← Back
Two family frame
168-17 65 AVENUE
QUEENS · Fresh Meadows-Utopia · BIN 4148909
💬 Discuss this project
1940Year Built
1.5Stories
B2Building Class
R4Zoning
2,633 sfGross Floor Area
2Units
Two family frame · 5,000 sf lot · 0.53 FAR built · Flood zone X
Locations of Work
Electrical
Roof1 filing · 11 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
08/03/2015$925K—— → —$351/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MOMENTUM SOLAR206/19/2025
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ISLAND ELECTRIC CORPElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SHAHRISH SHUVO ENGINEERIN8524106/19/2025
MXV SIA LLC9281101/30/2024
Building Lifecycle
All (13)Filed (2)Permit Issued (1)Signed Off (1)Objection (4)Special Inspection (5)
09/08/2025
Signed off — Alteration
Installation of solar panels; Rooftop, Railed, Grid tied, 19 Panels, 7.6 kW
Q00990566-I1
08/07/2025
Objection resolved — Addressed
07/10/2025
Objection raised — Admin
06/19/2025
Filed — Alteration
Installation of solar panels; Rooftop, Railed, Grid tied, 19 Panels, 7.6 kW
Q00990566-P1
04/28/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Shahrish Shuvo
04/28/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Shahrish Shuvo
04/28/2025
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
04/28/2025
Special inspection requirement — Final
Mina Makar
04/28/2025
Special inspection requirement — Air barrier - visual inspection
Mina Makar
02/22/2024
Permit issued — Solar
Q00990566-I1-SL
02/08/2024
Objection resolved — Addressed
02/05/2024
Objection raised — Other
01/30/2024
Filed — Alteration
Installation of solar panels; Rooftop, Railed, Grid tied, 19 Panels, 7.6 kW
Q00990566-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offMOMENTUM SOLAR02/22/2024
1 project · most recent 01/29/2024
FiledStatusContractorScope
01/29/2024CompleteISLAND ELECTRIC CORP—
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
04/28/2025Fire-Resistant Penetrations and JointsShahrish Shuvospecial
04/28/2025Structural Stability – Alterations of existing buildingsShahrish Shuvospecial
04/28/2025Energy Code Compliance InspectionsMina Makarprogress
04/28/2025FinalMina Makarprogress
04/28/2025Air barrier - visual inspectionMina Makarenergy_progress
▾Documents — 10 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/19/2026Q00990566-P1Request digital key ↗
08/19/2026Q00990566-I1Request digital key ↗
▸Seals & Professional Certifications5
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/19/2026Q00990566-I1Open ↗
08/19/2026Q00990566-P1Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
08/30/2026Q00990566-P1Open ↗
08/30/2026Q00990566-P1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/30/2026Q00990566-P1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/19/2026Q00990566-I1Open ↗
08/19/2026Q00990566-P1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q00990566-I1Open ↗