY112/26/2024
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
URENA CONST & DESIGN INCGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ENGINEERING CONSULTING SE2050112/26/2024
Building Lifecycle
All (16)Filed (1)Permit Issued (1)Violation (9)Special Inspection (5)
09/19/2025
Permit issued — General Construction
Q01158384-I1-GC
12/26/2024
Filed — Alteration
WORK TO REMOVE AND INSTALL NEW PLUMBING FIXTURES IN CONJUNCTION WITH PROPOSED INTERIOR EXISTING THREE FAMILY HOUSE TO REPAIR FIRE DAMAGE.
Q01158384-I1
12/19/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
PAUL MARINO
12/19/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
PAUL MARINO
12/19/2024
Special inspection requirement — Energy Code Compliance Inspections
PAUL MARINO
12/19/2024
Special inspection requirement — Insulation placement and R values
PAUL MARINO
12/19/2024
Special inspection requirement — Lighting in dwelling units
PAUL MARINO
05/15/2024
Violation issued (HPD, open)
I
05/07/2024
Violation issued (HPD, open)
C
05/07/2024
Violation issued (HPD, open)
C
05/07/2024
Violation issued (HPD, open)
C
05/07/2024
Violation issued (HPD, open)
C
11/16/2022
Violation issued (HPD, closed)
I
04/15/2021
Violation issued (HPD, closed)
A
11/22/2016
Violation issued (HPD, closed)
I
02/27/2015
Violation issued (HPD, closed)
I
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedURENA CONST & DESIGN INC09/19/2025
BISPLISSUEDMONARCH MECHANICAL,INC.01/22/2003
BISOTISSUEDFOUR BROTHERS GEN. CONSTR. & DEV01/09/2003
1 project · most recent 12/26/2024
Water/Sanitary
FiledStatusContractorScope
12/26/2024——Water/Sanitary
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
12/19/2024Fire-Resistant Penetrations and JointsPAUL MARINOspecial
12/19/2024Structural Stability – Alterations of existing buildingsPAUL MARINOspecial
12/19/2024Energy Code Compliance InspectionsPAUL MARINOprogress
12/19/2024Insulation placement and R valuesPAUL MARINOenergy_progress
12/19/2024Lighting in dwelling unitsPAUL MARINOenergy_progress
▾Documents — 9 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/21/2026Q01158384-I1Request digital key ↗
08/21/2026Q01158384-S1Request digital key ↗
▸Seals & Professional Certifications5
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/13/2026Q01158384-S1Open ↗
08/13/2026Q01158384-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
08/27/2026Q01158384-I1Open ↗
08/27/2026Q01158384-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/27/2026Q01158384-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/13/2026Q01158384-S1Open ↗
08/13/2026Q01158384-I1Open ↗