| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 05/19/2022 | $2.0M | — | — → — | — not available |
| 08/28/2018 | $1.9M | — | Private party → 168 EXETER L.L.C. | — not available |
| 05/02/2016 | $1.2M | — | Private party → Private party | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| ZPROEKT ARCHITECTURE | 13 | 09/02/2025 |
| SQUARE ARCH, LLC | 1 | 12/20/2023 |
| ARYEH SIEGEL ARCHITECT | 1 | 06/09/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| KAMTECH RESTORATION CORP | 2 | 03/21/2026 |
| HM CONSULTING EXPEDITING | 26 | 03/21/2026 |
| AVALON DESIGNS | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SAPOL CONSTRUCTION LLC | General Contractor | 16 | 07/08/2026 |
| PFL MECHANICAL CORP | Plumbing | 2 | 07/08/2026 |
| FALCO ELEC'L SERVICES INC | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| STEEL CORE ENGINEERING PL | 1098 | 9 | 09/02/2025 |
| SQ. ARCH, LLC | 4802 | 1 | 12/20/2023 |
| TECNICO SPECIAL INSPECTIO | 5939 | 1 | 09/20/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | LEON D. DEMATTEIS CONSTR | 07/28/2025 |
| DOB NOW | Curb Cut | Signed-off | LEON D. DEMATTEIS CONSTR | 05/23/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | LEON D. DEMATTEIS CONSTR | 01/09/2025 |
| DOB NOW | Plumbing | Signed-off | PFL MECHANICAL CORP | 08/09/2024 |
| DOB NOW | Structural | Signed-off | LEON D. DEMATTEIS CONSTR | 07/23/2024 |
| DOB NOW | Foundation | Signed-off | LEON D. DEMATTEIS CONSTR | 07/23/2024 |
| DOB NOW | General Construction | Permit Issued | LEON D. DEMATTEIS CONSTR | 01/19/2024 |
| DOB NOW | General Construction | Signed-off | LEON D. DEMATTEIS CONSTR | 01/18/2024 |
| DOB NOW | Plumbing | Signed-off | PFL MECHANICAL CORP | 05/08/2023 |
| DOB NOW | General Construction | Signed-off | LEON D. DEMATTEIS CONSTR | 03/06/2023 |
| DOB NOW | Mechanical Systems | Permit Issued | LEON D. DEMATTEIS CONSTR | 02/03/2023 |
| DOB NOW | Mechanical Systems | Signed-off | LEON D. DEMATTEIS CONSTR | 02/03/2023 |
| BIS | EQ | ISSUED | CHESAKL ENTERPRISES INC | 06/11/2025 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 09/02/2025 | Signed-off | SAPOL CONSTRUCTION LLC | Air Conditioning Systems | Cooling Mitsubishi Electric MXZ-SM60NAM2 60,000 BTU · Split System ×3 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/02/2025 | Signed-off | PFL MECHANICAL CORP | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/28/2025 | Complete | FALCO ELEC'L SERVICES INC | General Wiring |
| 03/31/2025 | Complete | FALCO ELEC'L SERVICES INC | General Wiring |
| 11/30/2023 | Complete | BERGER QUALITY ELEC'L CON | — |
| 07/06/2022 | Complete | FALCO ELEC'L SERVICES INC | 1 meters, 1 new_meters |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/04/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 07/09/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 06/24/2025 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 06/03/2025 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 05/27/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/22/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 08/26/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/14/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/05/2023 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 05/18/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/19/2025 | Subgrade Inspections | Alexander Sheyman | special |
| 09/19/2025 | Air barrier — testing | Alexander Sheyman | energy_progress |
| 09/19/2025 | Fenestration air leakage | Alexander Sheyman | energy_progress |
| 09/19/2025 | Fenestration areas | Alexander Sheyman | energy_progress |
| 09/19/2025 | Fenestration and door U-factor and product ratings | Alexander Sheyman | energy_progress |
| 09/19/2025 | Duct leakage testing, insulation and design | Alexander Sheyman | energy_progress |
| 09/19/2025 | Metering | Alexander Sheyman | energy_progress |
| 09/19/2025 | Protection of exposed foundation insulation | Alexander Sheyman | energy_progress |
| 09/19/2025 | Electric vehicle service equipment requirements | Alexander Sheyman | energy_progress |
| 09/19/2025 | HVAC-R and service water piping design and insulation | Alexander Sheyman | energy_progress |
| 09/19/2025 | Interior lighting power | Alexander Sheyman | energy_progress |
| 09/19/2025 | Air barrier - visual inspection | Alexander Sheyman | energy_progress |
| 09/19/2025 | Permanent certificate | Alexander Sheyman | energy_progress |
| 09/19/2025 | Insulation placement and R values | Alexander Sheyman | energy_progress |
| 09/19/2025 | HVAC-R and service water heating system controls | Alexander Sheyman | energy_progress |
| 09/19/2025 | HVAC-R and service water heating equipment | Alexander Sheyman | energy_progress |
| 09/19/2025 | Ventilation and air distribution system | Alexander Sheyman | energy_progress |
| 09/19/2025 | Fireplaces | Alexander Sheyman | energy_progress |
| 09/19/2025 | Maintenance information | Alexander Sheyman | energy_progress |
| 09/19/2025 | Lowest Floor Elevation | Alexander Sheyman | progress |
| 09/19/2025 | Energy Code Compliance Inspections | Alexander Sheyman | progress |
| 09/19/2025 | Fire-Resistance Rated Construction | Alexander Sheyman | progress |
| 09/19/2025 | Final | Alexander Sheyman | progress |
| 09/19/2025 | Masonry | Alexander Sheyman | special |
| 09/19/2025 | Mechanical Systems | Alexander Sheyman | special |