← Back
Walk-up cooperative
168 WAVERLY PLACE
MANHATTAN · BIN 1010237
💬 Discuss this project
1834Year Built
3Stories
C6Building Class
R6Zoning
3,696 sfGross Floor Area
2Units
1 Open Violation 0 unresolved · 1 paperwork only ▸
Walk-up cooperative · Owner of record: 168-170 OWNERS CORP · 1,680 sf lot · 2.2 FAR built · Flood zone X
Locations of Work
ArchitectureStructural
Roof1p · 1 filing · 20 docs
Bulkhead1p · 1 filing · 20 docs
Basement1p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
125 AVENUE GROUP1307/08/2026
168-170 OWNERS CORP203/22/2026
168-170 OWNERS CO-OP203/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
PRUDIGM ENGINEERING LLC308/01/2022
BLUE SKY DESIGN, INC.305/19/2022
ENTHINK ENGINEERS LLC212/06/2021
STEVEN KRATCHMAN ARCHITECT, PC310/04/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
CONVERSANO ASSOCIATES, INC.1803/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
KORONA CONSTRUCTION CORPGeneral Contractor507/08/2026
PHOENIX SUTTON STR INCGeneral Contractor203/21/2026
ELPO ELECTRICAL CONTG INCElectrical103/22/2026
HEMANCHAL DEONARINEElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
PRUDIGM ENGINEERING LLCU4304308/01/2022
BLUE SKY DESIGN, INC.1908305/19/2022
Nothing on file for this building.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWStructuralSigned-offKORONA CONSTRUCTION CORP10/21/2021
DOB NOWMechanical SystemsSigned-offKORONA CONSTRUCTION CORP10/12/2021
DOB NOWGeneral ConstructionSigned-offKORONA CONSTRUCTION CORP10/06/2021
DOB NOWSidewalk ShedSigned-offPHOENIX SUTTON STR INC08/10/2021
BISPLISSUEDKIN CHI PLBG & HTG CORP07/26/1999
BISOTISSUEDJAMES LEE CONSTRUCTION07/26/1999
2 projects · most recent 07/29/2021
General Wiring
FiledStatusContractorScope
07/29/2021CompleteELPO ELECTRICAL CONTG INC—
07/26/2021CompleteM & R ELECL CONTG AND REPGeneral Wiring
▾Special Inspection Requirements (DOB NOW) — 24
DateRequirementInspectorRole
07/29/2022Mechanical SystemsNaeem Anwarspecial
07/29/2022FinalNaeem Anwarprogress
07/29/2022Fire-Resistant Penetrations and JointsNaeem Anwarspecial
10/08/2021FinalNaeem Anwarprogress
10/08/2021Mechanical SystemsNaeem Anwarspecial
10/08/2021Fire-Resistant Penetrations and JointsNaeem Anwarspecial
10/06/2021FinalCARL HAMANNprogress
10/06/2021Insulation placement and R valuesCARL HAMANNenergy_progress
10/06/2021Lighting in dwelling unitsCARL HAMANNenergy_progress
10/06/2021Lighting controlsCARL HAMANNenergy_progress
10/06/2021Air barrier - visual inspectionCARL HAMANNenergy_progress
07/27/2021Structural Steel - DetailsANDREW RENFROEspecial
07/27/2021Structural Steel - High Strength BoltingANDREW RENFROEspecial
07/27/2021Structural Steel - WeldingANDREW RENFROEspecial
07/27/2021FinalANDREW RENFROEprogress
07/27/2021Post-installed Anchors—special
07/27/2021FinalSteven Kratchmanprogress
07/27/2021Insulation placement and R valuesSteven Kratchmanenergy_progress
07/27/2021Lighting in dwelling unitsSteven Kratchmanenergy_progress
07/27/2021Air barrier - visual inspectionSteven Kratchmanenergy_progress
07/27/2021Lighting controlsSteven Kratchmanenergy_progress
07/27/2021Structural Stability – Alterations of existing buildingsANDREW RENFROEspecial
07/27/2021MasonryANDREW RENFROEspecial
07/27/2021Alternative Materials - OTCR Buildings Bulletin NumberANDREW RENFROEspecial
▾Documents — 68 on file (BIS + DOB NOW)
▸Plans & Drawings11
▸DOB NOWPlans/Sketch8
09/03/2026M00512986-P2Request digital key ↗
09/03/2026M00512986-P3Request digital key ↗
09/03/2026M00512986-P4Request digital key ↗
Showing 3 of 8 on file for this type
▸DOB NOWPlans/Sketch - Structural3
09/03/2026M00250471-P2Request digital key ↗
08/15/2026M00250471-I1Request digital key ↗
08/15/2026M00250471-P1Request digital key ↗
▸Applications & Permits11
▸DOB NOWLPC Approval/Permit9
09/03/2026M00250471-P1Open ↗
09/03/2026M00512986-P2Open ↗
09/03/2026M00512986-P4Open ↗
Showing 3 of 9 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION2
03/03/2014121932686Open ↗
03/03/2014121932686Open ↗
▸Seals & Professional Certifications29
▸DOB NOWDPL-1: Design Professional Seal & Signature11
09/03/2026M00250471-P1Open ↗
09/03/2026M00250471-I1Open ↗
09/03/2026M00512986-P3Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWProgress Inspector Seal & Signature8
08/28/2026M00512986-I1Open ↗
08/28/2026M00512986-I1Open ↗
08/28/2026M00512986-I1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature8
08/28/2026M00512986-P4Open ↗
08/28/2026M00512986-P4Open ↗
08/23/2026M00250471-P1Open ↗
Showing 3 of 8 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION2
03/03/2014121932686Open ↗
03/03/2014121932686Open ↗
▸Trade Schedules & Equipment1
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
03/03/2014121932686Open ↗
▸Safety & Tenant Protection2
▸DOB NOWTenant Protection Plan2
08/15/2026M00250471-I1Open ↗
08/13/2026M00250471-P2Open ↗
▸Environmental & Asbestos5
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form4
09/03/2026M00512986-S1Open ↗
08/15/2026M00512986-I1Open ↗
08/13/2026M00250471-I1Open ↗
Showing 3 of 4 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
03/03/2014121932686Open ↗
▸Energy Compliance1
▸DOB NOWEN2: As Built Energy Analysis.1
08/15/2026M00512986-I1Open ↗
▸Approvals, Objections & Sign-offs4
▸BISLANDMARKS APPROVAL3
09/16/2014121932686Open ↗
06/30/2014121932686Open ↗
03/03/2014121932686Open ↗
▸DOB NOWDEP Variance (V5) letter1
08/13/2026M00250471-I1Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
03/03/2014121932686Open ↗
03/03/2014121932686Open ↗
▸Filing & Intake Forms2
▸BISEFILING COVER SHEET2
03/03/2014121932686Open ↗
03/03/2014121932686Open ↗