| Owner | Filings | Most Recent |
|---|---|---|
| TASLIM CONSTRUCTION | 16 | 07/08/2026 |
| 168-05 JAMAICA | 3 | 03/21/2026 |
| YED | 2 | 03/21/2026 |
| 168-05 JAMAICA ACE | 1 | 03/21/2026 |
| 168-05 JAMAICA AVE | 1 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 03/06/2019 | $2.5M | — | EMANDAR REALTY CORP. → 16801 LLC | $397/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| CHANDA ENGINEERING CONSULTANT PC | 6 | 12/28/2023 |
| CL ENGINEERING P.C. | 1 | 11/09/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| METRO DESIGN CONSULTANTS INC | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| TASLIM CONSTRUCTION INC | General Contractor | 2 | 07/08/2026 |
| MATSIKAS VASILIOS | Electrical | 1 | 03/21/2026 |
| VASILIOS MATSIKAS | Electrical | 1 | 03/21/2026 |
| HORBRIDGE PLUMBING & HEATING | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CHANDA ENG. CONSULTANT PC | 6842 | 5 | 12/12/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | HORBRIDGE PLUMBING & HEAT | 10/18/2023 |
| DOB NOW | Mechanical Systems | Permit Issued | TASLIM CONSTRUCTION INC | 10/17/2023 |
| DOB NOW | General Construction | Permit Issued | TASLIM CONSTRUCTION INC | 09/29/2023 |
| BIS | FP | ISSUED | FIRE COMMAND CO, INC | 10/24/2017 |
| BIS | PL | ISSUED | KATAN P & H INC | 09/14/2017 |
| BIS | OT | ISSUED | GUARANTEED HOME IMPROVEME | 07/17/2017 |
| BIS | MH | ISSUED | URENA CONST & DESIGN INC | 03/06/2017 |
| BIS | FP | ISSUED | MEGA FIRE PROTECTION INC | 11/15/2010 |
| BIS | OT | ISSUED | THREE STAR CONSTRUCTION C | 08/16/2010 |
| BIS | PL | ISSUED | LLOYD G DRUMMOND PLBG&GEN | 08/16/2010 |
| BIS | OT | ISSUED | TASLIM CONSTRUCTION INC | 06/04/2008 |
| BIS | OT | ISSUED | TASLIM CONSTRUCTION INC | 05/27/2008 |
| BIS | OT | ISSUED | PAUL SIGNS INC | 01/04/2006 |
| BIS | MH | ISSUED | ALL-RITE CONSTRUCTION CO | 11/14/2005 |
| BIS | PL | ISSUED | SCHMELZ BROS., INC | 11/01/2005 |
| BIS | OT | ISSUED | ALL-RITE CONSTRUCTION CO | 10/25/2005 |
| BIS | EQ | ISSUED | YORK SCAFFOLD EQUIPMENT CORP. | 12/18/2000 |
| BIS | EQ | ISSUED | YORK SCAFFOLD EQUIPMENT CORP. | 12/18/2000 |
| BIS | OT | ISSUED | GLENDALE SHADE AWNING CO INN. | 10/12/1995 |
| BIS | — | ISSUED | S H LAUFER | 08/30/1991 |
| BIS | — | ISSUED | S H LAUFER | 08/30/1991 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 12/12/2023 | Permit Issued | TASLIM CONSTRUCTION INC | Associated Ducts and Piping, Ventilation Systems | Ventilation Captiveaire NCA16 4,500 CFM · Kitchen Exhaust ×2 Ducts & Piping Canarm 212 3,400 CFM · Makeup Air ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/12/2023 | Permit Issued | HORBRIDGE PLUMBING & HEAT | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/11/2025 | Permit Issued | JP & SON ELECTRIC CORP | 6 meters |
| 12/07/2023 | Permit Issued | FIRST CHOICE ELECTRICAL | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 06/17/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/09/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 08/09/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 08/09/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/09/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 01/11/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/31/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/27/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/26/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 10/26/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/26/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/28/2023 | Final | — | progress |
| 12/12/2023 | Fire-Resistant Penetrations and Joints | KARTIK CHANDA | special |
| 12/09/2023 | Ventilation and air distribution system | KARTIK CHANDA | energy_progress |
| 12/09/2023 | Maintenance information | KARTIK CHANDA | energy_progress |
| 12/09/2023 | Final | KARTIK CHANDA | progress |
| 12/09/2023 | Energy Code Compliance Inspections | KARTIK CHANDA | progress |
| 12/09/2023 | Mechanical Systems | KARTIK CHANDA | special |
| 12/09/2023 | Fire-Resistant Penetrations and Joints | KARTIK CHANDA | special |
| 11/09/2022 | Construction Operations Influencing Adjacent Structures | — | special |
| 09/06/2022 | Energy Code Compliance Inspections | — | progress |
| 09/06/2022 | Fire-Resistance Rated Construction | — | progress |
| 09/06/2022 | Structural Wood Frame | — | progress |
| 09/06/2022 | Maintenance information | — | energy_progress |
| 09/06/2022 | HVAC-R and service water heating system controls | — | energy_progress |
| 09/06/2022 | Air barrier - visual inspection | — | energy_progress |
| 09/06/2022 | Metering | — | energy_progress |
| 09/06/2022 | Fenestration and door U-factor and product ratings | — | energy_progress |
| 09/06/2022 | Duct leakage testing, insulation and design | — | energy_progress |
| 09/06/2022 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 09/06/2022 | Permanent certificate | — | energy_progress |
| 09/06/2022 | Interior lighting power | — | energy_progress |
| 09/06/2022 | Fenestration air leakage | — | energy_progress |
| 09/06/2022 | Fenestration areas | — | energy_progress |
| 09/06/2022 | HVAC-R and service water heating equipment | — | energy_progress |
| 09/06/2022 | Masonry | — | special |